This document contains a bid tabulation report for a federal contract to replace the Wiggins Creek Bridge in Fremont County, Wyoming. Four contractors submitted bids by the May 16th deadline to remove the existing one-lane bridge and construct a new single-lane modular steel bridge approximately 100 feet long and 29 feet 4 inches wide. The low bid of $4,024,960 was submitted by Responsive Earth Work Solutions. The second lowest bid of $4,126,472.23 came from JM Concrete Inc. The highest bid of $5,262,825 was from Triple A Building Services. The engineer's estimate for the project was $4,480,000. Key work items included mobilization, surveying, excavation, structural and reinforced concrete, prefabricated steel bridge sections, drilled shaft foundations, guardrails, fencing, erosion control, temporary traffic control, and maintaining a road diversion during construction. The contract is anticipated to be awarded by May 25th to the responsive, responsible bidder offering the best value to the Federal Highway Administration and project owner.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Tabulation of Bids Report Date: 05/25/23

1 out of 10

Project No: WY FLAP CR CN10-277(1)

Project Name: Wiggins Creek Bridge

Schedule: A

Schedule Type: Base

Solcitation No: 6982AF23B000018

Division: Central Federal Lands

State: WY County: Fremont

Federal Land: Shoshone National Forest, BLM, Washakie Wilderness and Wind River Reservation Opened at: Lakewood, CO

Opened by: Leslie Karsten

Date: 05/16/23

I certify that this Bid Tabulation accurately reflects the offers received for this solicitation.

Signed: _______________________________

Title: _______________________________

Date: _______________________________

Contract Awarded to: ____________________ Award Date: ____________________

Contractor Comment Bid Amount Responsive

Earth Work Solutions (WY) $4,024,960.00 2506 Little Powder River Road Gillette, WY 82716

JM Concrete Inc. ( $4,126,472.23 ) no 1160 Jones Street Idaho Falls, ID 83401

Jerry Bornhoft Construction, Inc. ( $5,076,900.00 ) no 2787 E Monroe Ave.

Riverton, WY 82501

Triple A Building Services, Inc. $5,262,825.00 410 Grand Ave Suite 307 Laramie, WY 82073

Engineer's Estimate $4,480,000.00

Contracting Officer 05/25/2023

2 out of 10

Project No: WY FLAP CR CN10-277(1)

Project Name: Wiggins Creek Bridge

Schedule: A

Schedule Type: Base

Line Item Pay Item No. Description Quantity Unit Unit Price Amount

Number

A0020 15101-0000 MOBILIZATION

Earth Work Solutions (WY) Lump Sum $667,000.00 JM Concrete Inc. Lump Sum $571,500.00 Jerry Bornhoft Construction, Inc. Lump Sum $245,000.00 Triple A Building Services, Inc. Lump Sum $435,000.00 Engineer's Estimate ALL LPSM Lump Sum $447,913.00

A0040 15214-1000 SURVEY AND STAKING, BRIDGE

Earth Work Solutions (WY) Lump Sum $20,000.00 JM Concrete Inc. Lump Sum $35,000.00 Jerry Bornhoft Construction, Inc. Lump Sum $35,000.00 Triple A Building Services, Inc. Lump Sum $32,000.00 Engineer's Estimate ALL LPSM Lump Sum $25,000.00

A0060 15225-0000 SLOPE, REFERENCE, AND CLEARING AND GRUBBING CONTROL

Earth Work Solutions (WY) $50,000.00 $4,950.00 JM Concrete Inc. $202,020.00 $19,999.98 Jerry Bornhoft Construction, Inc. $250,000.00 $24,750.00 Triple A Building Services, Inc. $400,000.00 $39,600.00 Engineer's Estimate 0.099 MILE $27,000.00 $2,673.00

A0080 15236-2000 SURVEY CONTROL, GRADE FINISHING

Earth Work Solutions (WY) $50,000.00 $9,900.00 JM Concrete Inc. $100,000.00 $19,800.00 Jerry Bornhoft Construction, Inc. $250,000.00 $49,500.00 Triple A Building Services, Inc. $300,000.00 $59,400.00 Engineer's Estimate 0.198 MILE $20,000.00 $3,960.00

A0100 15301-0000 CONTRACTOR QUALITY CONTROL

Earth Work Solutions (WY) Lump Sum $50,000.00 JM Concrete Inc. Lump Sum $20,000.00 Jerry Bornhoft Construction, Inc. Lump Sum $38,000.00 Triple A Building Services, Inc. Lump Sum $100,000.00 Engineer's Estimate ALL LPSM Lump Sum $123,000.00

