J.2_Schedule_of_Rates.xlsx

XLSX spreadsheet 11 KB Posted

Attached to
Mobile Concrete Technology Center (MCTC) Program Federal contract opportunity
Solicitation number
693JJ320R000004
Issued by
Department of Transportation Federal Highway Administration

About this file

This document contains a schedule of rates and a presolicitation notice for a federal contract opportunity. The schedule of rates provides fully burdened hourly rates for various labor categories over a potential 60 month period of performance including a 24 month base period and three 12 month option periods. The labor categories include project manager, senior engineer, staff engineer, senior laboratory technician, and laboratory technician.

The presolicitation notice is for solicitation number 693JJ320R000004 to procure technical support services for the Mobile Concrete Technology Center Program. The objective is to provide technical assistance to stakeholders on concrete pavement technologies, test procedures, and quality initiatives. The potential 60 month single award firm fixed price contract includes a base period of two years and three option periods of one year each. The contractor must provide all necessary personnel, materials, equipment, and facilities to support tasks associated with the program. The solicitation is anticipated to be released in fall 2019 as an 8(a) small business set-aside on www.fbo.gov.

Attachment J.2 Schedule of Rates

View the file

Other files for this federal contract opportunity

Other files attached to Mobile Concrete Technology Center (MCTC) Program, newest first.
File Type Posted
Q&A_11-20-2019.pdf PDF
J.3_Disclosure_of_Lobbying_Activities.pdf PDF
J.4_Non-disclosure_Agreement.pdf PDF
693JJ320R000004.pdf PDF
J.1_Labor_Category_Descriptions.pdf PDF

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

sheet1

J.2 Schedule of Rates
Billing Category (Technical Support for the MCTC Program. Tasks 1, 2, and 3)Base Period (24 Months)Option Period I (12 Months)Option Period II (12 Months)Option Period III (12 Months)
Fully Burdened Hourly RateEstimated HoursTotal CostFully Burdened Hourly RateEstimated HoursTotal CostFully Burdened Hourly RateEstimated HoursTotal CostFully Burdened Hourly RateEstimated HoursTotal Cost
Project Manager$3,920$$1,960$$1,960$$1,960$
Senior Engineer$2,400$$1,200$$1,200$$1,200$
Staff Engineer$3,920$$1,960$$1,960$$1,960$
Senior Laboratory Technician$3,920$$1,960$$1,960$$1,960$
Laboratory Technician$3,920$$1,960$$1,960$$1,960$
SUBTOTAL0000