Bid Tabulation NM FLAP TAO B007 John Dunn Bridges.pdf

PDF 655 KB Posted

Attached to
NM FLAP TAO B007(1) John Dunn Bridges
Solicitation number
6982AF22B000009
Issued by

About this file

This document contains a bid tabulation report for the NM FLAP TAO B007(1) John Dunn Bridges federal contract opportunity. The report details bids received from two contractors and the independent government estimate to rehabilitate the John Dunn Bridge #5243 and replace Bridge #3807 in Taos, New Mexico. Work on Bridge #5243 includes replacing loose railing, deck surfacing rehabilitation, timber member replacement, coating repair, and steel truss replacement. Bridge #3807 replacement involves removing the existing bridge and constructing a new 50-foot precast bridge with micropile foundations. Monitor Construction Company submitted the low bid of $2,842,253 while Siete, Inc.'s bid was $4,042,109. The engineer's estimate was $3,205,000. The contract is scheduled to be awarded by the Federal Highway Administration.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Tabulation of Bids Report Date: 05/04/22

1 out of 10

Project No: NM FLAP TAO B007(1)

Project Name: John Dunn Bridges

Schedule: A

Schedule Type: Base

Solcitation No: 6982AF22B000009

Division: Central Federal Lands

State: NM County: Taos

Federal Land: BLM - Rio Grande del Norte National Monument Opened at: Lakewood, CO

Opened by: Leslie Karsten

Date: 05/03/22

I certify that this Bid Tabulation accurately reflects the offers received for this solicitation.

Signed: _______________________________

Title: _______________________________

Date: _______________________________

Contract Awarded to: ____________________ Award Date: ____________________

Contractor Comment Bid Amount Responsive

Monitor Construction Company, Inc. $2,842,253.00 8 Old Highway Lane Sonoita, AZ 85637

Siete, Inc. $4,042,109.00 8155 Park Road Rye, CO 81069

Engineer's Estimate $3,205,000.00

Contract Specialist

05/04/2022

2 out of 10

Project No: NM FLAP TAO B007(1)

Project Name: John Dunn Bridges

Schedule: A

Schedule Type: Base

Line Item Pay Item No. Description Quantity Unit Unit Price Amount

Number

A0010 15101-0000 MOBILIZATION

Monitor Construction Company, Inc. Lump Sum $284,000.00 Siete, Inc. Lump Sum $400,000.00 Engineer's Estimate ALL LPSM Lump Sum $438,777.75

A0020 15215-1000 SURVEY AND STAKING, APPROACH ROAD

Monitor Construction Company, Inc. $7,000.00 $7,000.00 Siete, Inc. $3,000.00 $3,000.00 Engineer's Estimate 1 EACH $10,000.00 $10,000.00

A0030 15215-2000 SURVEY AND STAKING, BRIDGE

Monitor Construction Company, Inc. $12,000.00 $12,000.00 Siete, Inc. $30,000.00 $30,000.00 Engineer's Estimate 1 EACH $35,470.00 $35,470.00

A0040 15215-7000 SURVEY AND STAKING, PARKING AREA

Monitor Construction Company, Inc. $2,000.00 $2,000.00 Siete, Inc. $3,000.00 $3,000.00 Engineer's Estimate 1 EACH $20,000.00 $20,000.00

A0050 15225-0000 SLOPE, REFERENCE, AND CLEARING AND GRUBBING CONTROL

Monitor Construction Company, Inc. $3,000.00 $300.00 Siete, Inc. $400,000.00 $40,000.00 Engineer's Estimate 0.10 MILE $58,900.00 $5,890.00

A0060 15236-2000 SURVEY CONTROL, GRADE FINISHING

Monitor Construction Company, Inc. $3,500.00 $350.00 Siete, Inc. $10,000.00 $1,000.00 Engineer's Estimate 0.10 MILE $35,600.00 $3,560.00