A0120 15401-0000 CONTRACTOR TESTING

Earth Work Solutions (WY) Lump Sum $50,000.00 JM Concrete Inc. Lump Sum $25,000.00 Jerry Bornhoft Construction, Inc. Lump Sum $35,000.00 Triple A Building Services, Inc. Lump Sum $80,000.00 Engineer's Estimate ALL LPSM Lump Sum $106,000.00

3 out of 10

Project No: WY FLAP CR CN10-277(1)

Project Name: Wiggins Creek Bridge

Schedule: A

Schedule Type: Base

Line Item Pay Item No. Description Quantity Unit Unit Price Amount

Number

A0140 15501-0000 CONSTRUCTION SCHEDULE

Earth Work Solutions (WY) Lump Sum $15,000.00 JM Concrete Inc. Lump Sum $50,000.00 Jerry Bornhoft Construction, Inc. Lump Sum $20,000.00 Triple A Building Services, Inc. Lump Sum $30,000.00 Engineer's Estimate ALL LPSM Lump Sum $11,000.00

A0160 15701-0000 SOIL EROSION CONTROL

Earth Work Solutions (WY) Lump Sum $30,000.00 JM Concrete Inc. Lump Sum $25,000.00 Jerry Bornhoft Construction, Inc. Lump Sum $185,000.00 Triple A Building Services, Inc. Lump Sum $35,000.00 Engineer's Estimate ALL LPSM Lump Sum $40,000.00

A0180 15720-0000 STORM WATER POLLUTION PREVENTION PLAN

Earth Work Solutions (WY) Lump Sum $10,000.00 JM Concrete Inc. Lump Sum $25,000.00 Jerry Bornhoft Construction, Inc. Lump Sum $20,000.00 Triple A Building Services, Inc. Lump Sum $20,000.00 Engineer's Estimate ALL LPSM Lump Sum $7,000.00

A0200 15802-0000 WATERING FOR DUST CONTROL

Earth Work Solutions (WY) Lump Sum $7,500.00 JM Concrete Inc. Lump Sum $25,000.00 Jerry Bornhoft Construction, Inc. Lump Sum $35,000.00 Triple A Building Services, Inc. Lump Sum $28,000.00 Engineer's Estimate ALL LPSM Lump Sum $27,000.00

A0220 20101-0000 CLEARING AND GRUBBING

Earth Work Solutions (WY) $15,000.00 $10,395.00 JM Concrete Inc. $43,250.00 $29,972.25 Jerry Bornhoft Construction, Inc. $93,795.10 $65,000.00 Triple A Building Services, Inc. $25,000.00 $17,325.00 Engineer's Estimate 0.693 ACRE $18,000.00 $12,474.00

A0240 20302-0700 REMOVAL OF FENCE

Earth Work Solutions (WY) $5.00 $3,050.00 JM Concrete Inc. $10.00 $6,100.00 Jerry Bornhoft Construction, Inc. $15.00 $9,150.00 Triple A Building Services, Inc. $5.00 $3,050.00 Engineer's Estimate 610 LNFT $10.00 $6,100.00

4 out of 10

Project No: WY FLAP CR CN10-277(1)

Project Name: Wiggins Creek Bridge

Schedule: A

Schedule Type: Base

Line Item Pay Item No. Description Quantity Unit Unit Price Amount

Number

A0260 20303-1600 REMOVAL OF PAVEMENT, ASPHALT

Earth Work Solutions (WY) $20.00 $13,300.00 JM Concrete Inc. $50.00 $33,250.00 Jerry Bornhoft Construction, Inc. $20.00 $13,300.00 Triple A Building Services, Inc. $20.00 $13,300.00 Engineer's Estimate 665 SQYD $25.00 $16,625.00

A0280 20304-2000 REMOVAL OF BRIDGE

Earth Work Solutions (WY) Lump Sum $100,000.00 JM Concrete Inc. Lump Sum $30,000.00 Jerry Bornhoft Construction, Inc. Lump Sum $250,000.00 Triple A Building Services, Inc. Lump Sum $250,000.00 Engineer's Estimate ALL LPSM Lump Sum $150,000.00

