ID Task Mode
Task Name Duration Start Finish
1 Salmon RCLT/AWOS‐Tower Replacement Project
65 days Mon 7/1/19 Fri 9/27/19
2 Contract Award 0 days Mon 7/1/19 Mon 7/1/19 3 Contract Approval 4 wks Mon 7/1/19 Fri 7/26/19 4 Work Schedule 2 wks Mon 7/1/19 Fri 7/12/19 5 Notice To Proceed 0 days Fri 7/26/19 Fri 7/26/19 6 Key Submitals 10 days Mon 7/29/19Fri 8/9/19 7 Tower Structure Design 2 wks Mon 7/1/19 Fri 7/12/19 8 Tower foundation design1 wk Mon 7/29/19Fri 8/2/19 9 Ice bridge design 3 days Mon 7/29/19Wed 7/31/19 10 Concrete mix design 3 days Mon 8/5/19 Wed 8/7/19 11 Contractor mobilization 1 wk Mon 7/29/19Fri 8/2/19 12 Fabrication 15 days Mon 7/22/19Fri 8/9/19 13 Tower fabrication & transportation to the 3 wks Mon
7/22/19 Fri 8/9/19
14 Ice bridge fabrication and transportation
1 wk Thu 8/1/19 Wed 8/7/19
15 Construction 23 days Mon 8/5/19 Wed 9/4/19 16 Construction Contractor
Tasks 23 days Mon 8/5/19 Wed 9/4/19
17 Site Preparation 1 day Mon 8/5/19 Mon 8/5/19 18 Foundation/Ground
EES Excavation 2 days Tue 8/6/19 Wed 8/7/19
19 Tower foundation/ground EES construction
3 days Thu 8/8/19 Mon 8/12/19
20 Ice bridge foundation 1 day Thu 8/8/19 Thu 8/8/19 21 Backfill 1 day Tue 8/13/19 Tue 8/13/19 22 Tower Installation 5 days Tue 8/20/19 Mon 8/26/19 23 Ice Bridge installation 1 day Fri 8/9/19 Fri 8/9/19 24 J‐Box Installation 1 day Tue 8/27/19 Tue 8/27/19 25 Heliax cable pull (JB‐JB2 days Wed 8/28/19Thu 8/29/19 26 Tower lightning protection 2 days Tue 9/3/19 Wed 9/4/19
27 RCL Contractor tasks 2 days Tue 8/27/19 Wed 8/28/19 28 Waveguide Installation2 days Tue 8/27/19 Wed 8/28/19 29 Microwave dish installation 2 days Tue 8/27/19 Wed
8/28/19 30 SSC/FAA Tasks 5 days Thu 8/29/19 Wed 9/4/19 31 AWOS Antenns installa2 days Thu 8/29/19 Fri 8/30/19 32 RCLT and AWOS Testin3 days Mon 9/2/19 Wed 9/4/19 33 Demolition 5 days Thu 9/5/19 Wed 9/11/19 34 Ice‐bridge demo 1 day Thu 9/5/19 Thu 9/5/19 35 Wooden tower‐Demo 2 days Fri 9/6/19 Mon 9/9/19 36 Final Site Preparation 2 days Tue 9/10/19 Wed 9/11/19 37 Delivery and Closure 7 days Thu 9/12/19 Fri 9/20/19 38 Inspection and Punch list1 day Thu 9/12/19 Thu 9/12/19 39 Implementing Punch list 5 days Fri 9/13/19 Thu 9/19/19 40 Final Inspection 1 day Fri 9/20/19 Fri 9/20/19 41 Deliver 0 days Fri 9/20/19 Fri 9/20/19 42 Closing 0 days Fri 9/20/19 Fri 9/20/19
7/1
7/26
9/20 9/20
T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S 3, '19 Jun 30, '19 Jul 7, '19 Jul 14, '19 Jul 21, '19 Jul 28, '19 Aug 4, '19 Aug 11, '19 Aug 18, '19 Aug 25, '19 Sep 1, '19 Sep 8, '19 Sep 15, '19 Sep 22, '19
Task
Split
Milestone
Summary
Project Summary
Inactive Task
Inactive Milestone
Inactive Summary
Manual Task
Duration-only
Manual Summary Rollup
Manual Summary
Start-only
Finish-only
External Tasks
External Milestone
Deadline
Progress
Manual Progress
Project: SMN Schedule Date: Tue 2/12/19