Statement of Work

SRQ RCAG

JCN 1400255

The SRQ RCAG is a 16 x 36’ CMU block building with a standalone EG shelter on site.

For this project the following is proposed to the exterior of the building.

· Replace existing roof with 60 MIL Durolast Single Ply roofing system.

· Power wash, prime and paint the exterior of the building

· Add 8’ x 14’ x 6” thick concrete pad outside of the entrance to both the equipment and telco rooms

· Remove existing awning and add a new roof structure over newly installed stoop with gutters and downspouts.

· Remove exhaust vent and re-block wall

· Replace existing 12” wood Fascia boards with PVC fascia

· Re-install lightning protection to the building per FAA Order 019F.

· Remove weeds, spray ground clear and add additional gravel to the site.

· Add two exterior LED floodlights on outside corners of building

· Provide funds to SSC for new door for JBOX for antennas and hardware for the tower and new locks for doors.

· Clean and paint 4 J-box’s

The following work shall be performed on the interior of the building:

Replace 9 1 x4 fluorescent lights with 9 new fluorescent lights with the solid prismatic lenses in equipment room. Additionally there are 1 1x4 each in the storage area and telco room, replace each of these with 2 2 x4 with solid prismatic lenses.

Remove carpet and tile throughout the building and install in tile with new cove bases throughout the facility.

-Install lighted LED exit / emergency signs with emergency lighting at the equipment room and telco room entrances.

At two locations inside the facility the new BARD units replaced existing thru the wall AC units. Remove plywood and rebrick opening and reinstall vent. Repaint as necessary. Additionally, remove and repaint on the exterior of the facility at these locations.

Disconnect is located too close to fence. Best solution is too turn disconnect 180 degrees and mount on new stainless steel unistrut rack along with meter located on opposite side. This will require coordination with the power company

Paint exterior of EG shelter with Dulux Metalsheild paint. Paint doors and building the same color as the equipment building.

Remove floor tiles, cove base and replace subfloor where needed. The floor titles have been tested and asbestos materials is present. Reinstall new flooring, sheet vinyl and cove base for entire shelter.

Remove and install new (5) 1 x 4 LED lights with solid prismatic lenses. Install new LED light on exterior of shelter door.

Remove exhaust fan and re-block wall

Other Miscellaneous work that may need to performed on this facility includes the installation of 2 new TVSS’s and possible grounding upgrade to interior of facility.

image6.png image7.png image8.png image9.png image1.png image2.png image3.png image4.png image5.png