This document contains Questions and Answers related to Federal Highway Administration (FHWA) Request for Quotation No. 693C7324Q000028 for a Wetland/Waters of the U.S. Delineation and Report at the U.S. Fish & Wildlife Refuge, Upper Mississippi National Wildlife Refuge, La Crosse District Counties, Wisconsin and Town of Shelby, WI.
The solicitation is for a wetland/waters delineation and report, which includes constructing a new access road and parking area and installing railroad crossing signals along State Highway 35. The work involves grading, aggregate surface course, asphalt concrete pavement, aggregate shoulders, a culvert, topsoil, turf establishment, and a railroad crossing signal with gate. Award may be based on best value to the government, considering proposed methods, qualifications, and experience, not solely on lowest cost. The contractor must use the Department of Transportation's eInvoicing system to submit invoices. The preferred field delineation is in fall 2024 before mid-October, if possible. Qualifications can be submitted in PDF format along with pricing.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
QUESTIONS & ANSWERS – RELATING TO FHWA REQUEST FOR QUOTATION NO.
693C7324Q000028
Q1. "The project scope includes constructing a new access road and parking area and installing railroad crossing signals along State Highway 35. The project work includes grading, 6- inch aggregate surface course, 10-foot wide asphalt concrete pavement, 3-foot wide aggregate shoulders, one culvert, topsoil, turf establishment, railroad crossing signal with gate, and other miscellaneous work." I believe this is only for the small delineation effort, correct?
A1. If I am understanding the posed question correctly, yes, the advert. is only for the delineation.
Q2. Do you GIS files for the project limits for the delineation?
A2. FHWA can provide a shape file of the limits of disturbance.
Q3. When is the preferred field delineation date - fall of 2024 or spring 2025?
A3. Ideally, they’d want to get this done before mid-October if they do it in the fall. If they can get the task performed prior to October 15th give or take, then fall 24 is preferred.
Q4. Would you provide more information on the preferred format of a response? Are you requesting price(s) in columns E and F of the RFQ form “RFQ+NO+693C7324Q000028”? Is there also an opportunity to submit our qualifications? If so, is there a preferred format?
A4. PDF format would be preferred. Yes, I’d like one consolidated price for this contract. Yes, you can submit qualifications in PDF form too.
Q5. Is there anyone that should be contacted prior to applying for the delineation work in Shelby, WI (Notice ID - 693C7324Q000028)?
A5. Notification to the Refuge staff is required to alert them of when the survey will be conducted. The point of contracts (POCs) are Cheryl Groom, Deputy District Refuge Manager - USFWS (608) 779-2386, cheryl_groom@fws.gov; and Brandon Jutz, Regional Transportation Coordinator -USFWS (612) 713-5407, brandon_jutz@fws.gov