697DCK-19-R-00456 Amendment 0001.pdf
PDF 7 MB Posted
- Attached to
- Amendment 0001 Issued for ST. LOUIS, AIR TRAFFIC CONTROL TOWER (STL ATCT) REPLACEMENT OF HOT WATER BOILERS
- Solicitation number
- 697DCK-19-R-00456
About this file
697DCK-19-R-00456 Amendment 0001 (pdf)
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
1. CONTRACT ID CODE
5. PROJECT NO. (If applicable)2. AMENDMENT/MODIFICATION NO. 3. EFFECTIVE DATE 4. REQUISITION/PURCHASE REQ.NO.
PAGE OF PAGES
6. ISSUED BY CODE 7. ADMINISTERED BY (If other than Item 6)
8. NAME AND ADDRESS OF CONTRACTOR (No., street, county, State and ZIP Code)
CODE
9A. AMENDMENT OF SOLICITATION NO.
9B. DATED (SEE ITEM 11)
10A. MODIFICATION OF CONTRACT/ORDER NO.
10B. DATED (SEE ITEM 13)
CODE FACILITY CODE
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers
Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended , by one of the following methods: (a) By completing
Items 8 and 15, and returning is extended, is not extended.
12. ACCOUNTING AND APPROPRIATION DATA (If required.)
13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS. IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
(x) A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO THE AUTHORITY OF:
D. OTHER (Specify type of modification and authority) appropriation date, etc.) SET FORTH IN ITEM 14.
E. IMPORTANT: Contractor is not, is required to sign this document and return
ORDER NO. IN ITEM 10A.
1 2
0001 07/25/2019
FEDERAL AVIATION ADMINISTRATION
AAQ-500 - REGIONAL ACQUISITIONS
10101 HILLWOOD PARKWAY
FORT WORTH TX 76177-1524
AAQ520FTW-AFN
x
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
separate letter or telegram which includes a reference to the solicitation and amendment number. FAILURE OF YOUR ACKNOWLEDGEMENT TO BE RECEIVED AT
THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted , such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted ; or (c) By ___________ 1 x x
697DCK-19-R-00456
1 copies to the issuing office.
07/05/2019
(x)
Amendment 0001: The purpose of this amendment is to incorporate the attached Contractor
Questions/Government Responses and release the Site Visit Attendance Log.
The due date of this SIR has not been extended and remains 4:00PM CST on August 1, 2019.
No responses will be accepted after this deadline.
16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)15A. NAME AND TITLE OF SIGNER (Type or print)
15C. DATE SIGNED 16B. CONTRACT AUTHORITY 15B. CONTRACTOR/OFFEROR 16C. DATE SIGNED
(Signature of person authorized to sign) (Signature of Contracting Officer)
Katherine Fogle
Except as provided herein, all terms and conditions of the document referenced in Item 9 A or 10A, as heretofore changed, remains unchanged and in full force and effect .
FAA Screening Information Request (SIR) No. 697DCK-19-R-00456 Amendment 0001
1 Replacement of Hot Water Boilers at St. Louis Air Traffic Control Tower (STL ATCT)
Contractor’s Questions & Answers
1) Who taking ownership of the material and units being removed? Will the FAA keep the old units or does the GC need to depose of?
Answer: The contractor shall take ownership and remove all equipment and material replaced or removed for this contract.
2) It looks to me like no bid-bond is required per the 1442 for this project. I understand that a performance and payment bond are required. Can you confirm please that no bid bond is required?
Answer: Yes, no bid bond is required for this project.
3) Drawings call for the contractor to demo (1) of the existing boilers while the 2nd boiler is to remain in operation. We want to confirm that the existing 2 boilers share a common stack and if this is the case, will the contractor need to have a temporary stack for the old boiler while the contractor installs the new type of material for the condensing boiler stacks?
Answer: The existing boilers share a common stack. There are three floors (basement, first and second floor). The boilers are in the basement. Please see the attached four (4) pictures.
The facility has indicated they are able to go without heat provided by the boilers during warm periods (June – September). To reduce impact to the facility and the contractor, it is the FAA’s intention that the work be done during the June – September time frame.
Sign-In Sheet Pre-Proposal Site Visit
Solicitation #697DCK-l 9-R-00456
REPLACEMENT OF HOT WATER BOILERS AT ST. LOUIS AIR TRAFFIC CONTROL
TOWER (STL ATCT)
Bridgeton, MO
July 16, 2019 10:00am
The Federal Aviation Administration (FAA) assumes no responsibility for any conclusions or interpretations made by the contractor based on the information made available by the FAA. Nor does the FAA assume responsibility for any understanding reached or representation made concerning conditions, which can affect the work by any of its officers or agents before the execution of this contract, unless that understanding or representation is expressly stated in the contract.
Name Company/
Organization
Tiffany Weber (Via Phone if needed) FAA-Acquisitions-Contract Specialist
Garey Watkins
FAA A TSS Coordinator
Douglas McElfresh V Mechanical Engineer
Pat Johnston
General Engineer
/ MW Cole Construction Mike Cole I • I LLC_ Deon E Anderson C), \OJ\ cA. e, W h
I 'Alia'e)son & Sons
/_.. o,}, �-" ?>, v M-u..., Contracting LLC Ryan Goewert - '
"J::'.Yn.., hb�>� Integrated Facility Services
Nathan Ketterer
/IJ /:£,,
Kay Bee Electric
Joseph Melendez v
American Mechanical
Dennis Green "hr"� J. }/{; l - - Mumhv Mechanical 9regory Sinn v Corrigan Company Mechanical
Robert Roland v American Boiler & "' Mechanical
Tyler Roland V
' American Boiler & I Mechanical
Todd Van Buren ,J Guarantee Electrical Ken Huskey J Guarantee Electrical Charles M. Peters
V 7 I -e,'< CMP Commercial Q :,.l,...o.Jf"' I Construction, Inc.
Sherman McCoy V \. "(); t) l 0. V\ °' Resource Electrical
Svstems, Inc.
Contact Information (Email/Phone#)
J r
| 697DCK-19-R-00456 Amendment 0001 |
| T21-Contractors DRAFT Questions Answers |
| IMG_1574 |
| IMG_1576 |
| IMG_1631 |
| IMG_1646 |
| Site Visit Attendance Log-redacted |
File details come from the government source that posted it.