This amendment modifies a solicitation for annual guy wire inspection services at the Federal Aviation Administration's Yeager Airport facility in Charleston, West Virginia. The services required include inspection of walkway bridges, masts, guy wire anchor points, foundations, and hardware; testing guy wire tensions; and reporting on inspection findings and recommended corrective actions. The amendment extends the proposal due date to January 13, 2023 and provides drawings of the airport structures and a sample past inspection request for reference. No incumbent is specified. The North American Industry Classification code applicable is 237130. The period of performance is February 1, 2023 to December 31, 2023.

View the file

Other files

File Type Posted
697DCK-23-R-00097 Annual Guy Wire Inspection.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT

1. CONTRACT ID CODE

5. PROJECT NO. (If applicable)2. AMENDMENT/MODIFICATION NO. 3. EFFECTIVE DATE 4. REQUISITION/PURCHASE REQ.NO.

PAGE OF PAGES

6. ISSUED BY CODE 7. ADMINISTERED BY (If other than Item 6)

8. NAME AND ADDRESS OF CONTRACTOR (No., street, county, State and ZIP Code)

CODE

9A. AMENDMENT OF SOLICITATION NO.

9B. DATED (SEE ITEM 11)

10A. MODIFICATION OF CONTRACT/ORDER NO.

10B. DATED (SEE ITEM 13)

CODE FACILITY CODE

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers

Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended , by one of the following methods: (a) By completing

Items 8 and 15, and returning is extended, is not extended.

12. ACCOUNTING AND APPROPRIATION DATA (If required.)

13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS. IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.

(x) A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO THE AUTHORITY OF:

D. OTHER (Specify type of modification and authority) appropriation date, etc.) SET FORTH IN ITEM 14.

E. IMPORTANT: Contractor is not, is required to sign this document and return

ORDER NO. IN ITEM 10A.

1 6

0001 12/09/2022

FEDERAL AVIATION ADMINISTRATION

AAQ-500 - REGIONAL ACQUISITIONS

10101 HILLWOOD PARKWAY

FORT WORTH TX 76177-1524

AAQ520FTW-AFN

x

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

separate letter or telegram which includes a reference to the solicitation and amendment number. FAILURE OF YOUR ACKNOWLEDGEMENT TO BE RECEIVED AT

THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted , such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted ; or (c) By ___________ x x

697DCK-23-R-00097

copies to the issuing office.

12/09/2022

(x)

The purpose of this amendment is to provide updated information regarding this solicitation:

1. The due date for proposal submissions, is extended to January 13, 2023

2. Questions and Answers are included as accompaniment to this solicitation amendment.

***Please be advised that late proposals will not be accepted.***

Period of Performance: 02/01/2023 to 12/31/2023

16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)15A. NAME AND TITLE OF SIGNER (Type or print)

15C. DATE SIGNED 16B. CONTRACT AUTHORITY 15B. CONTRACTOR/OFFEROR 16C. DATE SIGNED

(Signature of person authorized to sign) (Signature of Contracting Officer)

Jennifer J. Davis

Except as provided herein, all terms and conditions of the document referenced in Item 9 A or 10A, as heretofore changed, remains unchanged and in full force and effect .

X 1

Vendor questions and answers for SIR 697DCK-23-R-00097 (Annual Guy Wire Inspection at the Federal Aviation Administration, Yeager Airport in Charleston, WV)

1. Would it be possible to get a past inspection report or drawings on the Yeager Airport tower mast that is needing to be inspected. A: Reference attachments, “ALS Inspection Request”, and drawings “DR EA-E-09405 (1/2), and E-5298,11/11 ”

2. Could you pass on the drawings listed in the bid and a previous inspection report that we could review before bidding? A: Reference attachments “DR EA-E-09405 (1/2), and E-5298,11/11", In lieu of a report, a previous inspection request has been provided as attachment, “ALS Inspection Request”.

3. How many towers are in this structure? A: fifteen masts

4. Do you have plans with size of cables available or previous inspection report? A: There are a total of 112 guy wires. The guy wires are galvanized steel Bridge Strand, ranging from 5/8 to 1- 1/8 inches in diameter, the length of guys range 40 to 350 feet in length. Reference attachment “ALS Inspection Request”

Charleston West Virginia (CRW) Approach Lighting System (ALS) Light Bridge

We are requesting quote for an overall safety inspection of the complete ALS light bridge structure and the testing of guy wire tensions.

The ALS structure consists of fifteen (15) masts and fifteen (15) walkway bridges.

Mast heights range from 71 to 283 feet, each walkway bridge section spans from

130 to 210 feet, for a total walkway bridge length of 2400 feet. The starting walkway bridge abutment is at the end of runway 23 and connects to mast 4. Mast 6 is the 1000-foot bar and is equipped with a transverse walkway.

There are a total of 112 guy wires. The guy wires are galvanized steel Bridge

Strand, ranging from 5/8 to 1-1/8 inches in diameter, the length of guys range 40 to 350 feet in length.

Inspection of Walkway bridges and Masts:

Inspection of walkway bridges and masts, including all structural members, elevated platforms, guy wire anchor points, mast bases, foundations, miscellaneous hardware, safety ladders and security fences. Inspection of all masts will include measurements of masts vertical alignment and vertical linearity.

Guy wire Testing: Suggested testing Test method: A shunt or in-line device capable of measuring guy tensions from 5 to 25 (kips)

Shunt test method: Each guy wire test should be sampled a minimum of 3 times with results averaged If consistent results are not achieved relocating to a different location on each guy wire may be required to complete sampling.

Results expected.

A final report identifying concerns and issues found during inspections. Recommend actions to be taken and estimated cost for each action. Guy wire tension results adjusted or corrected to 60 deg Fahrenheit and documented in kilopounds (kips). A record of mast displacements with calculated total deviations for vertical alignment and vertical linearity

Vertical alignment:

DT = √(X12 + X22)

DT = Displacement Total X1 = Displacement of mast leg from vertical X2 = Adjacent measurement of displacement of mast leg from vertical

Vertical linearity:

DL = (XL + XR)/2

DL = Deviation from linearity XL = Lateral displacement left of reference line XR = Lateral displacement right of reference line