This document appears to be a FAQ (Frequently Asked Questions) related to a federal contract opportunity for a Concrete Walkway project at the ASTI MEB building in Anchorage, Alaska.

The key details are: The Federal Aviation Administration (FAA) has a requirement for a new concrete walkway approximately 300 LF. The contractor is responsible for all items of work per the attached Statement of Work (SOW). A site visit is scheduled for September 17th, 2024. This is a 100% Small Business Set-Aside under NAICS code 237310 with a $45M size standard. Proposals are due by October 7th, 2024 at 2pm Central Time. The FAQs provide additional details on requirements for topsoil and seeding, use of a boom pump, project timeline, sidewalk thickness and dimensions, and underground utilities in the work area.

View the file

Other files for this federal contract opportunity

Other files attached to Concrete Walkway, newest first.
File Type Posted
(SOW) ZAN ASTI Walkway 10.10.2024.pdf PDF
6973GH-24-R-00231 (3).pdf PDF
(SOW) ZAN ASTI Walkway 9.5.2024.docx DOCX document
Offeror Organizational Experience Form.pdf PDF
bildata.xlsx XLSX spreadsheet
Sol_6973GH-24-R-00231.pdf PDF
Wage Determination.txt TXT text file
Contractors Release Form DOT F 4220.4.doc DOC document
3.18-1.docx DOCX document

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

FAQ Anchorage, Alaska

1. Requirements for Topsoil and seed, is this something the vendors are going to be responsible for?

A: This is covered in the M.A.S.S Division -20 Earthwork, referenced in the (SOW) 10.0

REFERENCES AND STANDARDS

section -C. comment 10.1 Work site area see below.

3.0 Execution references div-20 Earthwork of the M.A.S.S which says on page 21 Before applying temporary or permanent seeding, Contractor shall prepare the surface to be seeded to reduce erosion potential and to facilitate germination and growth of vegetative cover. Contractor shall apply seed, maintain seeded areas, and reseed areas where growth of temporary vegetative cover is inadequate to stabilize disturbed ground. Contractor shall apply permanent seed, within the time periods required, at locations where seeding is indicated on the Drawings and after land-disturbing activity is permanently ceased.

10.1 Work Site Area: Upon finishing the construction, the Contractor must remove all construction debris, temporary structures, trailers, waste, and packaging materials from the work site area. The Contractor must remove any remaining construction materials and construction equipment from the site and thoroughly clean and restore storage areas to their original condition in kind before the final inspection.

2. Will it be permissible to use a boom pump to reach over all the overhead electrical when placing the concrete?

A: A boom pump was denied from the facility; however, they will be allowed to use a line pump.

3. Will this project be complete in summer?

A: Yes, May 2025 start time.

4. I see 4” and 6” thickness on sidewalks mentioned but can’t make out where the thicknesses apply?

A: 6” thick sidewalk continuous.

5. Is there a better drawing of the required sidewalks? The provided sketch seems to indicate distance (illegible mostly) but is missing width and thickness?

A: The width is 5’ wide x 6” deep per the M.A.S.S Detail. SOW has been updated to reflect the 6” deep. This is the only sketch available.

6. Is there a bond requirement?

A: No.

7. Do you know if there are any underground lines that contractors should worry about and work around? Or is it completely clear?

A: There are possible underground lines Some FAA utilities. Depending on where the sidewalks are going there is a gas like in the area that will require ENSTAR locate, this will be established before any work is to start for the awardee. JBER will handle water and sewer & their comm. No fee is charged by JBER for this service.