This document is Amendment No. 0002 to a solicitation for the Landslide Repairs in Ciales, Puerto Rico project, Solicitation Number 693C73-24-B-000008. The amendment revises the project plans, bid schedule, and special contract requirements. Specific changes include:
- Replacing plan sheets for the cantilever wall and gravity retaining wall details.
- Revising the bid schedule to add pay items for temporary shoring and bracing, update quantities for several items, and make other changes.
- Adding provisions in the special contract requirements for temporary shoring and bracing requirements.
- Providing a summary of questions and clarifications received from potential bidders.
- Extending the bid opening date to May 23, 2024.
The project is for repairs to landslides on several Puerto Rico highways, including utility relocation, embankment reconstruction, drainage, retaining walls, paving, and other work. The project is set aside for small business concerns with an estimated value between $5-10 million.
View the file
Other files
Show 40 more
Latest 50 of 53 listed here. See the rest on GovTribe.
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
(x)
693C7324B000008 x x
1 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted ; or (c) By separate letter or electronic communication which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGEMENT TO BE
RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR
OFFER. If by virtue of this amendment you desire to change an offer already submitted , such change may be made by letter or electronic communication, provided each letter or electronic communication makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
x
ASHBURN VA 20147
Attn: Construction
693C73
SUITE E2-3-300
QUANTUM PARK, 22001 LOUDOUN COUNTY PKWY
EASTERN FEDERAL LANDS HIGHWAY DIVISION
FEDERAL HIGHWAY ADMINISTRATION
ASHBURN VA 20147
ATTN: Acquisitions
693C73
SUITE E2-3-300
QUANTUM PARK, 22001 LOUDOUN COUNTY PKWY
EASTERN FEDERAL LANDS HIGHWAY DIVISION
FEDERAL HIGHWAY ADMINISTRATION
See Block 1405/07/20240002
13. THIS ITEM ONLY APPLIES TO MODIFICATION OF CONTRACTS/ORDERS. IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
12. ACCOUNTING AND APPROPRIATION DATA (If required) is not extended.is extended, Items 8 and 15, and returning
Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended , by one of the following methods: (a) By completing
The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
FACILITY CODE CODE
10B. DATED (SEE ITEM 13)
10A. MODIFICATION OF CONTRACT/ORDER NO.
9B. DATED (SEE ITEM 11)
9A. AMENDMENT OF SOLICITATION NO.
CODE
8. NAME AND ADDRESS OF CONTRACTOR (No., street, county, State and ZIP Code)
7. ADMINISTERED BY (If other than Item 6)CODE 6. ISSUED BY
PAGE OF PAGES
4. REQUISITION/PURCHASE REQ. NO.3. EFFECTIVE DATE2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO. (If applicable)
1. CONTRACT ID CODE
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
04/01/2024
CHECK ONE A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority) appropriation data, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).
E. IMPORTANT: Contractor is not is required to sign this document and return __________________ copies to the issuing office.
ORDER NO. IN ITEM 10A.
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
Project PR ER DOT PRMNT RPR(18)
The purpose of this Amendment is to:
1) Revise the Plans as follows:
a) AC-874579: Replace sheets GR-C-4 and RW-B-2.
b) See the Plan Sheet Changes section for details.
2) Revise the Solicitation Bid Schedule (B Pages) to:
a) Replace the Bid Schedule to add pay items and update quantities in Schedule A.
b) See the Bid Schedule Changes section for details.
Continued ...
16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)15A. NAME AND TITLE OF SIGNER (Type or print)
15C. DATE SIGNED 16B. UNITED STATES OF AMERICA 15B. CONTRACTOR/OFFEROR 16C. DATE SIGNED
(Signature of person authorized to sign) (Signature of Contracting Officer)
STANDARD FORM 30 (REV. 11/2016)
Prescribed by GSA FAR (48 CFR) 53.243
Previous edition unusable
Except as provided herein, all terms and conditions of the document referenced in Item 9 A or 10A, as heretofore changed, remains unchanged and in full force and effect .
ITEM NO. SUPPLIES/SERVICES QUANTITY UNIT UNIT PRICE AMOUNT
NAME OF OFFEROR OR CONTRACTOR
2 18
CONTINUATION SHEET
REFERENCE NO. OF DOCUMENT BEING CONTINUED PAGE OF
(A) (B) (C) (D) (E) (F)
693C7324B000008/0002
3) Revise the Special Contract Requirements (J Pages) as follows:
a) Subsections 206-1.01(c), 206-4.02, 206-5.02, and 206-5.05, to include provisions for Temporary
Shoring and Bracing.
b) See the Special Contract Requirement (J Pages) Changes section for details.