A0300 20420-0000 EMBANKMENT CONSTRUCTION

Earth Work Solutions (WY) $50.00 $35,500.00 JM Concrete Inc. $75.00 $53,250.00 Jerry Bornhoft Construction, Inc. $75.00 $53,250.00 Triple A Building Services, Inc. $250.00 $177,500.00 Engineer's Estimate 710 CUYD $60.00 $42,600.00

A0320 20801-0000 STRUCTURE EXCAVATION

Earth Work Solutions (WY) $60.00 $15,600.00 JM Concrete Inc. $75.00 $19,500.00 Jerry Bornhoft Construction, Inc. $105.00 $27,300.00 Triple A Building Services, Inc. $250.00 $65,000.00 Engineer's Estimate 260 CUYD $200.00 $52,000.00

A0340 20803-0000 STRUCTURAL BACKFILL

Earth Work Solutions (WY) $180.00 $11,340.00 JM Concrete Inc. $125.00 $7,875.00 Jerry Bornhoft Construction, Inc. $210.00 $13,230.00 Triple A Building Services, Inc. $300.00 $18,900.00 Engineer's Estimate 63 CUYD $175.00 $11,025.00

A0360 20815-0000 COFFERDAMS

Earth Work Solutions (WY) Lump Sum $55,000.00 JM Concrete Inc. Lump Sum $120,000.00 Jerry Bornhoft Construction, Inc. Lump Sum $100,000.00 Triple A Building Services, Inc. Lump Sum $75,000.00 Engineer's Estimate ALL LPSM Lump Sum $100,000.00

5 out of 10

Project No: WY FLAP CR CN10-277(1)

Project Name: Wiggins Creek Bridge

Schedule: A

Schedule Type: Base

Line Item Pay Item No. Description Quantity Unit Unit Price Amount

Number

A0380 25101-2400 PLACED RIPRAP, METHOD B, CLASS 4

Earth Work Solutions (WY) $400.00 $65,600.00 JM Concrete Inc. $250.00 $41,000.00 Jerry Bornhoft Construction, Inc. $390.00 $63,960.00 Triple A Building Services, Inc. $350.00 $57,400.00 Engineer's Estimate 164 CUYD $350.00 $57,400.00

A0400 25301-2000 GABIONS, POLYVINYL CHLORIDE COATED

Earth Work Solutions (WY) $240.00 $100,800.00 JM Concrete Inc. $25.00 $10,500.00 Jerry Bornhoft Construction, Inc. $250.00 $105,000.00 Triple A Building Services, Inc. $200.00 $84,000.00 Engineer's Estimate 420 SQFT $115.00 $48,300.00

A0420 25701-0100 CONTRACTOR FURNISHED GABION WALL DESIGN

Earth Work Solutions (WY) Lump Sum $12,500.00 JM Concrete Inc. Lump Sum $10,000.00 Jerry Bornhoft Construction, Inc. Lump Sum $115,000.00 Triple A Building Services, Inc. Lump Sum $10,000.00 Engineer's Estimate ALL LPSM Lump Sum $15,000.00

A0440 30202-2000 ROADWAY AGGREGATE, METHOD 2

Earth Work Solutions (WY) $50.00 $32,000.00 JM Concrete Inc. $125.00 $80,000.00 Jerry Bornhoft Construction, Inc. $135.00 $86,400.00 Triple A Building Services, Inc. $150.00 $96,000.00 Engineer's Estimate 640 TON $85.00 $54,400.00

A0460 55201-0200 STRUCTURAL CONCRETE, CLASS A (AE)

Earth Work Solutions (WY) $1,300.00 $193,700.00 JM Concrete Inc. $2,500.00 $372,500.00 Jerry Bornhoft Construction, Inc. $2,000.00 $298,000.00 Triple A Building Services, Inc. $1,100.00 $163,900.00 Engineer's Estimate 149 CUYD $2,200.00 $327,800.00

A0480 55401-1000 REINFORCING STEEL

Earth Work Solutions (WY) $3.15 $68,355.00 JM Concrete Inc. $3.00 $65,100.00 Jerry Bornhoft Construction, Inc. $3.50 $75,950.00 Triple A Building Services, Inc. $1.50 $32,550.00 Engineer's Estimate 21,700 LB $5.00 $108,500.00

6 out of 10

Project No: WY FLAP CR CN10-277(1)

