6973GH-19-R-00030-Install a new GFM fiberglass building WST RTR, Westerly Airport, RI.
Site Walkthrough Questions
1. How much will the new building weight and when will it be ready for delivery?
The new building will weigh about 9800lbs and will be ready in mid-March.
2. Who will unload building and apply for obstruction evaluation?
The FAA will obtain crane to off load and apply for obstruction evaluation (7460-1). The FAA will only provide one off load. If foundation is not ready for building on agreed upon date and time of delivery, the contractor will be responsible for moving and storing of shelter.
3. Who is responsible for FAA equipment move and cutover?
The FAA will move all electronic equipment and cutover of equipment. The contractor shall provide 2 movers for 8 hours to assist in moving of equipment.
4. Will work requiring electrical or telco outage be night work?
The Providence TRACON uses this RTR facility. Depending on the activities on the date and time of the requested outage, night work may be necessary. However, since the project will be performed during lower traffic season, night work in not likely. The WST airport is a 24 hour airport. The ASOS facility and airport Beacon light are powered by the existing building serves this airport. Again, since this is scheduled for a low traffic season, night work in unlikely.
5. Since removal of existing building is part of the contract, how much does the existing building weight?
The existing building weight approximately 8000 lbs.
6. What is the laydown area?
The FAA request the area below from the Airport Authority. Approval is pending.
7. What are the telco requirements?
Add to the bid package the circled items:
New telco pipe from new handhole to new building. The Telephone Company will install the telco line separately.