This document contains questions and answers from a pre-solicitation conference for an indefinite delivery, indefinite quantity contract opportunity with the Federal Highway Administration, Central Federal Lands Highway Division. The IDIQ will provide full service architectural and engineering services for transportation projects located on federal lands in 14 states in environmentally sensitive areas. There are currently five incumbent contract holders that will be replaced under this new solicitation. The solicitation will have a partial small business set-aside with a subcontracting goal of 3% for HUBZone small businesses. The total shared capacity of the multiple IDIQ awards is $85 million over five years. Questions were answered regarding the contract and proposal requirements, including that state professional engineering licenses will be required for listed states, SF330 forms and organizational charts must meet page limits, and multiple offices providing personnel must be listed.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| QnA 5.19.2021.pdf | ||
| Amendment A001.pdf | ||
| 6982AF21R000002 RFQ IDIQ.pdf |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Questions and Answers during Advertisement for
Full Service A-E IDIQ
May 19, 2021
Questions Answers
1 Who are the current contract holders? CFLHD has five current A&E IDIQ holders –
1) HDR Engineering, Inc.
2) CH2M Hill, Inc. (Jacobs Engineering Group, Inc.)
3) DJ&A, P.C.
4) Atkins North America, Inc.
5) Wood Environment & Infrastructure Solutions, Inc.
2 Do you know the typical Primes that may pursue this so we can explore teaming opportunities?
No
3 Do you know if there will be a HUBZone goal on this?
Subcontracting plans will be required from large businesses during the second phase of the solicitation. The HUBZone goal for subcontracting plans are 3%.
4 Who is the incumbent or is this a new contract?
See question #1
5 Is this an A-E or A-E-C (Architectural, Engineering, and
Construction) contract?
A-E
6 Will there be an IDIQ by geography (by state)?
No. The IDIQ will cover multiple states.
7 If not IDIQ by state (#3 above) is there a requirement for PE licensing for all of the listed states?
See the requirements under the Type of Contract section in the RFQ, page
1.
8 What is the extent of the “environmentally sensitive” areas (NEPA process, other)?
See the General Scope of Work section, page 2 of the RFQ.
9 Will the SF330 Part IIs be counted in the 80 page limit? Yes
10 Would the CFLHD consider allowing one 11 x 17 page for the
Organizational Chart?
No
11 Are covers, section dividers and TOC pages included in the 80 page limit?
No, this will be clarified in Amendment A001
12 Previous submittals have excluded divider pages, tabs, and front and back covers from the total page count. Is that requirement still appropriate for this submittal.
See Amendment A001
13 Do SF330 Part IIs count toward the 80-page limit? Since the contract covers multiple states and a Part II is requested from each office that will provide staff/work - there could be upward of 25 pages of Part IIs alone.
Yes. One Part II form showing the overall staff county companywide along with a list of each participating branch office is acceptable.
14 Are 11X17 pages allowed for the Organization chart? No
June 1, 2021
Questions Answers
1 In regards to the SF330 Part I, are we required to list all offices of the Prime that will be providing Key Personnel or is it acceptable to only list the Responsible office or Corporate office?
List all offices that will be providing key personnel.
2 Is it acceptable to only list the Corporate Office location for the
Subcontractors on the SF330 Part I? Due to the amount of office locations of our team within the AOR, we would be submitting multiple pages for Part I.
Yes