Questions and Answers During Advertisement for CO OMAD 300(67) 06212022.pdf

PDF 176 KB Posted

Attached to
CO OMAD 300(67) Minuteman Missile Access Roads
Solicitation number
6982AF22B000012
Issued by

About this file

This document contains questions and answers from potential bidders regarding Invitation for Bid (IFB) number 6982AF22B000012 from the Department of Transportation Federal Highway Administration. The IFB is for a road widening project along Minuteman missile access roads in Colorado. Key details include the project involves widening existing roads to match new road widths, excavated materials cannot be reused between project sections, dust control will be paid as a lump sum, the completion date cannot be extended, and bidders can view the project sites by driving county roads but cannot access missile silos.

View the file

Other files

Show all 13

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Questions and Answers During Advertisement for CO OMAD 300(67) Minuteman Missile Access Roads

Tuesday, June 21, 2022

Questions Answers

We need to know if all the section 1 existing material excavated out can be used as additional shouldering or carried forward into section 2 widenings? To haul it off would be very expensive; it's not a good product, and people wouldn't want it. Having wider shoulders in section 1 roads might be a better, cheaper option.

Only Typical Section 2 widening roadways have been cleared environmentally for widening. Follow SCR 212.03(a).

Does the excavated material in section 1 balance into the section 2 embankment, or will the contractor need to haul this material off? We would want to have cross-section information to see if it is an option to balance in the embankments

Material is not expected to balance between Typical Section 1 and 2. Follow SCR 212.03(a).

3 The Dust control is a lumpsum. This would be an expensive pay item, as we would need to have dust control as a daily event. Would the government consider an M-Gal unit price this way, they pay for what is done?

This item will be kept as a lumpsum item

4 Does the contractor own the export material? Or does the export road material belong to the Government or county?

See SCR 212.03(a), the Contractor owns any material not claimed by the County.

How does the contractor get paid if the back slope of the ditches ends up requiring import to maintain positive flow parallel to the road? We would have to spend a lot of time building up the back slope and regrading in the ditch for many feet on some of the roads, which might cause ROW problems.

The project does not include ditch grading as the intent is to widen the roadway base through Linear Grading as specified in Type 2 Widening shown on Sheet A5. In most areas, the surrounding topo is flat and used for farming so water would drain away from the roadway into the fields. Any costs associated to grading poor drainage areas created by Linear Grading is included in the cost of Linear Grading and will not be paid for separately.

Will this be a fixed subcontract? Unit prices will give you a lower number, but it will be higher if we end up with a lump sum contract. I see the Base lower than my takeoff; I'm coming up with 107,895tons. Do you want me to treat this as a lump sum contract or unit price?

The estimated quantity that we have in the contract is reasonable based on past OMAD projects. This will be unit price contract.

With not working the weekends, the tons per day would need to be around 2200-3000 tons to complete the base contract within the completion date. This is the max that could be accomplished; this would be about 50-60 trucks per day for around 55 days. The two pits quoting the project wouldn't be able to do more than that. The problem is the alternatives;

the two alternatives have less time to complete than the base bid quantities. Meaning we would not be able to complete them on time. Should we put in an additional 30 days of liquidated damages? Or can the Government change the completion date for the two alternatives? Alt X might be able to be completed on time, but there is no way alt Y can.

We are not able to extend contractor completion date due to weather concerns. Based on the past OMAD projects, production rate of 5,000 ton/day is what the contractors were able to place and we believe is reasonable.

8 Item # A20466-0000 Conserve and stockpile topsoil, are we to assume that we are going to windrow topsoil out past the catch point of the slope or haul it to stockpiles and re-haul back to place after embankment is complete?

Means and methods is up to the Contractor but there is no requirement in the contract to haul topsoil to a stockpile site and re-haul it back to the embankment.

We have a couple of subs that would like to put eyes on the job site. I know we cannot just drive up to the silo’s themselves, but we were wondering if we could do a drive by of several of the locations tomorrow via the county roads?