Project Name: Wiggins Creek Bridge

Schedule: A

Schedule Type: Base

Line Item Pay Item No. Description Quantity Unit Unit Price Amount

Number

A0500 55401-2000 REINFORCING STEEL, EPOXY COATED

Earth Work Solutions (WY) $4.60 $59,800.00 JM Concrete Inc. $5.00 $65,000.00 Jerry Bornhoft Construction, Inc. $3.50 $45,500.00 Triple A Building Services, Inc. $2.00 $26,000.00 Engineer's Estimate 13,000 LB $5.00 $65,000.00

A0520 55504-0000 PRE-FABRICATED STEEL BRIDGE (100'x29'-4" MODULAR STEEL VEHICULAR BRIDGE)

Earth Work Solutions (WY) Lump Sum $1,220,000.00 JM Concrete Inc. Lump Sum $1,775,400.00 Jerry Bornhoft Construction, Inc. Lump Sum $2,000,000.00 Triple A Building Services, Inc. Lump Sum $2,250,000.00 Engineer's Estimate ALL LPSM Lump Sum $1,125,000.00

A0540 55601-0900 BRIDGE RAILING, STEEL (WYDOT TL-3)

Earth Work Solutions (WY) $925.00 $260,850.00 JM Concrete Inc. $300.00 $84,600.00 Jerry Bornhoft Construction, Inc. $500.00 $141,000.00 Triple A Building Services, Inc. $500.00 $141,000.00 Engineer's Estimate 282 LNFT $500.00 $141,000.00

A0560 56501-0300 DRILLED SHAFT, 30-INCH DIAMETER

Earth Work Solutions (WY) $1,400.00 $336,000.00 JM Concrete Inc. $325.00 $78,000.00 Jerry Bornhoft Construction, Inc. $510.00 $122,400.00 Triple A Building Services, Inc. $1,000.00 $240,000.00 Engineer's Estimate 240 LNFT $2,000.00 $480,000.00

A0580 61701-4550 GUARDRAIL SYSTEM MGS, TYPE 2, CLASS A WOOD POSTS

Earth Work Solutions (WY) $200.00 $15,000.00 JM Concrete Inc. $125.00 $9,375.00 Jerry Bornhoft Construction, Inc. $200.00 $15,000.00 Triple A Building Services, Inc. $280.00 $21,000.00 Engineer's Estimate 75 LNFT $170.00 $12,750.00

A0600 61702-1500 TERMINAL SECTION, TYPE MGS TANGENT

Earth Work Solutions (WY) $2,500.00 $10,000.00 JM Concrete Inc. $5,000.00 $20,000.00 Jerry Bornhoft Construction, Inc. $7,000.00 $28,000.00 Triple A Building Services, Inc. $6,000.00 $24,000.00 Engineer's Estimate 4 EACH $8,000.00 $32,000.00

7 out of 10

Project No: WY FLAP CR CN10-277(1)

Project Name: Wiggins Creek Bridge

Schedule: A

Schedule Type: Base

Line Item Pay Item No. Description Quantity Unit Unit Price Amount

Number

A0620 61707-0000 STRUCTURE TRANSITION RAILING

Earth Work Solutions (WY) $50.00 $5,000.00 JM Concrete Inc. $100.00 $10,000.00 Jerry Bornhoft Construction, Inc. $300.00 $30,000.00 Triple A Building Services, Inc. $400.00 $40,000.00 Engineer's Estimate 100 LNFT $325.00 $32,500.00

A0640 61901-0000 FENCE (BUCK AND POLE)

Earth Work Solutions (WY) $30.00 $6,600.00 JM Concrete Inc. $35.00 $7,700.00 Jerry Bornhoft Construction, Inc. $105.00 $23,100.00 Triple A Building Services, Inc. $60.00 $13,200.00 Engineer's Estimate 220 LNFT $120.00 $26,400.00

A0660 61901-0800 FENCE, BARBED WIRE, 3 STRAND

Earth Work Solutions (WY) $20.00 $7,800.00 JM Concrete Inc. $20.00 $7,800.00 Jerry Bornhoft Construction, Inc. $75.00 $29,250.00 Triple A Building Services, Inc. $10.00 $3,900.00 Engineer's Estimate 390 LNFT $12.00 $4,680.00

A0680 62201-0200 DUMP TRUCK, 8 CUBIC YARD MINIMUM CAPACITY

Earth Work Solutions (WY) $125.00 $1,250.00 JM Concrete Inc. $250.00 $2,500.00 Jerry Bornhoft Construction, Inc. $195.00 $1,950.00 Triple A Building Services, Inc. $220.00 $2,200.00 Engineer's Estimate 10 HOUR $285.00 $2,850.00