4) Provide a summary of responses to questions and clarifications asked by potential bidders.
5) The Bid Opening Date has been extended to May 23, 2024, at 2:00 p.m. EDT.
NSN 7540-01-152-8067 OPTIONAL FORM 336 (4-86)
Sponsored by GSA
FAR (48 CFR) 53.110
Amendment No. 0002
Info Page 1 of 1
U.S. DEPARTMENT OF TRANSPORTATION
FEDERAL HIGHWAY ADMINISTRATION
EASTERN FEDERAL LANDS HIGHWAY DIVISION
Project PR ER DOT PRMNT RPR(18)
Puerto Rico Highway and Transportation Authority
Landslide Repairs in Ciales, Puerto Rico
The purpose of this Amendment is to:
1) Revise the Plans as follows:
a) AC-874579: Replace sheets GR-C-4 and RW-B-2.
b) See the Plan Sheet Changes section for details.
2) Revise the Solicitation Bid Schedule (B Pages) to:
a) Replace the Bid Schedule to add pay items and update quantities in Schedule A.
b) See the Bid Schedule Changes section for details.
3) Revise the Special Contract Requirements (J Pages) as follows:
a) Subsections 206-1.01(c), 206-4.02, 206-5.02, and 206-5.05, to include provisions for Temporary Shoring and Bracing.
b) See the Special Contract Requirement (J Pages) Changes section for details.
4) Provide a summary of responses to questions and clarifications asked by potential bidders.
5) The Bid Opening Date has been extended to May 23, 2024, at 2:00 p.m. EDT.
Plan Sheet Changes
PLANS_AC-874579_HWY-218-220-224.pdf
1. Delete Plan Sheet 55 (GR-C-4), and substitute with the Amended Plan_GR-C-4_AC- 874579_Amendment 2.
a) Sheet 55 (GR-C-4), Typical Section, was updated to remove a duplicate of callout number 1.
PLANS_AC-874579_HWY-218-220-224.pdf
2. Delete Plan Sheet 50 (RW-B-2), and substitute with the Amended Plan_RW-B-2_AC- 874579_Amendment 2
b) Sheet 50 (RW-B-2), Gravity Retaining Wall Section and Details, was revised to show the correct reinforcing steel spacing for the retaining wall.
TYPICAL SECTIONS AT PR-146/ LINE-1
ER-HWY-220 PR 146 KM 16.40
TYPICAL SECTIONS AT PR-146/ LINE-1
ER-HWY-220 PR 146 KM 16.40
LEAN CONCRETE DETAIL
DATE R E V I S I O N SLANDSLIDE & ROAD DAMAGE EVALUATION
AT PR-146 FROM KM 9.80 TO KM 16.40
MUNICIPALITY OF CIALES, PUERTO RICO
AND REPAIR RECOMMENDATIONS
PUERTO RICO HIGHWAY AND TRANSPORTATION AUTHORITY
6 Costa Verde Humacao, PR 00791-6036
Horacio Díaz & Associates Corp. CSP
STRUCTURAL & CIVIL ENGINEERING
HORACIO DÍAZ & ASSOCIATES
AC PROJECT
CODE NO.
HIGHWAY MUNICIPALITY ISLAND
FISCAL
YEAR
SHEET
NO.
TOTAL
SHEETSPROJECT NO.
FED AID HIGHWAY
C R/W
P.R.
RCN7499579 2022CIALES PR
ER-9999(330)
PR-146AC-874579 85
ORACLE
ER-9999(454)
A
3.
CL
NEW CANTILEVER WALL
NATURAL
GRADE LINE
COMPACTED SELECTED
BACKFILL
0.600.60
2.57
EXISTING
ROADWAY
2.46
EXISTING
ROADWAY
5.03
EXISTING PAVEMENT WIDTH
1.20VARIES
4.93
IN
SLOPE
7.50
HALF ROW PR-146 KM 14.1
EXCAVATION STD. SPEC. 206
0.
4.
2% 2% 4%
3.12
NEW GUARD RAIL
(CONTRACTOR SHALL COORDINATE POST
LOCATION TO AVOID PIPE DAMAGE)
RECONSTRUCTED
SLOPED GRADE
FILL, 6" TOP SOIL,
GEOTEXTILE FABRIC
AND YDROSEEDING
1 0.30
4" WELL COMPACTED SAND GRAVEL MIX
EARTH FAILURE PROFILE
0.
2.97
1.
