BID TABS 6982AF22B000020 AZ NV BR LCDO HOOVER PARKING.pdf
PDF 773 KB Posted
- Attached to
- AZ/NV BR LCDO Hoover Dam Parking Lot Rehab
- Solicitation number
- 6982AF22B000020
About this file
This bid tabulation report summarizes bids received for the AZ/NV BR LCDO Hoover Dam Parking Lot Rehab project. The project involves pavement preservation for 17 parking lots along the Hoover Dam Access Road, including full depth patching, crack sealing, surface treatment, permanent pavement markings, permanent signing, and slope failure repair. Key details include CKC Operations LLC providing the lowest bid of $1,074,113.17, while the engineer's estimate was $1,250,000. Other bidders were C&C Contracting, Inc. at $1,429,720.00, Construction Solutions Group, LLC at $1,516,997.76, Bookcliff Partners at $1,774,113.17, Cutting Edge Contractors, Inc. at $1,796,858.41, and V.C.I. Victor Construction, Inc. at $1,899,726.00. The solicitation number is 6982AF22B000020 and involves work items such as 48,500 square yards of fog seal and 4.2 miles of cleaning and sealing cracks. The project magnitude is estimated between $700,000 to $2,000,000.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Tabulation of Bids Report Date: 10/13/22
1 out of 9Source Selection Information - See FAR 2.101 & 3.104
Project No: AZ/NV BR LCDO HOOVER PARKING
Project Name: Hoover Dam Parking lots Rehab
Schedule: A
Schedule Type: Base
Solcitation No: 6982AF22B000020
Division: Central Federal Lands
State: AZ, NV County: Mohave, Clark
Federal Land: BOR Opened at: Lakewood CO
Opened by: Sheri Walsh
Date: 10/12/22
I certify that this Bid Tabulation accurately reflects the offers received for this solicitation.
Signed: _______________________________
Title: _______________________________
Date: _______________________________
Contract Awarded to: ____________________ Award Date: ____________________
Contractor Comment Bid Amount Responsive
CKC Operations LLC $1,074,113.17 3843 South Highway 40 Roosevelt, UT 84066
C&C Contracting, Inc $1,429,720.00 25 Stanford Place Monclair, NJ 07042
Construction Solutions Group, LLC $1,516,997.76 5512 Elk Valley Estates Dr St. Louis, MO 63128
Bookcliff Partners $1,774,113.17 2301 West 440 South Roosevelt, UT 84066
Cutting Edge Contractors, Inc $1,796,858.41 44 Harbor Pines Ct Las Vegas, NV 89183
V.C.I. Victor Construction, Inc $1,899,726.00 14118 Meridian Parkway Riverside , CA 92518
Engineer's Estimate $1,250,000.00
2 out of 9Source Selection Information - See FAR 2.101 & 3.104
Project No: AZ/NV BR LCDO HOOVER PARKING
Project Name: Hoover Dam Parking lots Rehab
Schedule: A
Schedule Type: Base
Line Item Pay Item No. Description Quantity Unit Unit Price Amount
Number
A0020 15101-0000 MOBILIZATION
CKC Operations LLC Lump Sum $218,090.73 C&C Contracting, Inc Lump Sum $150,000.00 Construction Solutions Group, LLC Lump Sum $197,600.00 Bookcliff Partners Lump Sum $568,090.73 Cutting Edge Contractors, Inc Lump Sum $254,851.60 V.C.I. Victor Construction, Inc Lump Sum $260,000.00 Engineer's Estimate ALL LPSM Lump Sum $151,325.00
A0040 15301-0000 CONTRACTOR QUALITY CONTROL
