QnA 11.16.2020.pdf
PDF 89 KB Posted
- Attached to
- NV FLAP 300(1) Fossil House Road
- Solicitation number
- 6982AF20B000023
About this file
This document contains questions and answers from an advertisement for the NV FLAP 300(1) Fossil House Road project. The project provides improvements to Union Canyon Road and Fossil House Road to provide access to the Berlin Ichthyosaur State Park in Nye County, Nevada. Key details include:
-
A part-time Construction Quality Control Manager is required on-site per the specifications. The Superintendent can also fulfill this role.
-
A separate Site Safety and Health Officer is not required, but the contractor must abide by all regulations including COVID-19 protocols.
-
The contract completion date is November 13, 2021, providing the project duration.
-
The related federal contract opportunity is a HUBZone set-aside for the NV FLAP 300(1) Fossil House Road project. The project scope includes improvements such as five low water crossings along Union Canyon Road and roadway widening and a soldier pile wall along Fossil House Road to provide access to the Berlin Ichthyosaur State Park. The soliciting agency is the Department of Transportation Federal Highway Administration.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Bid Tabulation Fossil House Road.pdf | ||
| Bid Opening Summary NV FLAP 300(1).pdf | ||
| QnA 12.4.2020.pdf | ||
| QnA 12.3.2020.pdf | ||
| QnA 12.2.2020.pdf | ||
| A002.pdf | ||
| A001.pdf | ||
| Fossil House Road Geotechnical Report.pdf | ||
| 6982AF20B000023.pdf | ||
| Fossil House Plan Set.pdf | ||
| Fossil House Final Drainage Report.pdf | ||
| FP-14.pdf |
Show all 12
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Questions and Answers during Advertisement for NV FLAP 300(1) Fossil House Road
November 16, 2020
Questions Answers 1 Section 153.02 Qualifications deletes both the Full-Time and Part-
Time on site CQC. What are the on-site requirements for this position and can the Superintendent also fulfill this role?
Section 153.02 of the SCR’s deleted the requirement for a Full Time QCM, but a part time QCM is still necessary. The requirements for a part time QCM are in 153.02 (a)(2) of the SCR’s on page E-24.
2 Is a Site Safety Health Officer required on-site for this project?
No separate Site Safety Health Officer is required for this project, however, the contractor is required to abide by all regulations (Including COVID regulations).
3 Subsection 108.01 of the SCRs does not list the Completion Date or Project Duration, can you provide the duration of the project?
Section 108.01 of the SCR’s, page E-16 of the Invitation for Bid, shows a contract completion date of November 13, 2021.