A0070 15301-0000 CONTRACTOR QUALITY CONTROL

Monitor Construction Company, Inc. Lump Sum $65,000.00 Siete, Inc. Lump Sum $175,000.00 Engineer's Estimate ALL LPSM Lump Sum $215,000.00

3 out of 10

Project No: NM FLAP TAO B007(1)

Project Name: John Dunn Bridges

Schedule: A

Schedule Type: Base

Line Item Pay Item No. Description Quantity Unit Unit Price Amount

Number

A0080 15401-0000 CONTRACTOR TESTING

Monitor Construction Company, Inc. Lump Sum $80,000.00 Siete, Inc. Lump Sum $175,000.00 Engineer's Estimate ALL LPSM Lump Sum $115,000.00

A0090 15501-0000 CONSTRUCTION SCHEDULE

Monitor Construction Company, Inc. Lump Sum $1,500.00 Siete, Inc. Lump Sum $25,000.00 Engineer's Estimate ALL LPSM Lump Sum $10,000.00

A0100 15701-0000 SOIL EROSION CONTROL

Monitor Construction Company, Inc. Lump Sum $55,000.00 Siete, Inc. Lump Sum $125,000.00 Engineer's Estimate ALL LPSM Lump Sum $40,000.00

A0110 15720-0000 STORM WATER POLLUTION PREVENTION PLAN

Monitor Construction Company, Inc. Lump Sum $15,000.00 Siete, Inc. Lump Sum $25,000.00 Engineer's Estimate ALL LPSM Lump Sum $10,000.00

A0120 15802-0000 WATERING FOR DUST CONTROL

Monitor Construction Company, Inc. Lump Sum $5,000.00 Siete, Inc. Lump Sum $1,000.00 Engineer's Estimate ALL LPSM Lump Sum $75,000.00

A0130 20101-0000 CLEARING AND GRUBBING

Monitor Construction Company, Inc. $55,000.00 $11,000.00 Siete, Inc. $500,000.00 $100,000.00 Engineer's Estimate 0.20 ACRE $18,000.00 $3,600.00

A0140 20301-0400 REMOVAL OF BRIDGE

Monitor Construction Company, Inc. $30,000.00 $30,000.00 Siete, Inc. $175,000.00 $175,000.00 Engineer's Estimate 1 EACH $75,000.00 $75,000.00

4 out of 10

Project No: NM FLAP TAO B007(1)

Project Name: John Dunn Bridges

Schedule: A

Schedule Type: Base

Line Item Pay Item No. Description Quantity Unit Unit Price Amount

Number

A0150 20301-2400 REMOVAL OF SIGN

Monitor Construction Company, Inc. $200.00 $400.00 Siete, Inc. $2,000.00 $4,000.00 Engineer's Estimate 2 EACH $270.00 $540.00

A0160 20420-0000 EMBANKMENT CONSTRUCTION

Monitor Construction Company, Inc. $55.00 $44,000.00 Siete, Inc. $100.00 $80,000.00 Engineer's Estimate 800 CUYD $100.00 $80,000.00

A0170 25101-2300 PLACED RIPRAP, METHOD B, CLASS 3

Monitor Construction Company, Inc. $420.00 $63,000.00 Siete, Inc. $300.00 $45,000.00 Engineer's Estimate 150 CUYD $200.00 $30,000.00

A0180 25101-2700 PLACED RIPRAP, METHOD B, CLASS 7

Monitor Construction Company, Inc. $450.00 $112,500.00 Siete, Inc. $325.00 $81,250.00 Engineer's Estimate 250 CUYD $300.00 $75,000.00

A0190 25302-1000 GABIONS, GALVANIZED OR ALUMINIZED COATED

Monitor Construction Company, Inc. $450.00 $6,750.00 Siete, Inc. $2,000.00 $30,000.00 Engineer's Estimate 15 CUYD $500.00 $7,500.00