A0700 62201-0950 WHEEL LOADER, 3 CUBIC YARD MINIMUM RATED CAPACITY

Earth Work Solutions (WY) $160.00 $1,600.00 JM Concrete Inc. $500.00 $5,000.00 Jerry Bornhoft Construction, Inc. $235.00 $2,350.00 Triple A Building Services, Inc. $195.00 $1,950.00 Engineer's Estimate 10 HOUR $300.00 $3,000.00

A0720 62201-2850 MOTOR GRADER, 12 FOOT MINIMUM BLADE

Earth Work Solutions (WY) $160.00 $1,600.00 JM Concrete Inc. $500.00 $5,000.00 Jerry Bornhoft Construction, Inc. $235.00 $2,350.00 Triple A Building Services, Inc. $200.00 $2,000.00 Engineer's Estimate 10 HOUR $300.00 $3,000.00

8 out of 10

Project No: WY FLAP CR CN10-277(1)

Project Name: Wiggins Creek Bridge

Schedule: A

Schedule Type: Base

Line Item Pay Item No. Description Quantity Unit Unit Price Amount

Number

A0740 62301-0000 GENERAL LABOR

Earth Work Solutions (WY) $60.00 $2,400.00 JM Concrete Inc. $85.00 $3,400.00 Jerry Bornhoft Construction, Inc. $97.00 $3,880.00 Triple A Building Services, Inc. $35.00 $1,400.00 Engineer's Estimate 40 HOUR $95.00 $3,800.00

A0760 62302-1000 SPECIAL LABOR, HIRED TECHNICAL SERVICES

Earth Work Solutions (WY) $200.00 $2,000.00 JM Concrete Inc. $250.00 $2,500.00 Jerry Bornhoft Construction, Inc. $400.00 $4,000.00 Triple A Building Services, Inc. $65.00 $650.00 Engineer's Estimate 10 HOUR $285.00 $2,850.00

A0780 62302-1100 SPECIAL LABOR, HIRED SURVEY SERVICES

Earth Work Solutions (WY) $250.00 $2,500.00 JM Concrete Inc. $250.00 $2,500.00 Jerry Bornhoft Construction, Inc. $400.00 $4,000.00 Triple A Building Services, Inc. $350.00 $3,500.00 Engineer's Estimate 10 HOUR $295.00 $2,950.00

A0800 62405-0300 PLACING CONSERVED TOPSOIL, 4-INCH DEPTH

Earth Work Solutions (WY) $7.00 $8,050.00 JM Concrete Inc. $18.00 $20,700.00 Jerry Bornhoft Construction, Inc. $45.00 $51,750.00 Triple A Building Services, Inc. $20.00 $23,000.00 Engineer's Estimate 1,150 SQYD $7.00 $8,050.00

A0820 62511-2000 SEEDING, HYDRAULIC METHOD

Earth Work Solutions (WY) $4.00 $5,200.00 JM Concrete Inc. $10.00 $13,000.00 Jerry Bornhoft Construction, Inc. $8.00 $10,400.00 Triple A Building Services, Inc. $5.00 $6,500.00 Engineer's Estimate 1,300 SQYD $6.00 $7,800.00

A0840 62516-2000 MULCHING, HYDRAULIC METHOD

Earth Work Solutions (WY) $8.00 $10,400.00 JM Concrete Inc. $5.00 $6,500.00 Jerry Bornhoft Construction, Inc. $9.00 $11,700.00 Triple A Building Services, Inc. $5.00 $6,500.00 Engineer's Estimate 1,300 SQYD $5.00 $6,500.00

9 out of 10

Project No: WY FLAP CR CN10-277(1)

Project Name: Wiggins Creek Bridge

Schedule: A

Schedule Type: Base

Line Item Pay Item No. Description Quantity Unit Unit Price Amount

Number

A0860 62901-1000 ROLLED EROSION CONTROL PRODUCT, TYPE 3.B

Earth Work Solutions (WY) $7.00 $14,000.00 JM Concrete Inc. $5.00 $10,000.00 Jerry Bornhoft Construction, Inc. $9.50 $19,000.00 Triple A Building Services, Inc. $4.00 $8,000.00 Engineer's Estimate 2,000 SQYD $8.00 $16,000.00