CKC Operations LLC Lump Sum $101,980.62 C&C Contracting, Inc Lump Sum $140,000.00 Construction Solutions Group, LLC Lump Sum $200,000.00 Bookcliff Partners Lump Sum $451,980.62 Cutting Edge Contractors, Inc Lump Sum $59,616.00 V.C.I. Victor Construction, Inc Lump Sum $250,000.00 Engineer's Estimate ALL LPSM Lump Sum $50,000.00
A0060 15401-0000 CONTRACTOR TESTING
CKC Operations LLC Lump Sum $16,996.77 C&C Contracting, Inc Lump Sum $34,000.00 Construction Solutions Group, LLC Lump Sum $32,000.00 Bookcliff Partners Lump Sum $16,996.77 Cutting Edge Contractors, Inc Lump Sum $14,904.00 V.C.I. Victor Construction, Inc Lump Sum $85,000.00 Engineer's Estimate ALL LPSM Lump Sum $50,000.00
A0080 15501-0000 CONSTRUCTION SCHEDULE
CKC Operations LLC Lump Sum $8,498.38 C&C Contracting, Inc Lump Sum $3,000.00 Construction Solutions Group, LLC Lump Sum $47,000.00 Bookcliff Partners Lump Sum $8,498.38 Cutting Edge Contractors, Inc Lump Sum $14,754.96 V.C.I. Victor Construction, Inc Lump Sum $100,000.00 Engineer's Estimate ALL LPSM Lump Sum $10,000.00
A0100 20301-2400 REMOVAL OF SIGN
CKC Operations LLC $100.00 $10,000.00 C&C Contracting, Inc $130.00 $13,000.00 Construction Solutions Group, LLC $102.00 $10,200.00 Bookcliff Partners $100.00 $10,000.00 Cutting Edge Contractors, Inc $243.30 $24,330.00 V.C.I. Victor Construction, Inc $220.00 $22,000.00 Engineer's Estimate 100 EACH $175.00 $17,500.00
3 out of 9Source Selection Information - See FAR 2.101 & 3.104
Project No: AZ/NV BR LCDO HOOVER PARKING
Project Name: Hoover Dam Parking lots Rehab
Schedule: A
Schedule Type: Base
Line Item Pay Item No. Description Quantity Unit Unit Price Amount
Number
A0120 20304-1000 REMOVAL OF STRUCTURES AND OBSTRUCTIONS
CKC Operations LLC Lump Sum $15,000.00 C&C Contracting, Inc Lump Sum $32,000.00 Construction Solutions Group, LLC Lump Sum $42,000.00 Bookcliff Partners Lump Sum $15,000.00 Cutting Edge Contractors, Inc Lump Sum $13,570.09 V.C.I. Victor Construction, Inc Lump Sum $74,000.00 Engineer's Estimate ALL LPSM Lump Sum $15,000.00
A0140 20420-0000 EMBANKMENT CONSTRUCTION
CKC Operations LLC $144.47 $1,444.70 C&C Contracting, Inc $1,500.00 $15,000.00 Construction Solutions Group, LLC $1,620.00 $16,200.00 Bookcliff Partners $144.47 $1,444.70 Cutting Edge Contractors, Inc $6,233.60 $62,336.00 V.C.I. Victor Construction, Inc $5,900.00 $59,000.00 Engineer's Estimate 10 CUYD $100.00 $1,000.00
A0160 25101-0100 PLACED RIPRAP, METHOD A, CLASS 1 (Barrier Rock)
CKC Operations LLC $280.45 $119,191.25 C&C Contracting, Inc $400.00 $170,000.00 Construction Solutions Group, LLC $249.47 $106,024.75 Bookcliff Partners $280.45 $119,191.25 Cutting Edge Contractors, Inc $455.40 $193,545.00 V.C.I. Victor Construction, Inc $1,075.00 $456,875.00 Engineer's Estimate 425 CUYD $200.00 $85,000.00
A0180 25201-1000 SPECIAL ROCK EMBANKMENT, MECHANICALLY-PLACED
CKC Operations LLC $101.98 $4,079.20 C&C Contracting, Inc $1,500.00 $60,000.00 Construction Solutions Group, LLC $1,018.39 $40,735.60 Bookcliff Partners $101.98 $4,079.20 Cutting Edge Contractors, Inc $670.68 $26,827.20 V.C.I. Victor Construction, Inc $2,000.00 $80,000.00 Engineer's Estimate 40 CUYD $300.00 $12,000.00