A0200 30202-2100 ROADWAY AGGREGATE, METHOD 2, SURFACE COURSE

Monitor Construction Company, Inc. $65.00 $17,550.00 Siete, Inc. $75.00 $20,250.00 Engineer's Estimate 270 TON $64.00 $17,280.00

A0210 40301-0000 ASPHALT CONCRETE PAVEMENT

Monitor Construction Company, Inc. $300.00 $10,500.00 Siete, Inc. $300.00 $10,500.00 Engineer's Estimate 35 TON $150.00 $5,250.00

5 out of 10

Project No: NM FLAP TAO B007(1)

Project Name: John Dunn Bridges

Schedule: A

Schedule Type: Base

Line Item Pay Item No. Description Quantity Unit Unit Price Amount

Number

A0220 40702-0100 CHIP SEAL, TYPE 1A

Monitor Construction Company, Inc. $20.00 $7,500.00 Siete, Inc. $10.00 $3,750.00 Engineer's Estimate 375 SQYD $55.00 $20,625.00

A0230 41102-1000 PRIME COAT, METHOD 1

Monitor Construction Company, Inc. $5.00 $800.00 Siete, Inc. $10.00 $1,600.00 Engineer's Estimate 160 SQYD $3.00 $480.00

A0240 41105-0000 BLOTTER

Monitor Construction Company, Inc. $50.00 $15.00 Siete, Inc. $10.00 $3.00 Engineer's Estimate 0.3 TON $400.00 $120.00

A0250 41201-0000 TACK COAT

Monitor Construction Company, Inc. $1,500.00 $300.00 Siete, Inc. $2,000.00 $400.00 Engineer's Estimate 0.2 TON $4,000.00 $800.00

A0260 41801-3000 ASPHALT CONCRETE PAVEMENT PATCH, TYPE 3

Monitor Construction Company, Inc. $100.00 $23,000.00 Siete, Inc. $35.00 $8,050.00 Engineer's Estimate 230 SQYD $35.00 $8,050.00

A0270 55201-0200 STRUCTURAL CONCRETE, CLASS A (AE)

Monitor Construction Company, Inc. $900.00 $120,600.00 Siete, Inc. $1,700.00 $227,800.00 Engineer's Estimate 134 CUYD $2,300.00 $308,200.00

A0280 55240-0000 GROUT

Monitor Construction Company, Inc. $550.00 $13,200.00 Siete, Inc. $500.00 $12,000.00 Engineer's Estimate 24 CUFT $300.00 $7,200.00

6 out of 10

Project No: NM FLAP TAO B007(1)

Project Name: John Dunn Bridges

Schedule: A

Schedule Type: Base

Line Item Pay Item No. Description Quantity Unit Unit Price Amount

Number

A0290 55302-3500 PRECAST, PRESTRESSED CONCRETE SLAB

Monitor Construction Company, Inc. $1,500.00 $382,500.00 Siete, Inc. $1,900.00 $484,500.00 Engineer's Estimate 255 LNFT $900.00 $229,500.00

A0300 55303-0000 PRESTRESSING SYSTEM

Monitor Construction Company, Inc. Lump Sum $48,000.00 Siete, Inc. Lump Sum $60,000.00 Engineer's Estimate ALL LPSM Lump Sum $10,000.00

A0310 55401-1000 REINFORCING STEEL

Monitor Construction Company, Inc. $4.00 $46,436.00 Siete, Inc. $4.00 $46,436.00 Engineer's Estimate 11,609 LB $4.00 $46,436.00

A0320 55401-2000 REINFORCING STEEL, EPOXY COATED

Monitor Construction Company, Inc. $4.00 $25,996.00 Siete, Inc. $5.00 $32,495.00 Engineer's Estimate 6,499 LB $3.75 $24,371.25

A0330 55501-0000 STRUCTURAL STEEL

Monitor Construction Company, Inc. Lump Sum $3,500.00 Siete, Inc. Lump Sum $30,000.00 Engineer's Estimate ALL LPSM Lump Sum $35,000.00

