QnA 1.6.23.pdf

PDF 142 KB Posted

Attached to
KS FLAP KIN 50(1) Cheney Reservoir Access Road
Solicitation number
6982AF22B000035
Issued by

About this file

This document contains questions and answers from an advertisement for a federal-aid highway project located in Kingman County, Kansas. The project involves rehabilitating 2.0 miles of RS 607 (NE 50 St) from RS 1428 (NE 150 Ave) east to the Kingsman County Line (N 407th St W) to improve public access to Cheney State Park and Cheney Reservoir. The scope of work includes widening the roadway to provide 26' from edge of pavement to edge of pavement plus 4' gravel shoulders on each side for the length of the project, as well as a 2.5" asphalt concrete overlay of the existing roadway. Questions addressed taxation requirements, temporary traffic control options, the acceptability of a previously approved local asphalt mix design, qualifications for quality control personnel, and the acceptability of ASTM test methods in place of AASHTO standards.

View the file

Other files

File Type Posted
Tabulation of Bids KS FLAP KIN 50(1).pdf PDF
Bid Opening Summary KS FLAP KIN 50(1).pdf PDF
A002.pdf PDF
QnA 12.22.22 Cheney.pdf PDF
A001 Cheney.pdf PDF
QnA 12.15.22.pdf PDF
KS FLAP 50(1) KIN 100 Plans_Sealed_Signed.pdf PDF
6982AF22B000035.pdf PDF
FP-14.pdf PDF
KS FLAP KIN 50(1) 100 Final Pavement Report rev.pdf PDF
KS FLAP KIN 50(1) 100 Drainage Design Report rev.pdf PDF
Show all 11

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Questions and Answers during Advertisement for KS FLAP KIN50(1) Cheney Reservoir Access

January 6, 2023

Questions Answers 1 Is this project tax exempt? Refer to clause 52.229-3 Federal, State, and Local Taxes on sheet C-12 of the IFB.

2 Will use of temporary traffic signals be allowed rather than use of flaggers?

Submit a traffic control plan in accordance with Section 104, 156, and 635 of the FP and SCR’s, MUTCD, and Sheet T9 of the plans for approval by the CO in coordination with the project partners. Note 4 on Sheet T9 states “CO to close only portion of roadway where work will be performed.

Construction zone may move each day.”

3 Our paving contractor is requesting using a previously approved KDOT asphalt mix design used in Kingman County, KS on K-42 Hwy. Would this be acceptable?

Per FP-14 403.02(a), A KDOT mix approved for use in the last 12 months may be used. Table 403-1 can be disregarded if it conflicts with state DOT standards.

4 Is the QC person is required to have a NICET III in highway materials? We don’t see a lot of NICET in this region. Are KDOT equivalents acceptable?

Per SCR section 153.02(a)(1)(b), an equivalent certification would be considered.

5 The testing charts from the spec book are calling for AASHTO standards primarily. GSI, as well as the other 2 big firms in Wichita use ASTM’s, or rather are certified by the AASHTO organization in ASTM test methods. Are ASTM test methods acceptable?

AASHTO standards are used on all CFL projects.