This document contains questions and answers from a pre-bid meeting for a federal transportation project. The project involves reconstructing roads and constructing asphalt and concrete trails as well as a pedestrian bridge over a railroad in Pueblo West, Colorado. No pre-bid conference was held and the opportunity is full and open competition with HUBZone price preference. Only bridge railing needs environmental stain and existing guardrail will be removed and reset. The contractor takes ownership of removed asphalt and flagging costs for work near the railroad will be paid directly by the agency. Standard warranties apply but there is no separate project warranty. Electronic CAD files and bollards are not provided. EEBACS training is required but there is no cost for participation. The anticipated notice to proceed date refers to standard FAR clauses and any project extension would require an amendment.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Questions and Answers during Advertisement for CO FLAP PUW16(1) Nichols Road
September 22, 2022
Questions Answers 1 Will there be a pre-bid conference for this opportunity? No, a pre-bid conference will not be held.
2 Can you tell me what the set-Aside is for this Project?
This project is Full and Open Competition with HUBZone price preference, please refer to the cover page of the solicitation and Clause 52.219-4 starting on page C-4 of the solicitation.
3 Ref: page E-52 - Treat all galvanized material for guardrail systems with a weathering agent according to Section 563. Does weathering agent mean “environmental stain”? Section 563 appears to be painting, does this section include environmental stain (Natina)? Is guardrail to be painted or stained?
Please refer to the SCR changes in Amendment A001. The only item to be painted with Natina is item 55601-0900 Bridge Railing, Steel.
4 Ref: page E-62 – Where is the information from Task Force 13 Guide to Standardized Roadside Safety Hardware related to the guardrail? I am not seeing this included in the project documents.
Please refer to the SCR changes in Amendment A001. New guardrail is not proposed. Proposed improvements will remove & reset existing guardrail.
Here is the link to the Task Force 13 guide: TF13 Hardware Guide Home (tf13guides.org)
5 After removal of the existing asphalt, please confirm if the contractor takes ownership of the material or another agency? If another agency is to take possession of the material is there a requirement on sizing?
The contractor will take ownership of the removed material. Remove the material from the project according to SCR subsection 203.05(a).
6 What is the anticipated date to receive an NTP? Is there a possibility to get a Purchase Order and/or Task Order sooner so that long lead items can be ordered?
Refer to FAR 52.211-10 Commencement, Prosecution, and Completion of Work. (APR 1984) Alternate I (APR 1984) on page C-3 for the Notice to Proceed date.
A purchase order or task order will not be done prior to the Notice to Proceed.
7 We are seeing extended lead times currently on prefabricated structures. The last pedestrian bridge of this nature caused significant issues with scheduling. In the event this item takes
Refer to Amendment A001 Section 108 of the SCR’s. Please bid the project according to the anticipated NTP date in FAR 52.211-10 and revised completion date in Section 108 of the SCR’s in Amendment A001.
https://tf13guides.org/Guides/ https://tf13guides.org/Guides/ longer to design, engineer, and fabricate, is there a possibility for an extension?
8 Can CAD files be provided prior to bid for takeoff comparison?
No, electronic CAD files will not be provided.
9 Confirming that flaggers for work on/near the railroad will be invoiced and paid directly through CPW and the contractor is not to include this price in their bid?
Correct. See SCR Subsection 107.04(b).
10 Is there a cost associated with the EEBACS Training that is required for the contractor?
No, only the contractor’s time to participate.
11 What is the warranty period?
The only warranty is manufacturer’s warranties associated with their proprietary products (for example see SCR 636.06 (c)).
There is no warranty period for the project.
12 Section 601 states all Minor Concrete is to be Harvest Gold, except around the removable bollards. Can you verify there are bollards to be installed as I am unable to locate these and there is no pay item for them?
No bollards are to be installed. These references have been removed from the Section 601 of the SCR’s. Refer to Amendment A001.
13 As part of the bid package, a submittal of document A-23 Hazardous Materials is to be included. Is this to include fuel, grease, oil, and etc. from heavy equipment or is this just for stored/delivered materials on-site, how detailed of a list needs to be provided?
Please refer to FAR Clause 52.223-3 Hazardous Material Identification and Material Safety Data for instructions on what materials to include in the list.