A0880 63308-3000 OBJECT MARKER, TYPE 3

Earth Work Solutions (WY) $1,000.00 $4,000.00 JM Concrete Inc. $1,000.00 $4,000.00 Jerry Bornhoft Construction, Inc. $900.00 $3,600.00 Triple A Building Services, Inc. $300.00 $1,200.00 Engineer's Estimate 4 EACH $950.00 $3,800.00

A0900 63501-2000 TEMPORARY TRAFFIC CONTROL, TRAFFIC SIGNAL SYSTEM

Earth Work Solutions (WY) Lump Sum $100,000.00 JM Concrete Inc. Lump Sum $50,000.00 Jerry Bornhoft Construction, Inc. Lump Sum $95,000.00 Triple A Building Services, Inc. Lump Sum $110,000.00 Engineer's Estimate ALL LPSM Lump Sum $62,500.00

A0920 63502-0600 TEMPORARY TRAFFIC CONTROL, BARRICADE TYPE 3

Earth Work Solutions (WY) $1,000.00 $2,000.00 JM Concrete Inc. $2,500.00 $5,000.00 Jerry Bornhoft Construction, Inc. $900.00 $1,800.00 Triple A Building Services, Inc. $2,500.00 $5,000.00 Engineer's Estimate 2 EACH $825.00 $1,650.00

A0940 63502-1300 TEMPORARY TRAFFIC CONTROL, DRUM

Earth Work Solutions (WY) $300.00 $7,500.00 JM Concrete Inc. $250.00 $6,250.00 Jerry Bornhoft Construction, Inc. $792.00 $19,800.00 Triple A Building Services, Inc. $200.00 $5,000.00 Engineer's Estimate 25 EACH $170.00 $4,250.00

A0960 63502-1600 TEMPORARY TRAFFIC CONTROL, WARNING LIGHT TYPE B

Earth Work Solutions (WY) $1,000.00 $4,000.00 JM Concrete Inc. $5,000.00 $20,000.00 Jerry Bornhoft Construction, Inc. $900.00 $3,600.00 Triple A Building Services, Inc. $200.00 $800.00 Engineer's Estimate 4 EACH $220.00 $880.00

10 out of 10

Project No: WY FLAP CR CN10-277(1)

Project Name: Wiggins Creek Bridge

Schedule: A

Schedule Type: Base

Line Item Pay Item No. Description Quantity Unit Unit Price Amount

Number

A0980 63502-3900 TEMPORARY TRAFFIC CONTROL, CONSTRUCTION SIGN

Earth Work Solutions (WY) $500.00 $8,000.00 JM Concrete Inc. $1,000.00 $16,000.00 Jerry Bornhoft Construction, Inc. $2,100.00 $33,600.00 Triple A Building Services, Inc. $650.00 $10,400.00 Engineer's Estimate 16 EACH $125.00 $2,000.00

A1000 63503-0400 TEMPORARY TRAFFIC CONTROL, CONCRETE BARRIER

Earth Work Solutions (WY) $50.00 $43,000.00 JM Concrete Inc. $125.00 $107,500.00 Jerry Bornhoft Construction, Inc. $95.00 $81,700.00 Triple A Building Services, Inc. $100.00 $86,000.00 Engineer's Estimate 860 LNFT $150.00 $129,000.00

A1020 63503-1000 TEMPORARY TRAFFIC CONTROL, PLASTIC FENCE

Earth Work Solutions (WY) $6.00 $4,020.00 JM Concrete Inc. $20.00 $13,400.00 Jerry Bornhoft Construction, Inc. $14.00 $9,380.00 Triple A Building Services, Inc. $10.00 $6,700.00 Engineer's Estimate 670 LNFT $6.00 $4,020.00

A1040 65001-1000 CONSTRUCT AND MAINTAIN DIVERSION

Earth Work Solutions (WY) Lump Sum $300,900.00 JM Concrete Inc. Lump Sum $80,000.00 Jerry Bornhoft Construction, Inc. Lump Sum $320,000.00 Triple A Building Services, Inc. Lump Sum $300,000.00 Engineer's Estimate ALL LPSM Lump Sum $500,000.00

Total Schedule - All Items

Earth Work Solutions (WY) $4,024,960.00 JM Concrete Inc. $4,126,472.23 Jerry Bornhoft Construction, Inc. $5,076,900.00 Triple A Building Services, Inc. $5,262,825.00 Engineer's Estimate $4,480,000.00

File details come from the government source that posted it. Updated .