6973GH-23-R-00216-0001.pdf

PDF 173 KB Posted

Attached to
BIL FUNDED**** Relocate Security Gate and Add Additional Fencing
Solicitation number
6973GH-23-R-00216
Issued by

About this file

This amendment modifies a solicitation for a federal contract to relocate a security gate and add additional fencing at a airport. The Federal Aviation Administration is seeking proposals to construct a new security gate and install additional perimeter fencing at T.F. Green Airport in Rhode Island. Offerors must submit a proposal guarantee, performance bond, and payment bond with their responses. The deadline for proposals is August 25, 2023. The statement of work, facility drawings, wage determinations, and experience requirements are provided as attachments.

View the file

Other files

File Type Posted
6973GH-23-R-00216 P00002.pdf PDF
Payment Bond.pdf PDF
Bid Bond.pdf PDF
Performance Bond.pdf PDF
Experience Information Form.pdf PDF
PVD-ATCT Security Gate Drawing.pdf PDF
SIR 6973GH-23-R-00216.pdf PDF
Wage Determination_ RI20230001 06.30.2023.pdf PDF
SOW - PVD ATCT Security Gate.pdf PDF
Uniform Bipartisan Infrastructure Law Report.xlsx XLSX spreadsheet

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT

1. CONTRACT ID CODE

5. PROJECT NO. (If applicable)2. AMENDMENT/MODIFICATION NO. 3. EFFECTIVE DATE 4. REQUISITION/PURCHASE REQ.NO.

PAGE OF PAGES

6. ISSUED BY CODE 7. ADMINISTERED BY (If other than Item 6)

8. NAME AND ADDRESS OF CONTRACTOR (No., street, county, State and ZIP Code)

CODE

9A. AMENDMENT OF SOLICITATION NO.

9B. DATED (SEE ITEM 11)

10A. MODIFICATION OF CONTRACT/ORDER NO.

10B. DATED (SEE ITEM 13)

CODE FACILITY CODE

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers

Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended , by one of the following methods: (a) By completing

Items 8 and 15, and returning is extended, is not extended.

12. ACCOUNTING AND APPROPRIATION DATA (If required.)

13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS. IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.

(x) A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO THE AUTHORITY OF:

D. OTHER (Specify type of modification and authority) appropriation date, etc.) SET FORTH IN ITEM 14.

E. IMPORTANT: Contractor is not, is required to sign this document and return

ORDER NO. IN ITEM 10A.

1 2

0001 08/25/2023

AAQ-710 LOGISTICS CENTER ACQ

FAA AERONAUTICAL CENTER

PO BOX 25082

BLDG 014-AHQ, ROOM 233A

AAQ710-AFN

OKLAHOMA CITY OK 73125

x

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

separate letter or telegram which includes a reference to the solicitation and amendment number. FAILURE OF YOUR ACKNOWLEDGEMENT TO BE RECEIVED AT

THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted , such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted ; or (c) By ___________ 1 x x

6973GH-23-R-00216

1 copies to the issuing office.

08/25/2023

(x)

The purpose of this amendment is to incorporate the Proposal and Performance Bonds as well as the Proposal Guarantee requirement.

16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)15A. NAME AND TITLE OF SIGNER (Type or print)

15C. DATE SIGNED 16B. CONTRACT AUTHORITY 15B. CONTRACTOR/OFFEROR 16C. DATE SIGNED

(Signature of person authorized to sign) (Signature of Contracting Officer)

Samantha A. Pearce

Except as provided herein, all terms and conditions of the document referenced in Item 9 A or 10A, as heretofore changed, remains unchanged and in full force and effect .

X

LIST OF CHANGES:

Section I - Contract Clauses was revised as follows.

Clause List was revised as follows.

Clause 3.4.1-1 is incorporated as follows:

3.4.1-1 PROPOSAL GUARANTEE (JAN 2017)

(a) Offerors must furnish a proposal guarantee in the form of a proposal bond, a postal money order, a certified or cashier's check, an irrevocable letter of credit, or United States bonds or notes with a maturity of less than five years.

(b) The required amount of the proposal guarantee is 100 percent of total proposal price.

(c) The Contracting Officer will return proposal guarantees, other than proposal bonds:

(1) To unsuccessful offerors as soon as possible after an award decision is made; and

(2) To the successful offeror after it signs the contract and submits acceptable bonds required under the contract.

(d) If the successful offeror fails to sign the contract or submit the required bonds within the time specified by the Contracting Officer, the contract may be terminated for default.

(e) If the contract is terminated for default, the offeror is liable for any cost of acquiring the work in excess of its proposed price, and the guarantee is available to offset the difference. However, the guarantee is not an exclusive remedy.

Clause 3.4.1-4 is incorporated as follows:

3.4.1-4 PERFORMANCE BOND REQUIREMENTS (JAN 2017)

(a) The contractor is required to submit a performance bond in a penal amount equal to 100 percent of the contract price, but for this contract the amount required by the Contracting Officer is the total amount of contract award..

(b) The bond must be executed on specified forms, and sureties must be acceptable to the Federal Aviation Administration. Corporate sureties must appear on the list in Treasury Circular 570, and the amount of the bond may not exceed the underwriting limit stated for the surety on that list.

(c) Failure to submit an acceptable bond may be cause for termination of the contract for default.

(End of clause)

Clause 3.4.1-5 is incorporated as follows:

3.4.1-5 PAYMENT BOND REQUIREMENTS (JAN 2018)

(a) The contractor is required to submit a payment bond in the penal amount of 100 percent within the time required by the Contracting Officer.

(b) The bond must be executed on the forms attached to this SIR, and sureties must be acceptable to the Federal Aviation Administration. Corporate sureties must appear on the list in Treasury Circular 570, and the amount of the bond may not exceed the underwriting limit stated for the surety on that list.

(c) Failure to submit an acceptable bond may be cause for termination of the contract for default.

Section J - List of Documents, Exhibits and Other Attachments was revised as follows.

Attachment List was revised as follows.

Table has been revised and now reads as follows:

ATTACHMENT TITLE DATE NO. OF

PAGES

1 SOW - PVD ATCT Security Gate 06/05/2023 76 2 PVD-ATCT Security Gate Drawing 08/25/2023 1 3 Wage Determination_ RI20230001 06.30.2023 06/30/2023 15 4 Experience Information Form 08/25/2023 1 5 Uniform Bipartisan Infrastructure Law Report 08/25/2023 4 6 Bid Bond 08/25/2023 2 7 Payment Bond 08/25/2023 2 8 Performance Bond 08/25/2023 2

File details come from the government source that posted it. Updated .