A0200 41402-2000 CRACKS, CLEANING AND SEALING
CKC Operations LLC $7,478.58 $28,044.68 C&C Contracting, Inc $10,000.00 $37,500.00 Construction Solutions Group, LLC $35,664.84 $133,743.15 Bookcliff Partners $7,478.58 $28,044.68 Cutting Edge Contractors, Inc $69,528.96 $260,733.60 V.C.I. Victor Construction, Inc $13,000.00 $48,750.00 Engineer's Estimate 3.75 MILE $40,000.00 $150,000.00
4 out of 9Source Selection Information - See FAR 2.101 & 3.104
Project No: AZ/NV BR LCDO HOOVER PARKING
Project Name: Hoover Dam Parking lots Rehab
Schedule: A
Schedule Type: Base
Line Item Pay Item No. Description Quantity Unit Unit Price Amount
Number
A0220 41801-2000 ASPHALT CONCRETE PAVEMENT PATCH, TYPE 2
CKC Operations LLC $917.83 $183,566.00 C&C Contracting, Inc $200.00 $40,000.00 Construction Solutions Group, LLC $249.67 $49,934.00 Bookcliff Partners $917.83 $183,566.00 Cutting Edge Contractors, Inc $370.56 $74,112.00 V.C.I. Victor Construction, Inc $650.00 $130,000.00 Engineer's Estimate 200 SQYD $300.00 $60,000.00
A0240 42201-0000 SEAL COAT
CKC Operations LLC $2.31 $122,430.00 C&C Contracting, Inc $4.00 $212,000.00 Construction Solutions Group, LLC $3.93 $208,290.00 Bookcliff Partners $2.31 $122,430.00 Cutting Edge Contractors, Inc $5.54 $293,620.00 V.C.I. Victor Construction, Inc $1.75 $92,750.00 Engineer's Estimate 53,000 SQYD $5.00 $265,000.00
A0260 60915-1000 WHEELSTOP, CONCRETE
CKC Operations LLC $212.46 $3,186.90 C&C Contracting, Inc $165.00 $2,475.00 Construction Solutions Group, LLC $113.40 $1,701.00 Bookcliff Partners $212.46 $3,186.90 Cutting Edge Contractors, Inc $290.63 $4,359.45 V.C.I. Victor Construction, Inc $150.00 $2,250.00 Engineer's Estimate 15 EACH $225.00 $3,375.00
A0280 61401-0000 LEAN CONCRETE BACKFILL
CKC Operations LLC $169.97 $1,699.70 C&C Contracting, Inc $1,000.00 $10,000.00 Construction Solutions Group, LLC $463.68 $4,636.80 Bookcliff Partners $169.97 $1,699.70 Cutting Edge Contractors, Inc $933.14 $9,331.40 V.C.I. Victor Construction, Inc $600.00 $6,000.00 Engineer's Estimate 10 CUYD $2,500.00 $25,000.00
A0300 62201-0100 DUMP TRUCK, 6 CUBIC YARD MINIMUM CAPACITY
CKC Operations LLC $132.60 $1,326.00 C&C Contracting, Inc $220.00 $2,200.00 Construction Solutions Group, LLC $216.00 $2,160.00 Bookcliff Partners $132.60 $1,326.00 Cutting Edge Contractors, Inc $229.31 $2,293.10 V.C.I. Victor Construction, Inc $80.00 $800.00 Engineer's Estimate 10 HOUR $165.00 $1,650.00
5 out of 9Source Selection Information - See FAR 2.101 & 3.104
Project No: AZ/NV BR LCDO HOOVER PARKING
Project Name: Hoover Dam Parking lots Rehab
Schedule: A
Schedule Type: Base
Line Item Pay Item No. Description Quantity Unit Unit Price Amount
Number
A0320 62201-3000 HYDRAULIC EXCAVATOR
CKC Operations LLC $195.46 $1,954.60 C&C Contracting, Inc $350.00 $3,500.00 Construction Solutions Group, LLC $270.00 $2,700.00 Bookcliff Partners $195.46 $1,954.60 Cutting Edge Contractors, Inc $298.52 $2,985.20 V.C.I. Victor Construction, Inc $80.00 $800.00 Engineer's Estimate 10 HOUR $275.00 $2,750.00
A0340 62301-0000 GENERAL LABOR
