This amendment modifies a federal solicitation to replace a tactical communications tower and shelter. The amendment extends the proposal due date from August 28 to August 31, 2023 at 4:00 PM Pacific Daylight Time in response to received requests for information. It also provides answers to questions that potential offerors submitted. The replacement tower and shelter are located in Republic, Washington for the Department of Transportation Federal Aviation Administration. No other changes are included in the amendment.
View the file
Other files
Show all 14
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
1. CONTRACT ID CODE
5. PROJECT NO. (If applicable)2. AMENDMENT/MODIFICATION NO. 3. EFFECTIVE DATE 4. REQUISITION/PURCHASE REQ.NO.
PAGE OF PAGES
6. ISSUED BY CODE 7. ADMINISTERED BY (If other than Item 6)
8. NAME AND ADDRESS OF CONTRACTOR (No., street, county, State and ZIP Code)
CODE
9A. AMENDMENT OF SOLICITATION NO.
9B. DATED (SEE ITEM 11)
10A. MODIFICATION OF CONTRACT/ORDER NO.
10B. DATED (SEE ITEM 13)
CODE FACILITY CODE
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers
Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended , by one of the following methods: (a) By completing
Items 8 and 15, and returning is extended, is not extended.
12. ACCOUNTING AND APPROPRIATION DATA (If required.)
13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS. IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
(x) A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO THE AUTHORITY OF:
D. OTHER (Specify type of modification and authority) appropriation date, etc.) SET FORTH IN ITEM 14.
E. IMPORTANT: Contractor is not, is required to sign this document and return
ORDER NO. IN ITEM 10A.
1 2
0003 08/24/2023
AAQ-721 LOGISTICS CENTER ACQ
FAA AERONAUTICAL CENTER
PO BOX 25082
BLDG 014-AHQ, ROOM 233A
AAQ0721-AFN
OKLAHOMA CITY OK 73125
AAQ-721 LOGISTICS CENTER ACQ
FAA AERONAUTICAL CENTER
PO BOX 25082
BLDG 014-AHQ, ROOM 233A
AAQ721-AFN
OKLAHOMA CITY OK 73125
x
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
separate letter or telegram which includes a reference to the solicitation and amendment number. FAILURE OF YOUR ACKNOWLEDGEMENT TO BE RECEIVED AT
THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted , such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted ; or (c) By ___________ 1 x x
6973GH-23-R-00166
1 copies to the issuing office.
07/27/2023
(x)
The purpose of Amendment 0003 is to extend the closing date for proposals from August 28 to
August 31, 2023 1600 PD. This amendment also includes the responses to the RFI's that were received from the interested vendors.
16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)15A. NAME AND TITLE OF SIGNER (Type or print)
15C. DATE SIGNED 16B. CONTRACT AUTHORITY 15B. CONTRACTOR/OFFEROR 16C. DATE SIGNED
(Signature of person authorized to sign) (Signature of Contracting Officer)
Bryon R. Nolan
Except as provided herein, all terms and conditions of the document referenced in Item 9 A or 10A, as heretofore changed, remains unchanged and in full force and effect .
LIST OF CHANGES:
The purpose of this amendment is to provide extend the deadline for proposals, and to provide response to the RFI's that have been received.
FIRST: The original due date for proposals was August 28, 2023 at 4 pm PD.
SECOND: The due date for proposals has been changed to August 31, 2023 at 4pm PD.
THIRD: The responses to the RFI's that have been received are provided.
All proposals, and attachments submitted must be submitted to only bryon.r.nolan@faa.gov.
No other changes.