All the routes to the site are county routes so you should not have any issues looking at the site.

10 What is the availability of water in the areas? Can we pump out of ponds, ditches, and streams?

Contractors for previous OMAD projects covering the same area were able to purchase water. The contractor cannot cannot get water from pond, ditch or streams due to water rights and other laws. Please refer to SCR Section 105.01.

The table I prepared below is from dates and quantities in the contract. The distance to haul aggregates to the sites is very long. The availability of trucks to haul the aggregates is very limited. The sources for the volume of aggregates are limited too. It will likely be necessary to use several suppliers to get the volume needed. The Quarry West of Cheyenne is 149 miles away. A trailer-dump can carry 22 tons. Can the completion date for all schedules be changed to November 2023?

Award for any option(s) is expected within 30 days of base schedule award and it is expected that the contractor will have more than 16 working days to complete options X and Y.

12 Where should the costs for the project manager and the superintendent? Should these costs be distributed among clin items of our choosing, or do you want to see these costs in one line item?

This is the contractor’s decision.

The bidders information form asks for the resume of the on-site project manager. There is no other reference to the project manager in the specifications that I can see. Is the project manager to be priced as a full time on-site project manager?

A resume for a project manager is not required for this project.

Where should costs relating to overhead in the general conditions go, i.e. trucks, phones, job trailers, etc.?

Should these costs be distributed among clin items of our choosing, or do you want to see these costs in one line item?

This is the contractor’s decision

15 Where should travel costs go? This is the contractor’s decision.

16 Where should insurance and bond costs go? This is the contractor’s decision.

17 Is the Erosion Control Supervisor supposed to be a full time on-site position?

There is no requirement for a full time Erosion control supervisor.

18 Will granite base be accepted? The specifications are calling for a plasticity index of 10 (+/-3) and granite will not meet these specifications.

Material needs to meet the plasticity index (PI) specs.

Can arrangements be made so that a bid can be hand delivered to the Lakewood Office? The building has been in lockdown the last few years and it has been difficult to find anyone willing to accept a hand delivered bid.

You can always hand deliver a bid, there is always a security guard at the front and there is always someone from acquisitions in the building to accept the bid.

We have continuously accepted hand delivered bids throughout the pandemic.

20 With the variable price of fuel, is there a possibility of having a fuel escalation clause to cover the haul costs of material to the sites if diesel price exceeds $6/gallon?

Since this is a single season construction project and the construction is scheduled to start soon, we do not intend to have fuel escalation clause.

21 Most of the cattle guards to be replaced are in good to excellent condition. Can they be re-used? Do removed cattleguards become property of the contractor?

The Cattle guards are being replaced because they do not match the width of the roadway, it is contractor’s decision to discard, or salvage removed cattleguards

22 For road work shown on Schedule A, Sheet C16, the road is a gated dead end. The landowner does not allow for travel outside the ROW. Can a turnaround area be used in front of the missile site M-10?

Coordination of temporary turnaround locations would have to completed by the COR and USAF during construction

For Conserved Topsoil and Aggregate-Topsoil Course, the Typical Sections show this material placed on the ditch fore slope. Shouldn’t this material be placed outside the construction limits on the back slope as the county maintenance crews frequently pull material from the fore slope to be placed on the road surfaces.

Conserved Topsoil and Aggregate Topsoil Course is to be placed on the foreslope of the ditch or embankment below the Aggregate Surface Course as shown on Sheet A5 and A6, at the conclusion of construction.

24 Is seeding only placed on the borrow ditch back slope since County Maintenance crews frequently blade material from the fore slope to the road surface?

Seeding is to be placed on Conserved Topsoil and Aggregate Topsoil Course that is to be placed on the foreslope of the ditch or embankment below the Aggregate Surface Course as shown on Sheet A5 and A6, at the conclusion of construction.