A0340 55601-0900 BRIDGE RAILING, STEEL (STAINED)

Monitor Construction Company, Inc. $365.00 $43,800.00 Siete, Inc. $2,000.00 $240,000.00 Engineer's Estimate 120 LNFT $600.00 $72,000.00

A0350 55720-0000 REPAIR STRUCTURAL TIMBER AND LUMBER

Monitor Construction Company, Inc. Lump Sum $27,000.00 Siete, Inc. Lump Sum $15,000.00 Engineer's Estimate ALL LPSM Lump Sum $2,000.00

7 out of 10

Project No: NM FLAP TAO B007(1)

Project Name: John Dunn Bridges

Schedule: A

Schedule Type: Base

Line Item Pay Item No. Description Quantity Unit Unit Price Amount

Number

A0360 56301-2000 PAINTING, STEEL STRUCTURE

Monitor Construction Company, Inc. Lump Sum $477,140.00 Siete, Inc. Lump Sum $500,000.00 Engineer's Estimate ALL LPSM Lump Sum $550,000.00

A0370 56320-0000 CONTAINMENT SYSTEM AND WORKER PROTECTION PLAN

Monitor Construction Company, Inc. Lump Sum $200,000.00 Siete, Inc. Lump Sum $75,000.00 Engineer's Estimate ALL LPSM Lump Sum $25,000.00

A0380 56401-1000 BEARING DEVICE, ELASTOMERIC

Monitor Construction Company, Inc. $1,200.00 $12,000.00 Siete, Inc. $5,000.00 $50,000.00 Engineer's Estimate 10 EACH $2,000.00 $20,000.00

A0390 56701-0000 MICROPILE

Monitor Construction Company, Inc. $850.00 $414,800.00 Siete, Inc. $750.00 $366,000.00 Engineer's Estimate 488 LNFT $750.00 $366,000.00

A0400 56705-0000 MICROPILE LOAD VERIFICATION TEST

Monitor Construction Company, Inc. $35,000.00 $35,000.00 Siete, Inc. $50,000.00 $50,000.00 Engineer's Estimate 1 EACH $14,000.00 $14,000.00

A0410 56706-0000 MICROPILE PROOF LOAD TEST

Monitor Construction Company, Inc. $6,500.00 $26,000.00 Siete, Inc. $25,000.00 $100,000.00 Engineer's Estimate 4 EACH $9,000.00 $36,000.00

A0420 61701-4550 GUARDRAIL SYSTEM MGS, TYPE 2, CLASS A WOOD POSTS (STAINED)

Monitor Construction Company, Inc. $60.00 $10,500.00 Siete, Inc. $175.00 $30,625.00 Engineer's Estimate 175 LNFT $100.00 $17,500.00

8 out of 10

Project No: NM FLAP TAO B007(1)

Project Name: John Dunn Bridges

Schedule: A

Schedule Type: Base

Line Item Pay Item No. Description Quantity Unit Unit Price Amount

Number

A0430 61702-0000 TERMINAL SECTION TYPE END ANCHOR

Monitor Construction Company, Inc. $2,400.00 $7,200.00 Siete, Inc. $4,000.00 $12,000.00 Engineer's Estimate 3 EACH $6,000.00 $18,000.00

A0440 61707-0000 STRUCTURE TRANSITION RAILING (METAL BARRIER)

Monitor Construction Company, Inc. $52.00 $1,976.00 Siete, Inc. $500.00 $19,000.00 Engineer's Estimate 38 LNFT $180.00 $6,840.00

A0450 61801-0000 CONCRETE BARRIER (TYPE 32)

Monitor Construction Company, Inc. $200.00 $8,000.00 Siete, Inc. $600.00 $24,000.00 Engineer's Estimate 40 LNFT $300.00 $12,000.00