CKC Operations LLC $84.98 $3,399.20 C&C Contracting, Inc $110.00 $4,400.00 Construction Solutions Group, LLC $189.00 $7,560.00 Bookcliff Partners $84.98 $3,399.20 Cutting Edge Contractors, Inc $96.26 $3,850.40 V.C.I. Victor Construction, Inc $55.00 $2,200.00 Engineer's Estimate 40 HOUR $100.00 $4,000.00
A0360 62302-1000 SPECIAL LABOR, HIRED TECHNICAL SERVICES
CKC Operations LLC $310.38 $3,103.80 C&C Contracting, Inc $155.00 $1,550.00 Construction Solutions Group, LLC $324.00 $3,240.00 Bookcliff Partners $310.38 $3,103.80 Cutting Edge Contractors, Inc $248.40 $2,484.00 V.C.I. Victor Construction, Inc $70.00 $700.00 Engineer's Estimate 10 HOUR $285.00 $2,850.00
A0380 63301-0000 SIGN SYSTEM (FLASHING LIGHT BEACON)
CKC Operations LLC $750.00 $1,500.00 C&C Contracting, Inc $8,300.00 $16,600.00 Construction Solutions Group, LLC $5,810.40 $11,620.80 Bookcliff Partners $750.00 $1,500.00 Cutting Edge Contractors, Inc $9,160.37 $18,320.74 V.C.I. Victor Construction, Inc $1,600.00 $3,200.00 Engineer's Estimate 2 EACH $5,000.00 $10,000.00
A0400 63301-0000 SIGN SYSTEM
CKC Operations LLC $510.00 $35,700.00 C&C Contracting, Inc $2,000.00 $140,000.00 Construction Solutions Group, LLC $1,603.80 $112,266.00 Bookcliff Partners $510.00 $35,700.00 Cutting Edge Contractors, Inc $2,487.11 $174,097.70 V.C.I. Victor Construction, Inc $500.00 $35,000.00 Engineer's Estimate 70 EACH $800.00 $56,000.00
6 out of 9Source Selection Information - See FAR 2.101 & 3.104
Project No: AZ/NV BR LCDO HOOVER PARKING
Project Name: Hoover Dam Parking lots Rehab
Schedule: A
Schedule Type: Base
Line Item Pay Item No. Description Quantity Unit Unit Price Amount
Number
A0420 63301-0000 SIGN SYSTEM (PANEL)
CKC Operations LLC $510.00 $15,300.00 C&C Contracting, Inc $390.00 $11,700.00 Construction Solutions Group, LLC $280.80 $8,424.00 Bookcliff Partners $510.00 $15,300.00 Cutting Edge Contractors, Inc $646.46 $19,393.80 V.C.I. Victor Construction, Inc $900.00 $27,000.00 Engineer's Estimate 30 EACH $800.00 $24,000.00
A0440 63308-3000 OBJECT MARKER, TYPE 3
CKC Operations LLC $45.90 $183.60 C&C Contracting, Inc $220.00 $880.00 Construction Solutions Group, LLC $156.60 $626.40 Bookcliff Partners $45.90 $183.60 Cutting Edge Contractors, Inc $926.84 $3,707.36 V.C.I. Victor Construction, Inc $300.00 $1,200.00 Engineer's Estimate 4 EACH $500.00 $2,000.00
A0460 63309-0100 DELINEATOR, TYPE 1
CKC Operations LLC $78.00 $780.00 C&C Contracting, Inc $110.00 $1,100.00 Construction Solutions Group, LLC $81.00 $810.00 Bookcliff Partners $78.00 $780.00 Cutting Edge Contractors, Inc $194.87 $1,948.70 V.C.I. Victor Construction, Inc $100.00 $1,000.00 Engineer's Estimate 10 EACH $100.00 $1,000.00
A0480 63310-0000 CHANNELIZING DEVICE (YELLOW)
CKC Operations LLC $76.49 $1,147.35 C&C Contracting, Inc $90.00 $1,350.00 Construction Solutions Group, LLC $64.80 $972.00 Bookcliff Partners $76.49 $1,147.35 Cutting Edge Contractors, Inc $144.82 $2,172.30 V.C.I. Victor Construction, Inc $100.00 $1,500.00 Engineer's Estimate 15 EACH $100.00 $1,500.00
A0500 63310-0000 CHANNELIZING DEVICE (WHITE)
