NM FLAP 159 Catwalk_Pre-Bid Meeting Presentation.pdf

PDF 10 MB Posted

Attached to
NM FLAP 159(1) Catwalk Access Road
Solicitation number
6982AF23B000019
Issued by

About this file

This presentation outlines the scope of work for the NM FLAP 159(1) Catwalk Access Road project. The project involves replacing 4.8 miles of asphalt surfacing on NM 174, widening sections to 10-foot lanes with 1-foot shoulders, replacing two existing concrete low water crossings of Whitewater Creek, constructing six additional concrete low water crossings on tributary drainages, and raising grades in historically flooded sections. The scope also includes replacing major drainage culverts. Contract requirements include complying with various environmental permits, developing erosion control measures and best practices, conducting nest surveys prior to vegetation removal from March to August, adhering to the Gila National Forest Fire Plan, and meeting a completion date of August 30, 2024 for Schedule A work. The full and open solicitation was advertised with bid opening on July 27, 2023 and intent to award the entire scope of work. Questions regarding Solicitation Number 6982AF23B000019 must be submitted in writing by July 20.

View the file

Other files

Show all 14

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

NM FLAP 159(1)

Catwalk Access Road

Pre-Bid Meeting July 11, 2023

Presentation Outline

• Project Partners

• Project Introduction

• Project Scope Details

• Project Photo Log

• Contract Requirements & Solicitation Notes

• Questions

Project Partners

Design Engineer;

Construction Contract

Administration

Land Management Agency

Roles & Responsibilities

Maintaining Agency

Project Introduction Project Location

Project Location – Schedule A, Option X, Option Y

Purpose and Need

• 2012 Whitewater-Baldy Complex Fire

• 2013 Flood Event and subsequent roadway closure

• Socio-economic Impacts

• Increase resiliency of roadway during flood events

• Provide safe and reliable access to Catwalk Trail

• Improve safety by providing consistent lane widths

Project Scope Details

The project design includes the following elements on NM 174:

• Replacement of 4.8 miles of asphalt surfacing;

• Minor widening, beginning near Milepost 1.0, to provide consistent roadway width (10-foot-wide lanes with 1-foot-wide shoulder);

• Replacement of 2 existing, in-stream, concrete, low water crossings of Whitewater Creek

• Construction of 6 concrete, low water crossings on tributary drainages;

• Minor grade raise of sections of roadway historically prone to flooding;

• and, replacement of major drainage culverts.

Remove and Replace Asphalt, No Widening

Minor Widening (10’ Lanes & 1’ Shoulders), Remove and Replace Asphalt Minor Widening (10’ lanes & 1’ Shoulders), Grade Raise, Remove and Replace Asphalt

Concrete Low Water Crossing Construction or Replacement Culvert Replacement (increased size from existing) & erosion protection

MAP KEY

NM FLAP 159(1) Catwalk Access Road MP

MP

MP

1 Roadway Milepost

NM FLAP 159(1) Catwalk Access Road

MP

Remove and Replace Asphalt, No Widening

Minor Widening (10’ Lanes & 1’ Shoulders), Remove and Replace Asphalt Minor Widening (10’ lanes & 1’ Shoulders), Grade Raise, Remove and Replace Asphalt

Concrete Low Water Crossing Construction or Replacement Culvert Replacement (increased size from existing) & erosion protection

MAP KEY

MP

1 Roadway Milepost

NM FLAP 159(1) Catwalk Access Road

MP

Remove and Replace Asphalt, No Widening

Minor Widening (10’ Lanes & 1’ Shoulders), Remove and Replace Asphalt Minor Widening (10’ lanes & 1’ Shoulders), Grade Raise, Remove and Replace Asphalt

Concrete Low Water Crossing Construction or Replacement Culvert Replacement (increased size from existing) & erosion protection

MAP KEY

NM FLAP 159(1) Catwalk Access Road

MP

Catwalk Trail Parking AreaMP 4.8

Remove and Replace Asphalt, No Widening

Minor Widening (10’ Lanes & 1’ Shoulders), Remove and Replace Asphalt Minor Widening (10’ lanes & 1’ Shoulders), Grade Raise, Remove and Replace Asphalt

Concrete Low Water Crossing Construction or Replacement Culvert Replacement (increased size from existing) & erosion protection

MAP KEY

Schedule A - Typical Section

Schedule A

Option X

Project Photo Log Schedule A – General Conditions

Schedule A – General Conditions, LWC improvements

Schedule A – General Conditions, In-Stream LWC improvement

Option X – Existing LWC Conditions

Option X – Existing LWC Conditions

Option Y – Mill and Fill

Option Y – Mill and Fill

Contract Requirements

• Comply with 401, 404, and Stream Alteration Permit

• Contractor Developed SWPPP and erosion control measures, use BMPs

• Vegetation Clearing and Migratory Birds Impacts – Nest Survey required for vegetation removal between March 1 and August 30

• Comply with Gila NF Fire Plan

• Traffic Control Requirements

• Schedule A Contract Completion Date of August 30, 2024

• No additional contract time for Options X and Y

Solicitation Notes

• Full and Open Advertisement

• Intent is to award full scope of the work

• Bid opening scheduled for July 27, 2023 at 2:00pm MDT.

• Submit all questions in writing to CFLContracts@dot.gov. Deadline to submit questions is July 20, 2023 at 4:00 pm MDT.

mailto:CFLContracts@dot.gov

Questions

Thank you for your interest in this project

Slide Number 1
Slide Number 2
Slide Number 3
Slide Number 4
Slide Number 5
Slide Number 6
Slide Number 7
Slide Number 8
Slide Number 9
Slide Number 10
Slide Number 11
Slide Number 12
Slide Number 13
Slide Number 14
Slide Number 15
Slide Number 16
Slide Number 17
Slide Number 18
Slide Number 19
Slide Number 20
Slide Number 21
Slide Number 22
Slide Number 23
Slide Number 24
Slide Number 25
Slide Number 26
Slide Number 27
Slide Number 28
Slide Number 29
Slide Number 30
Slide Number 31
Slide Number 32
Slide Number 33

File details come from the government source that posted it. Updated .