This document is an amendment to a solicitation for a contract to remove a solar panel wall and reconstruct the CMU wall of the Chattanooga Metropolitan Airport (CHA) Air Traffic Control Tower (ATCT) Base Building in Chattanooga, TN. The amendment replaces the previous Statement of Work (SOW) with a revised version dated 5/13/24 and adds a Q&A sheet as an addendum. The solicitation number is 6973GH-24-Q-00089, and it is set-aside for Small Businesses. Proposals are due by 4:00 PM Central Time on May 20, 2024, and the contract will be awarded to the lowest priced, responsive and responsible offeror. The solicitation includes instructions for submitting proposals, evaluation factors, and a site visit scheduled for May 7, 2024. All previous SOWs are now obsolete, and the new attachments are the revised SOW and the Q&A sheet.

View the file

Other files

Show all 14

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT

1. CONTRACT ID CODE

5. PROJECT NO. (If applicable)2. AMENDMENT/MODIFICATION NO. 3. EFFECTIVE DATE 4. REQUISITION/PURCHASE REQ.NO.

PAGE OF PAGES

6. ISSUED BY CODE 7. ADMINISTERED BY (If other than Item 6)

8. NAME AND ADDRESS OF CONTRACTOR (No., street, county, State and ZIP Code)

CODE

9A. AMENDMENT OF SOLICITATION NO.

9B. DATED (SEE ITEM 11)

10A. MODIFICATION OF CONTRACT/ORDER NO.

10B. DATED (SEE ITEM 13)

CODE FACILITY CODE

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers

Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended , by one of the following methods: (a) By completing

Items 8 and 15, and returning is extended, is not extended.

12. ACCOUNTING AND APPROPRIATION DATA (If required.)

13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS. IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.

(x) A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO THE AUTHORITY OF:

D. OTHER (Specify type of modification and authority) appropriation date, etc.) SET FORTH IN ITEM 14.

E. IMPORTANT: Contractor is not, is required to sign this document and return

ORDER NO. IN ITEM 10A.

1 2

0003 05/14/2024

AAQ-710 LOGISTICS CENTER ACQ

FAA AERONAUTICAL CENTER

PO BOX 25082

BLDG 014-AHQ, ROOM 233A

AAQ710-AFN

OKLAHOMA CITY OK 73125

x

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

separate letter or telegram which includes a reference to the solicitation and amendment number. FAILURE OF YOUR ACKNOWLEDGEMENT TO BE RECEIVED AT

THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted , such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted ; or (c) By ___________ 1 x x

6973GH-24-Q-00089

1 copies to the issuing office.

04/11/2024

(x)

The solicitation is amended to replace the SOW (SOW_CHA ATCT Beautification Solar

Wall_revised_5-2-24) with the SOW revised on 5/13/24 (SOW_CHA ATCT Beautification Solar

Wall_revised_5-13-24) and also add the Q&A Sheet with answers to all questions asked during this solicitation period. The Q&A sheet is now an addendum to the SOW.

New Attachments:

1. SOW_CHA ATCT Beautification Solar Wall_revised_5-13-24.pdf

2. QandA Sheet CHA Solar Wall_updated 5.13.24.pdf

All previous SOWs are obsolete.

Continued ...

16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)15A. NAME AND TITLE OF SIGNER (Type or print)

15C. DATE SIGNED 16B. CONTRACT AUTHORITY 15B. CONTRACTOR/OFFEROR 16C. DATE SIGNED

(Signature of person authorized to sign) (Signature of Contracting Officer)

Stephen N. Branch

Except as provided herein, all terms and conditions of the document referenced in Item 9 A or 10A, as heretofore changed, remains unchanged and in full force and effect .

ITEM NO. SUPPLIES/SERVICES QUANTITY UNIT UNIT PRICE AMOUNT

NAME OF OFFEROR OR CONTRACTOR

2 2

CONTINUATION SHEET

REFERENCE NO. OF DOCUMENT BEING CONTINUED PAGE OF

(A) (B) (C) (D) (E) (F)

6973GH-24-Q-00089/0003

All other terms and conditions of this solicitation remain unchanged.

LIST OF CHANGES:

Section J - List of Documents, Exhibits and Other Attachments was revised as follows.

Attachment List was revised as follows.

Table has been revised and now reads as follows:

ATTACHMENT TITLE DATE NO. OF

PAGES

1 SOW_CHA ATCT Beautification Solar Wall_revised_5-13-24 05/14/2024 34

2 Wage Determination_HamiltonTN_TN20240180 03/22/2024 6 3 Contractors Release Form DOT F 4220.4 04/10/2024 1 4 Uniform Bipartisan Infrastructure Law Report 04/10/2024 1 5 Offeror Organizational Experience Form 04/10/2024 2 6 SF-24_BidBond 05/09/2024 2 7 SF-25_PerformanceBond 05/09/2024 2 8 SF-25A_PaymentBond 05/09/2024 2 9 QandA Sheet CHA Solar Wall_updated 5.13.24 05/13/2024 4