CKC Operations LLC $76.49 $6,501.65 C&C Contracting, Inc $90.00 $7,650.00 Construction Solutions Group, LLC $64.80 $5,508.00 Bookcliff Partners $76.49 $6,501.65 Cutting Edge Contractors, Inc $99.19 $8,431.15 V.C.I. Victor Construction, Inc $100.00 $8,500.00 Engineer's Estimate 85 EACH $100.00 $8,500.00
7 out of 9Source Selection Information - See FAR 2.101 & 3.104
Project No: AZ/NV BR LCDO HOOVER PARKING
Project Name: Hoover Dam Parking lots Rehab
Schedule: A
Schedule Type: Base
Line Item Pay Item No. Description Quantity Unit Unit Price Amount
Number
A0520 63402-0300 PAVEMENT MARKINGS, TYPE B, SOLID
CKC Operations LLC $3,922.33 $50,990.29 C&C Contracting, Inc $3,800.00 $49,400.00 Construction Solutions Group, LLC $2,764.80 $35,942.40 Bookcliff Partners $3,922.33 $50,990.29 Cutting Edge Contractors, Inc $5,418.17 $70,436.21 V.C.I. Victor Construction, Inc $3,500.00 $45,500.00 Engineer's Estimate 13.00 MILE $2,500.00 $32,500.00
A0540 63402-0500 PAVEMENT MARKINGS, TYPE C, SOLID
CKC Operations LLC $2,037.08 $1,018.54 C&C Contracting, Inc $6,000.00 $3,000.00 Construction Solutions Group, LLC $4,357.80 $2,178.90 Bookcliff Partners $2,037.08 $1,018.54 Cutting Edge Contractors, Inc $8,584.70 $4,292.35 V.C.I. Victor Construction, Inc $4,500.00 $2,250.00 Engineer's Estimate 0.50 MILE $5,500.00 $2,750.00
A0560 63405-0050 PAVEMENT MARKINGS, SYMBOLS
CKC Operations LLC $69.81 $7,539.48 C&C Contracting, Inc $80.00 $8,640.00 Construction Solutions Group, LLC $56.97 $6,152.76 Bookcliff Partners $69.81 $7,539.48 Cutting Edge Contractors, Inc $128.51 $13,879.08 V.C.I. Victor Construction, Inc $120.00 $12,960.00 Engineer's Estimate 108 EACH $600.00 $64,800.00
A0580 63406-0100 RAISED PAVEMENT MARKER, NON-REFLECTIVE
CKC Operations LLC $45.61 $10,490.30 C&C Contracting, Inc $10.00 $2,300.00 Construction Solutions Group, LLC $5.51 $1,267.30 Bookcliff Partners $45.61 $10,490.30 Cutting Edge Contractors, Inc $21.08 $4,848.40 V.C.I. Victor Construction, Inc $4.00 $920.00 Engineer's Estimate 230 EACH $5.00 $1,150.00
A0600 63406-0200 RAISED PAVEMENT MARKER, NON-PLOWABLE, BI-DIRECTIONAL REFLECTIVE
CKC Operations LLC $58.27 $2,913.50 C&C Contracting, Inc $10.00 $500.00 Construction Solutions Group, LLC $5.51 $275.50 Bookcliff Partners $58.27 $2,913.50 Cutting Edge Contractors, Inc $69.67 $3,483.50 V.C.I. Victor Construction, Inc $5.00 $250.00 Engineer's Estimate 50 EACH $8.00 $400.00
8 out of 9Source Selection Information - See FAR 2.101 & 3.104
Project No: AZ/NV BR LCDO HOOVER PARKING
Project Name: Hoover Dam Parking lots Rehab
Schedule: A
Schedule Type: Base
Line Item Pay Item No. Description Quantity Unit Unit Price Amount
Number
A0620 63501-1000 TEMPORARY TRAFFIC CONTROL, TRAFFIC CONTROL SUPERVISOR
CKC Operations LLC Lump Sum $3,399.35 C&C Contracting, Inc Lump Sum $72,000.00 Construction Solutions Group, LLC Lump Sum $54,000.00 Bookcliff Partners Lump Sum $3,399.35 Cutting Edge Contractors, Inc Lump Sum $57,928.26 V.C.I. Victor Construction, Inc Lump Sum $77,431.00 Engineer's Estimate ALL LPSM Lump Sum $30,000.00
A0640 63502-0600 TEMPORARY TRAFFIC CONTROL, BARRICADE TYPE 3
