This document is an Amendment (Amendment 02) to Solicitation Number 697DCK-25-R-00226 for the Federal Aviation Administration's (FAA) William J. Hughes Technical Center electricity procurement. The amendment includes responses to nine supplier questions covering topics such as contract terms, PJM ancillary services, proposal submission dates, and hedging practices. Key updates include extending the proposal submission deadline to April 28, 2025 at 1:00 p.m., with a contract award date no later than May 1, 2025 at 10:00 a.m. The FAA confirmed this is a commercial item acquisition for non-residential electricity sales, requires all PJM ancillary services be included in pricing, and clarified that the agency has not made and does not intend to make any hedges during the contract term. The solicitation remains a firm-fixed price contract with all original clauses remaining in effect, and the FAA emphasized that taking exception to any contract terms would render a proposal unresponsive and unacceptable.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
AMENDMENT OF SOLICITATION!MODIFICATION OF CONTRACT
1. CONTRACTID CODE PAGE OF PAGES
__________________________ ii 4
2. AMENDMENT/MODIFICATION NO. 3. EFFECTIVE DATE 4. REQUISITION/PURCHASE REQ.NO. 5. PROJECT NO. (Ifapp!icüIa)
02 04/15/2025
6. ISSUED BY CODE PAQ 092OASW-AFN
7. ADMINISTERED BY (Ifother than Item 6) CODE
FEDERAL AVIATION ADMINISTRATION
SOUTHWEST REGION
REAL ESTATE & UTILITIES GRP, AAQ-920
10101 HILLWOOD PARKWAY
FORT WORTH TX 76177-1524
B. NAMEANDADDRESS OF CONTRACTOR (No., afree county, State and ZIP Code) 9A. AMENDMENT OFSOLICITATION NO.
697DCK-25-R-00226
X 9B. DATED (SEE hEM 11)
04/15/2025 bA. MODIFICATION OF CONTRACT/ORDER NO.
lOB. DATED (SEE ITEM 13)
CODE FACILITY CODE
11: THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITAIlONS lThe above numbered solicitatIon Is amended as set forth In Item 14. The hour and date specified for receipt of Offers Dis extended. is not extended.
Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methodx (a) By completing Items B and 15, and returning copies of the amendment; (b) By acknowledgIng receipt of this amendment on each copy of the offer submitted; or (c) By separate letter or telegram which Includes a reference to the solicitation and amendment number. FAILURE OF YOUR ACKNOWLEDGEMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIORTO THE HOURAND DATE SPECIFIED MAY RESULTIN REJECTION OF YOUR OFFER If by virtue of this amendment you desire to change an offer already submitted, such change maybe made by tetegram or letter, provided each telegram or letter makes reference to the solIcitation and this amendment, and is received prior to the opening hour and date specified.
12. ACCOUNTINGAND APPROPRIATION DATA (If required.)
13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS. IT MODIFIES THE CONTRACT/ORDER NO. PS DESCRIBED IN ITEM 14.
A. ThIS CHANGE ORDER IS ISSUED PURSUANT TO: (Speclly authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT
ORDER NO. IN ITEM bA.
B. THE ABWE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, D appropriation date, etc.) SET FORTH IN ITEM 14.
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO THEAUTHORITY OF:
0. OTHER (Spec/I' type of modification and authority)
5. NPORTANT: Contractor is not. D is required to sign this document and return copies to the Issuing office.
14. DESCRIPTION OFAMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
The SIR is being modified to add the responses to suppliers questions. See attachment.
Except as provided herein, all terms and conditions of the document referenced In Item 9 A or 1OA, as heretofore changed, remains unchanged and In full force and effect.
iSA. NAMEAND TITLE OF SIGNER (Type orprinf) 16A. NAME AND TITLE OF CONTRACTING OFFICER (Type orprint)
Carolyn R. Myers Real Estate Contracting Officer
15B. CONTRACTOR/OFFEROR 15C. DATE SIGNED 166. CONTRACTAIJFHORITY I 16C. DATE SIGNED
CAROLYN R MYERS D:g:taIIyegnedbyCAROLYNRMYERS Date: 2025.04.15 09:44:36 -05,00, 104/15/2025
(Signature ofponaotho,izedtoaign) (Signalurn ofContracting Owner)
SIR 697DCK-25-R-00226
RESPONSES TO SUPPLIERS QUESTIONS
1. Question: Would the supplier be able to recover for what we deem to be a loss from reselling their hedges due to an early termination of the contract?
Answer: The Government reserves the right to terminate this contract for its sole convenience in accordance with contract clause 3.10.6-1 Termination for Convenience of the Government (Fixed Price) (Oct 1996). This clause and any other referenced clauses in Solicitation Number 697/DCK-25-R-00226 apply. If the supplier takes exception to any of the clauses in the FAA's Solicitation Number 697/DCK-25-R-00226 your proposal will be rendered unresponsive and unacceptable.
2. Question: Please confirm the FAA considers this SIR to be a commercial item acquisition?
Answer: The FAA considers Solicitation Number 697/DCK-25-R-00226 to be a commercial acquisition per Section G.2 (q) Non-Residential Sale.
Question: The FAA included clause 3.3.2-1 FAA Cost Principles on page 15 of the SIR.
