SF-30_A0001_050521.pdf

PDF 250 KB Posted

Attached to
AMENDMENT A0002 UPDATE* ODA STC Certification & Association Project Management
Solicitation number
6973GH-21-R-00097
Issued by

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods:

(a) By completing items 8 and 15, and returning or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment your desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT 1. CONTRACT ID CODE

2. AMENDMENT/MODIFICATION NO. 3. EFFECTIVE DATE 4. REQUISITION/PURCHASE REQ. NO. 5. PROJECT NO. (If applicable)

7. ADMINISTERED BY (If other than Item 6) CODE

(SF-30) FAA Template No. 11 (8/97)

FACILITY CODE

9A. AMENDMENT OF SOLICITATION

NO.

9B. DATED (SEE ITEM 11)

10A. MODIFICATION OF CONTRACT/ORDER NO.

10B. DATED (SEE ITEM 13)

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers is extended, is not extended.

12. ACCOUNTING AND APPROPRIATION DATA (If required) copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;

13. THIS ITEM ONLY APPLIES TO MODIFICATION OF CONTRACTS/ORDERS.

IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.

CHECK ONE A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT ORDER NO.

IN ITEM 10A.

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).

C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER (Specify type of modification and authority)

Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

15C. DATE SIGNED

15A. NAME AND TITLE OF SIGNER (Type or print)

16C. DATE SIGNED

16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

PAGE OF PAGES

6. ISSUED BY CODE

8. NAME AND ADDRESS OF CONTRACTOR (No., street, county, State and ZIP Code) (X)

CODE

15B. CONTRACTOR/OFFEROR

(Signature of person authorized to sign)

16B. UNITED STATES OF AMERICA

(Signature of Contracting Officer)

OMB Control No. 2120-0595

p. 1

A0001

AAQ0732-AFN

Kathleen D. Islas, Contracting Officer kathleen.d.islas@faa.gov, (405) 954-8534

The purpose of this Amendment (A0001) is to provide the Vendor Questions and Government Answers (attached) to interested industry providers of this requirement.

AAQ-732 TRAINING & AVIATION ACQ

FAA AERONAUTICAL CENTER

PO BOX 25082

BLDG 014-AHQ, ROOM 233A

OKLAHOMA CITY OK 73125

OFFEROR 6973GH-21-R-00097

05/05/2021

04/13/2021

05/05/2021

Solicitation Section Date Received Question FAA Response

Section J‐Attch 1, PWS Section 2.3.1 & 2.4.1 4/21/2021

Block 5 within the CDRL specifies the Contract Reference as “PWS 2.3.1”.

No such line item exists. Does “PWS 2.4.1” fit more appropriately within

Block 5?

Yes, the CDRL is wrong. The correct PWS reference is 2.4.1 and 2.4.2. A corrected CDRL will be posted to the SIR/RFO announcement as an amendment.

COR 4/21/2021

Is the contractor expected to generate the design and substantiating data of the MMS? If not, do separate solicitations exist for the remaining work‐scopes?

No. The contractor should submit their proposal to the technical requirement as specified in the SIR/RFO and PWS.

COR 4/21/2021

Is the contractor expected to fabricate and install the MMS? If not, do separate solicitations exist for the remaining work‐scopes?

No. The FAA will provide a MMS for installation .

The contractor should submit their proposal to the technical requirement as specified in the SIR/RFO and PWS.

Section J‐Attch 1, PWS 9.1 4/22/2021

In reference to the requirement provided in the PWS Section 9.1

“Organizational Qualifications” ‐‐ Contractor must demonstrate previous

STC certification on part 25 75,000 lbs. MTW or less; and Part 23 12,500 lbs. MTW or less within the last 5 years from proposal date. Is the "and" a hard requirement?

Yes

PWS 4/23/2021

In addition to our ODA UMs making all necessary reviews to the technical data as described within the PWS and finding compliance to the airworthiness standards, are there any additional engineering design support requirements expected of the contractor?

No

SIR/RFO Section L.1 4/22/2021

Table L.1 within the SIR outlines the required documents necessary for a complete proposal. I do not see the CDRL listed within the table so should we assume that the CDRL provided is not necessary for submission?

A “CDRL” is a “Contract Data Requirement List” that provides instructions for how the data as identified in the CDRL is to be submitted. There is no proposal submission for this artifact as it is an attachment to the contract document and is a requirement for the contract upon award.

SIR/RFO Section L.1 4/23/2021

Table L.1 Volume I Tab B specifies Contract Documentation for SIR

Sections A‐K. AMS 3.2.2.3‐15 requires the offeror to sign indicating their authorization to negotiate, but is not included in the table. Should we assume this is not necessary for submission?

Section A is the form page of the solicitation that becomes the signature page for the contract document to the vendor selected for award. It is the first page of the SIR/RFO. It is required to be signed by the offeror upon submission of the proposal.

SIR/RFO Section L.1 4/23/2021

Table L.1 Volume IV Tab D specifies that the offerors must submit the Past

Performance Questionnaires within the proposal. Within the Past

Performance Survey document, it specifies when completed, that it should be submitted by the reference to the contracting officer. Because the proposal requires the questionnaires to be submitted, do we ask the reference to also send us a copy?

The FAA Contracting Officer (CO) requests the reference to submit the PPQ directly to the CO.

Offerors may, upon their own discretion, request the reference to send a copy of the completed PPQ directly to Offeror. The is under no requirement by the FAA to send the Offeror a copy of the completed PPQ. Per the Section L.14, “Past

Performance Factor” – “the offeror is required to include with their submitted proposal a completed copy of the front page of each attached survey that includes contact information for whom past performance was accomplished for.”

5/5/2021

Who do you intend to be responsible for the creation of the following reports (as required):

‐ Lighting & Bonding

‐ Damage Tolerance/Fatique

‐ Decompression

‐ Electrical Load Data/Analysis

‐ Fire Protection

‐ Flutter/Vibration

‐ Stress

‐ System Safety

‐ Weight and Balance/Weight & Arm

The Contractor is the ODA so they will be responsible for writing the reports and issuing their approval to find compliance.

All test plans and engineering will be completed by the FAA engineering team. The ODA will ensure the test plans are adequate and include all the appropriate rules for testing.