This document is a Results of Bid Opening report from the Federal Highway Administration's Eastern Federal Lands Highway Division for a construction project at Cherokee National Forest. The bid opening occurred on August 13, 2026, at 2:00 p.m. local time in Ashburn, VA, for Solicitation No. 693C73-26-B-000015, Project TN ERFO FS CHRKE804 2020-2(2). The performance period for completion of Schedule A is 588 calendar days.
Nine contractors submitted bids for this construction project, with total prices ranging from $5,475,940.00 to $10,583,302.00. Adams Contracting Co. Inc. submitted the lowest bid at $5,475,940.00, followed by Apex Construction Group, LLC at $6,184,884.36, Howard W. Pence, Inc. at $6,893,649.00, Central Southern Construction Corp. at $7,383,272.40, Estes Bros Const., Inc. at $7,399,573.11, Mendez Group, Inc. at $7,576,616.42, Williams Construction and Cabinetry, Inc. at $8,154,818.40, Road Worx, Inc. at $8,600,034.20, and C-A Native Construction, Inc. at $10,583,302.00. The Engineer's Estimate was $8,786,562.41. The document notes that the Eastern Federal Lands Highway Division is conducting a thorough review and verification of all information, and the low bidder will be contacted once this review is completed. This abstract is not indicative of the final award determination.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Federal Highway Administration
Eastern Federal Lands Highway Division
Results of Bid Opening
Cherokee National Forest
PROJECT: TN ERFO FS CHRKE804 2020-2(2)
SOLICITATION NO. 693C73-26-B-000015
August 13, 2026 at 2:00 p.m.
Ashburn, VA
*EFL is reviewing and verifying all information. This abstract is not indicative to who will receive the award.
The low bidder will be contacted once a thorough review has been completed.
FEDERAL HIGHWAY ADMINISTRATION
EASTERN FEDERAL LANDS HIGHWAY DIVISION
BID OPENING for SOLICITATION NO. 693C73-25-B-000015
Project: TN ERFO FS CHRKE804 2020-2(2)
August 13, 2026, 2:00 p.m. local time
The performance period for the completion of Schedule A is 588 calendar days.
BIDDER SCHEDULE TOTAL TOTAL PRICE
Adams Contracting Co. Inc. SCHEDULE A
$5,475,940.00
SCHEDULE A =
$5,475,940.00
Apex Construction Group, LLC SCHEDULE A
$6,184,884.36
SCHEDULE A =
$6,184,884.36
C-A Native Construction, Inc. SCHEDULE A
$10,583,302.00
SCHEDULE A =
$10,583,302.00
Central Southern Construction Corp. SCHEDULE A
$7,383,272.40
SCHEDULE A =
$7,383,272.40
*EFL is reviewing and verifying all information. This abstract is not indicative to who will receive the award.
The low bidder will be contacted once a thorough review has been completed.
BIDDER SCHEDULE TOTAL TOTAL PRICE
Estes Bros Const., Inc. SCHEDULE A
$7,399,573.11
SCHEDULE A =
$7,399,573.11
Howard W. Pence, Inc. SCHEDULE A
$6,893,649.00
SCHEDULE A =
$6,893,649.00
Mendez Group, Inc. SCHEDULE A
$7,576,616.42
SCHEDULE A =
$7,576,616.42
Road Worx, Inc. SCHEDULE A
$8,600,034.20
SCHEDULE A =
$8,600,034.20
*EFL is reviewing and verifying all information. This abstract is not indicative to who will receive the award.
The low bidder will be contacted once a thorough review has been completed.
FEDERAL HIGHWAY ADMINISTRATION
EASTERN FEDERAL LANDS HIGHWAY DIVISION
BID OPENING for SOLICITATION NO. 693C73-25-B-000015
Project: TN ERFO FS CHRKE804 2020-2(2)
August 13, 2026, 2:00 p.m. local time
The performance period for the completion of Schedule A is 588 calendar days.
BIDDER SCHEDULE TOTAL TOTAL PRICE
Williams Construction and Cabinetry, Inc.
SCHEDULE A
$8,154,818.40
SCHEDULE A =
$8,154,818.40
Engineer’s Estimate SCHEDULE A
$8,786,562.41
SCHEDULE A =
$8,786,562.41
*EFL is reviewing and verifying all information. This abstract is not indicative to who will receive the award.
The low bidder will be contacted once a thorough review has been completed.
FEDERAL HIGHWAY ADMINISTRATION
EASTERN FEDERAL LANDS HIGHWAY DIVISION
BID OPENING for SOLICITATION NO. 693C73-25-B-000015
Project: TN ERFO FS CHRKE804 2020-2(2)
August 13, 2026, 2:00 p.m. local time
The performance period for the completion of Schedule A is 588 calendar days.
| Slide 1 |
| Slide 2: FEDERAL HIGHWAY ADMINISTRATION EASTERN FEDERAL LANDS HIGHWAY DIVISION BID OPENING for SOLICITATION NO. 693C73-25-B-000015 Project: TN ERFO FS CHRKE804 2020-2(2) August 13, 2026, 2:00 p.m. local time The performance period for the completion of Sc |
| Slide 3: FEDERAL HIGHWAY ADMINISTRATION EASTERN FEDERAL LANDS HIGHWAY DIVISION BID OPENING for SOLICITATION NO. 693C73-25-B-000015 Project: TN ERFO FS CHRKE804 2020-2(2) August 13, 2026, 2:00 p.m. local time The performance period for the completion of Sc |
| Slide 4: FEDERAL HIGHWAY ADMINISTRATION EASTERN FEDERAL LANDS HIGHWAY DIVISION BID OPENING for SOLICITATION NO. 693C73-25-B-000015 Project: TN ERFO FS CHRKE804 2020-2(2) August 13, 2026, 2:00 p.m. local time The performance period for the completion of Sc |
File details come from the government source that posted it. Updated .