A0460 61804-1000 TERMINAL SECTION, TYPE 1 (TRANSITION)

Monitor Construction Company, Inc. $2,500.00 $2,500.00 Siete, Inc. $5,000.00 $5,000.00 Engineer's Estimate 1 EACH $7,000.00 $7,000.00

A0470 62201-0250 DUMP TRUCK, 10 CUBIC YARD MINIMUM CAPACITY

Monitor Construction Company, Inc. $100.00 $2,000.00 Siete, Inc. $100.00 $2,000.00 Engineer's Estimate 20 HOUR $115.00 $2,300.00

A0480 62201-0950 WHEEL LOADER, 3 CUBIC YARD MINIMUM RATED CAPACITY

Monitor Construction Company, Inc. $80.00 $1,600.00 Siete, Inc. $100.00 $2,000.00 Engineer's Estimate 20 HOUR $145.00 $2,900.00

A0490 62301-0000 GENERAL LABOR

Monitor Construction Company, Inc. $50.00 $2,000.00 Siete, Inc. $50.00 $2,000.00 Engineer's Estimate 40 HOUR $60.00 $2,400.00

9 out of 10

Project No: NM FLAP TAO B007(1)

Project Name: John Dunn Bridges

Schedule: A

Schedule Type: Base

Line Item Pay Item No. Description Quantity Unit Unit Price Amount

Number

A0500 62302-1000 SPECIAL LABOR, HIRED TECHNICAL SERVICES

Monitor Construction Company, Inc. $150.00 $1,500.00 Siete, Inc. $150.00 $1,500.00 Engineer's Estimate 10 HOUR $200.00 $2,000.00

A0510 62302-1100 SPECIAL LABOR, HIRED SURVEY SERVICES

Monitor Construction Company, Inc. $160.00 $1,600.00 Siete, Inc. $150.00 $1,500.00 Engineer's Estimate 10 HOUR $300.00 $3,000.00

A0520 62510-2000 SEEDING, HYDRAULIC METHOD

Monitor Construction Company, Inc. $15,000.00 $3,000.00 Siete, Inc. $7,000.00 $1,400.00 Engineer's Estimate 0.20 ACRE $3,000.00 $600.00

A0530 62515-2000 MULCHING, HYDRAULIC METHOD

Monitor Construction Company, Inc. $5,500.00 $1,100.00 Siete, Inc. $7,000.00 $1,400.00 Engineer's Estimate 0.20 ACRE $3,300.00 $660.00

A0540 63301-0000 SIGN SYSTEM

Monitor Construction Company, Inc. $810.00 $3,240.00 Siete, Inc. $1,600.00 $6,400.00 Engineer's Estimate 4 EACH $1,000.00 $4,000.00

A0550 63308-3000 OBJECT MARKER, TYPE 3

Monitor Construction Company, Inc. $310.00 $3,100.00 Siete, Inc. $125.00 $1,250.00 Engineer's Estimate 10 EACH $415.00 $4,150.00

A0560 63501-0000 TEMPORARY TRAFFIC CONTROL

Monitor Construction Company, Inc. Lump Sum $32,500.00 Siete, Inc. Lump Sum $35,000.00 Engineer's Estimate ALL LPSM Lump Sum $40,000.00

10 out of 10

Project No: NM FLAP TAO B007(1)

Project Name: John Dunn Bridges

Schedule: A

Schedule Type: Base

Line Item Pay Item No. Description Quantity Unit Unit Price Amount

Number

A0570 63701-0000 FIELD OFFICE

Monitor Construction Company, Inc. $30,000.00 $30,000.00 Siete, Inc. $45,000.00 $45,000.00 Engineer's Estimate 1 EACH $33,000.00 $33,000.00

Total Schedule - All Items

Monitor Construction Company, Inc. $2,842,253.00 Siete, Inc. $4,042,109.00 Engineer's Estimate $3,205,000.00