This bid opening summary documents the bids received for the Canyon Rims Road project. TNT General Contractors submitted the lowest bid totaling $7,710,827.65 for Schedule A, Option X, and Option Y. Staker Parsons dba Nielson Construction & Materials bid $8,128,000.06 and Steve Manning Construction, Inc. bid $9,692,311.00. The engineer's estimate was $8,670,775.80. The project involves rehabilitating, restoring, and resurfacing 9.28 miles of Needles Overlook Road including pavement patching, chip sealing, full depth reclamation and pavement overlay. Option X extends this work an additional 1.52 miles and Option Y constructs a turn lane and acceleration/deceleration lanes on US 191. The solicitation was issued by the Department of Transportation Federal Highway Administration to improve public access and safety at the Canyon Rims Special Recreation Management Area in Utah.

View the file

Other files

Show all 12

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Bid Opening Summary

Project Name: Canyon Rims Road Project Number: UT FTBL 7133(1) Bid Opening Date: 4/6/2023 Time: 2:00 p.m. MST Bid Opening Location: Lakewood, CO Bid Opening Officer: Jorey Deml

Amendments: (1) 4/4/23

Bidder’s Name Schedule A Option X Option Y BID TOTAL

1. TNT General

Contractors Nephi, UT

$3,687,185.50 $1,310,121.50 $2,713,520.65 $7,710,827.65

2. Staker Parsons dba Nielson Construction & Materials

$4,454,317.04 $1,137,639.51 $2,536,043.51 $8,128,000.06

3. Steve Manning Construction, Inc.

$4,361,639.00 $1,528,084.00 $3,802,588.00 $9,692,311.00

Engineer’s Estimate

$3,786,853.00 $1,072,484.80 $3,811,438.00 $8,670,775.80