CKC Operations LLC $582.75 $4,662.00 C&C Contracting, Inc $1,200.00 $9,600.00 Construction Solutions Group, LLC $2,000.00 $16,000.00 Bookcliff Partners $582.75 $4,662.00 Cutting Edge Contractors, Inc $393.20 $3,145.60 V.C.I. Victor Construction, Inc $5.00 $40.00 Engineer's Estimate 8 EACH $400.00 $3,200.00
A0660 63502-1050 TEMPORARY TRAFFIC CONTROL, TUBULAR MARKER
CKC Operations LLC $59.49 $11,898.00 C&C Contracting, Inc $150.00 $30,000.00 Construction Solutions Group, LLC $81.00 $16,200.00 Bookcliff Partners $59.49 $11,898.00 Cutting Edge Contractors, Inc $48.65 $9,730.00 V.C.I. Victor Construction, Inc $1.00 $200.00 Engineer's Estimate 200 EACH $65.00 $13,000.00
A0680 63502-1600 TEMPORARY TRAFFIC CONTROL, WARNING LIGHT TYPE B
CKC Operations LLC $400.00 $6,000.00 C&C Contracting, Inc $475.00 $7,125.00 Construction Solutions Group, LLC $540.00 $8,100.00 Bookcliff Partners $400.00 $6,000.00 Cutting Edge Contractors, Inc $95.62 $1,434.30 V.C.I. Victor Construction, Inc $20.00 $300.00 Engineer's Estimate 15 EACH $150.00 $2,250.00
A0700 63503-1000 TEMPORARY TRAFFIC CONTROL, PLASTIC FENCE
CKC Operations LLC $3.40 $6,800.00 C&C Contracting, Inc $25.00 $50,000.00 Construction Solutions Group, LLC $10.80 $21,600.00 Bookcliff Partners $3.40 $6,800.00 Cutting Edge Contractors, Inc $4.69 $9,380.00 V.C.I. Victor Construction, Inc $0.40 $800.00 Engineer's Estimate 2,000 LNFT $7.50 $15,000.00
9 out of 9Source Selection Information - See FAR 2.101 & 3.104
Project No: AZ/NV BR LCDO HOOVER PARKING
Project Name: Hoover Dam Parking lots Rehab
Schedule: A
Schedule Type: Base
Line Item Pay Item No. Description Quantity Unit Unit Price Amount
Number
A0720 63504-1000 TEMPORARY TRAFFIC CONTROL, CONSTRUCTION SIGN
CKC Operations LLC $53.21 $15,963.00 C&C Contracting, Inc $100.00 $30,000.00 Construction Solutions Group, LLC $162.00 $48,600.00 Bookcliff Partners $53.21 $15,963.00 Cutting Edge Contractors, Inc $19.80 $5,940.00 V.C.I. Victor Construction, Inc $1.00 $300.00 Engineer's Estimate 300 SQFT $75.00 $22,500.00
A0740 63505-1000 TEMPORARY TRAFFIC CONTROL, PAVEMENT MARKINGS
CKC Operations LLC $2,890.93 $17,345.58 C&C Contracting, Inc $4,000.00 $24,000.00 Construction Solutions Group, LLC $2,246.40 $13,478.40 Bookcliff Partners $2,890.93 $17,345.58 Cutting Edge Contractors, Inc $3,965.91 $23,795.46 V.C.I. Victor Construction, Inc $250.00 $1,500.00 Engineer's Estimate 6.00 MILE $3,000.00 $18,000.00
A0760 63506-0500 TEMPORARY TRAFFIC CONTROL, FLAGGER
CKC Operations LLC $85.68 $29,988.00 C&C Contracting, Inc $95.00 $33,250.00 Construction Solutions Group, LLC $135.00 $47,250.00 Bookcliff Partners $85.68 $29,988.00 Cutting Edge Contractors, Inc $119.97 $41,989.50 V.C.I. Victor Construction, Inc $25.00 $8,750.00 Engineer's Estimate 350 HOUR $100.00 $35,000.00
Total Schedule - All Items
CKC Operations LLC $1,074,113.17 C&C Contracting, Inc $1,429,720.00 Construction Solutions Group, LLC $1,516,997.76 Bookcliff Partners $1,774,113.17 Cutting Edge Contractors, Inc $1,796,858.41 V.C.I. Victor Construction, Inc $1,899,726.00 Engineer's Estimate $1,250,000.00
| 2022-10-13T10:06:47-0600 | |
| KELLY JANE PALMER |
File details come from the government source that posted it. Updated .