SCOPE OF WORK

Tower Replacement QPO RCAG Barnegat, New Jersey

1.0 GENERAL

All work is on FAA property located near Barnegat, NJ. There’s a paved driveway & parking area, equipment building, 4 antenna towers, and other items located on the site. The FAA wants to replace existing towers with a single 16’x16’ platform tower, while keeping facility in service.

2.0 SCOPE OF WORK

The Contractor shall perform the following work:

1. Provide ground mapping for existing cable on site.

2. Provide soil boring and design for one new tower 40’ tall 16’x16’ platform on site.

3. Demolish and remove Tower 2 before platform installation, as shown in drawings.

4. Install one new 40’ free standing tower with a 16’x16’ platform, stairway with safety rail, cable ladder, obstruction light, lightning terminals, and 8 antenna mounts.

5. Install grounding protection for new tower with down conductors to new counterpoise for tower.

Attached new tower counterpoise systems to existing system.

6. Install 1 ice bridge overhead cable system from the building to the new tower. This will accommodate 20 runs of LMR-600 DB and power conduit run for tower.

7. Install new openings to back side of building to accommodate 4” entry boots as shown in drawings.

8. Provide and install 20 runs of new LMR-600 cable from new tower junction box to RTR building ground bar location as shown in drawings. FAA to terminate cables.

9. Provide LMR -400 for cable runs from Tower junction box to antennas and from shelter ground bar location to communication racks.

10. Demolish remaining existing towers and associated hardware, cables, and junction boxes after

FAA successful cutover from old towers to new platform. (All existing towers to be demolished to 2’ below grade.)

11. Plug penetrations and restore existing J-box areas to surrounding conditions after J-box and cable removal.

12. Restore tower areas to surrounding conditions.

13. Resurface access road and parking area according to drawings and specs.

2.1 GENERAL REQUIREMENTS

a.) Contractor shall repair any damage done by him to any entity, at his cost. Contractor shall be covered by minimum locally required liability insurance.

b.) Contractor must provide FAA with a safety and security plan before any work begins. Plan will include procedures for accident prevention, emergency procedures, and phone number & map to nearest emergency medical facility.

c.) All work shall be coordinated, scheduled, & approved by FAA COR.

d.) Contractor will be continuously monitored by an FAA Resident Engineer during all work hours.

d.) Contractor's Superintendent shall be present at the work site during all times work is performed. Superintendent shall carry a cell phone and, be prepared to make and receive calls to & from the FAA at all times while on work site.

e.) All materials used must be approved by the FAA before installation. Contract will submit information on all items given in Part 3.0 below.

2.2 WORK HOURS AND CONDITIONS

a.) Work will only be done during daylight hours between 7:00AM to 5:00PM. Mon thru Fri.

b.) Weekend work will only be authorized if necessary due to weather. No overtime will be allowed c.) Contractor will report & coordinate each days work in advance with FAA COR and FAA technician that is trained to operate and repair RCAG equipment.

3.0 SUBMITTALS

All plans, materials, and information will meet FAA approval before NTP. Submittals will include the following:

a.) Construction schedule b.) List of workers and subcontractors c.) Bonding & Insurance d.) Construction materials disposal plans & permits e.) Safety and Health Plan f.) Fall Protection Safety Plan g.) Crane Set-up/Operation Plan h.) Soil boring analysis data and foundation recommendations i.) Tower Fabrication: design, layout, shop drawings, antenna mounts, etc. (foundation design- NJ State PE stamped drawings / tower design– PE stamped within continental US.)

j.) Junction-boxes / type / make-model / size / etc.

k.) Conduits & LMR cables, connectors, etc. to be supplied.

l.) Any and all materials to be provided on this project.

m.) All others Per COR’s request

4.0 PRE BID SITE VISIT

The Contractor is encouraged to carefully examine areas of the proposed work, to see first hand the extent of work involved. The submission of a proposal will be considered evidence that the bidder has made such examination and is satisfied as to the conditions to be encountered in performing the work. All site visits must be coordinated in advance. The FAA Contracting Officer will provide a date for one official site visit with the Engineer. If any other visits are needed, Contractor must give FAA at least five days advance notice before appearing on site.

All visitors must be escorted by an employee of FAA or, other authorized personnel.

5.0 DRAWINGS

1. Attachment A: QPO-1305290

5.1 SPECIFICATIONS

1. Specifications Attached

6.0 LOCATION OF WORK

200 Warren Grove Rd., Barnegat, NJ 08005 Ocean County, New Jersey

LAT/LON: 39.779232 N, 74.341734 W

7.0 CONTACTS

Cody Decker, FAA Engineering James Beam, FAA SSC Manager AJW-2E13A, N.E. Regional Office AJW-WEE51-AIY 1200 District ave. Building 284 ACY Tower Burlington, MA 01803 Atlantic City Int Airport, 470-585-1399 Atlantic City, NJ 08405 E-mail: Cody.Decker@faa.gov w: 609-677-9620 c: 6094641367

E-mail: James.Beam@faa.gov

Christopher Plant, FAA SSC Tech Chris Hollingsworth, FAA SSC Tech

AJW-WEE51-AIY AJW-WEE51-AIY

Building 284 ACY Tower Building 284 ACY Tower Atlantic City Int Airport, Atlantic City Int Airport, Atlantic City, NJ 08405 Atlantic City, NJ 08405 w: 609-677-9614 c: 609-464-1368 w: 609-677-9614 ext. 166 c: 609-417-8653 E-mail: Christopher.Plant@faa.gov E-mail: Chris.Hollingsworth@faa.gov

8.0 FOR FAA USE ONLY

JCN: 1305290 JON: 1218SO0086

< ~ END OF DOCUMENT ~ >