According to the Prescription for that clause it "Must be used in all SIRs and contracts except for firm-fixed price contracts and fixed-price contracts with economic price adjustments (where adjustments are not based on actual costs incurred) for commercial items." The SIR also includes the clause 3.2.4-1 Type of Contract which indicates the FAA will issue a FIRM FIXED PRICE contract. Because the resulting contract will be firm-fixed price, will the Government consider removing clause 3.3.2-1? If 3.3.2-1 FAA Cost Principles is removed, please confirm whether clause 3.2.2.3-3 1 Facilities Capital Cost of Money should also be removed based on its Prescription?
Answer: The FAA views this question and clarification as an exception to Solicitation Number 697DCK-25-R-00226 and the FAA does not agree to this exception. All clauses referenced in Solicitation Number 697DCK-25-R-00226 apply. If you take exception to the FAA's Solicitation Number 697DCK-25-R-00226, your proposal will be rendered unresponsive and unacceptable.
Question: Is the Attestation for the retirement of Energy Attribute Certificates required given the recent Executive Orders around CFE?
Answer: Yes, the Attestation for the retirement of Energy Attribute Certificates are required per the terms of Section G.4 Contractor Attestation Confirming Compliance With NJ RPS.
5. Question: Option 1 and 2 Adders both list "all PJM Ancillary services". Can you please confirm this will require all suppliers to fix the following ancillaries:
a). Reactive Services b). Black Start c.) Reactive Supply & Voltage Control
Answer: Per the terms of Section C.4. 1 of Solicitation Number 2971DCK-25-R-00226, the Real-Time Fixed Price Adder and the Day-Ahead Fixed Price Adder include all PJM ancillary services with no exceptions.
6. Question: Per the requested hold period from submission due April 23 1 p.m., April 26 is a Saturday. Is this to be amended to April 25 by 10 a.m.?
Answer: The FAA will issue an Amendment to Solicitation Number 297/DCK-25-R-00226, Section L. Instructions, Conditions, and Notices to Bidders that will extend the proposal submission due date to no later than 1:00 p.m. on April 28, 2025 with a contract award date no later than 10:00 AM on May 1, 2025.
7. Question: Can you advise on the typical award notification period your prior bids for this facility?
Answer: See response to Question 6 above.
8. Question: Has the FAA made any hedges in the last 5 years of service?
Answer: No, the FAA has not made any hedges in the last 5 years of service.
9. Question: Does the FAA intend to make any hedges in the upcoming contract term?
Answer: No, the FAA does not intend to make any hedges in the upcoming contract term.
INSTRUCTIONS
Instructions for items other than those that are self-explanatory, are as follows:
(a) Item 1 (Contract ID Code). Insert the contract type identification code that appears in the title block of the contract being modified.
Item 3 (Effective date)
(1) For a solicitation amendment, change order, or administrative change, the effective date shall be the issue date of the amendment, change order, or administrative change.
(2) For a supplemental agreement, the effective date shall be the date agreed to by the contracting parties.
(3) For a modification issued as an initial or confirming notice of termination for the convenience of the Government, the effective date and the modification number of the confirming notice shall be the same as the effective date and modification number of the initial notice.
(4) For a modification converting a termination for default to a termination for the convenience of the Government, the effective date shall be the same as the effective date of the termination for default.
(5) For a modification confirming the contacting officer's determination of the amount due in settlement of a contract termination, the effective date shall be the same as the effective date of the initial decision.
Item 6 (Issued By). Insert the name and address of the issuing office. If applicable, insert the appropriate issuing office code in the code block.
Item 8 (Name and Address of Contractor). For modifications to a contract or order, enter the contractor's name, address, and code as shown in the original contract or order, unless changed by this or a previous modification.
Item 9. (Amendment of Solicitation No. - Dated) and 10.
(Modification of Contract/Order No.-Dated). Check the appropriate box and in the corresponding blanks insert the Number and date of the original solicitation, contract, or order.
Item 12 (Accounting and Appropriation Date). When appropriate, indicate the impact of the modification on each affected accounting classification by inserting one of the following entries.
(1) Accounting classification
Net Increase $
(2) Accounting classification
Net Decrease $
NOTE: If there are changes to multiple accounting classifications that cannot be placed in block 12, insert an asterisk and the words "See continuation sheet."
Item 13. Check the appropriate box to indicate the type of modification. Insert in the corresponding blank the authority under which the modification is issued. Check whether or not contractor must sign this document. (See FAR 43.103).
(1) Organize amendments or modifications under the appropriate Uniform Contract Format (UCF) section headings from the applicable solicitation or contract. The UCF table of contents, however, shall not be set forth in this document.
(2) Indicate the impact of the modification on the overall total contract price by inserting one of the following entries:
(i) Total contract price increased by $ (ii)Total contract price decreased by $ (iii)Total contract price unchanged.
(3) State reason for modification.
(4) When removing, reinstating, or adding funds, identify' the contract items and accounting classifications.
(5) When the SF 30 is used to reflect a determination by the contracting officer of the amount due in settlement of a contract terminated for the convenience of the Government, the entry in Item 14 of the modification may be limited -
(i) A reference to the letter determination; and (ii)A statement of the net amount determined to be due in settlement of the contract.
(6) Include subject matter or short title of solicitation/contract where feasible.
Item 16B. The contracting officer's signature is not required on solicitation amendments. The contracting officer's signature is normally affixed last on supplemental agreements.
Item 14 (Description of AmendmentlModification). STANDARD FORM 30 (Rev 10-83) BACK