0.46
319.54
RET. WALL ER-HWY-224 PROFILE
AT CROSS SECTION 140+10
TOW=324.06
0.
1.52
1.
0.20 DRAIN PIPE CONNECTED TO RCP PIPE
STD. SPEC. 605
GEOTEXTILE STD. SPEC. 712
SHEAR KEY AT SLOPE BASE
A-1-B OR BETTER COMPACTED
IN LAYERS
7.952.00
1.
5.00
1.
1.00
COMPACTED SELECTED
BACKFILL
EXCAVATION STD. SPEC. 206
EXCAVATION STD. SPEC. 206
ROCK RIP RAP
D50=0.30STD
SPEC. 623
NEW 0.76 DIA RCP PIPE
L=16.21 M.
STD. SPEC. 603
DESIGN SOIL PARAMETERS
EFFECTIVE
FRICTION ANGLE
EFFECTIVE
COHESION
MOIST WEIGHT
UNIT
RETAINED SOIL 35° 0 130 pcf
FOUNDATION SOIL 35° 0 105 pcf
ULTIMATE SOIL BEARING CAPACITY 7,000 PSF
COEFFICIENT OF FRICTION BETWEEN CONCRETE AND SOILS = 0.32
DESIGN PEAK HORIZONTAL ACCELERATION COEFFICIENT = 0.2
0.30
0.
0.
0.46 2.97
3.
RET. WALL ER-HWY-224 DETAIL
0.46
2%
0.
1.52
RW601@0.25
REINFORCING STEEL
STD SPEC. 602
RW402@0.30
RW401@0.30
RW701@0.12
RW501@0.30
0.
4" WELL COMPACTED
SAND GRAVEL MIX
SILT BARRIER GEOTEXTILE AROUND EXCAVATION STD SPEC 712
STRUCTURAL CONCRETE
CLASS A-4 RETAINING
WALL STD SPEC. 601
0.46
0.
0.46
DRAIN PIPE TO RCP PIPE
CONNECTION DETAIL
NEW 0.76 DIA RCP PIPE
STD. SPEC. 603
0.20 DRAIN PIPE CONNECTED
TO RCP PIPE
STD. SPEC. 605
ALLOWABLE BEARING CAPACITY 3,500 PSF
DATE R E V I S I O N S
JU
N
E
, 2
LANDSLIDE & ROAD DAMAGE EVALUATION
AT PR-146 FROM KM 9.80 TO KM 16.40
MUNICIPALITY OF CIALES, PUERTO RICO
AND REPAIR RECOMMENDATIONS
PUERTO RICO HIGHWAY AND TRANSPORTATION AUTHORITY
6 Costa Verde Humacao, PR 00791-6036
Horacio Díaz & Associates Corp. CSP
STRUCTURAL & CIVIL ENGINEERING
HORACIO DÍAZ & ASSOCIATES
AC PROJECT
CODE NO.
HIGHWAY MUNICIPALITY ISLAND
FISCAL
YEAR
SHEET
NO.
TOTAL
SHEETSPROJECT NO.
FED AID HIGHWAY
C R/W
P.R.
RCN7499579 2022CIALES PR
ER-9999(330)
PR-146AC-874579 85
ORACLE
ER-9999(454)
NOT TO SCALE
B Pages Changes Summary Page 1 of 1
Bid Schedule Changes
1. Delete Bid Schedule Pages B-1 through B-6 and substitute with the amended Bid Schedule, Pages B-1 through B-6.
a) Revised bid quantities for the following Schedule A pay items:
1. Pay item 20300-4000, Borrow Class A
2. Pay item 20300-5000, Borrow Class B
3. Pay item 93400-1000, Structural Concrete, Class III (General Use)
4. Pay item 93400-3000, Structural Concrete, Class V (General Use)
b) Add Pay Items on Schedule A:
1. Pay item 20600-5000, Temporary Shoring and Bracing (HWY-227)
2. Pay item 20600-6000, Temporary Shoring and Bracing (HWY-228)
3. Pay item 93400-2000, Structural Concrete, Class IV (General Use)
B I D S C H E D U L E
SCHEDULE: A
PROJECT NO: PR ER DOT PRMNT RPR(18)
PROJECT NAME:
CQ = "Contract Quantity"
Item No. Quantity Unit Unit Price Amount
15000-1000 Line 0010 ALL LPSM $
15100-1000 Line 0020 ALL LPSM $
15102-0000 Line 0030 1 CTSM $
15401-0000 Line 0040 ALL LPSM $
15401-1000 Line 0050 ALL LPSM $
15401-2000 Line 0060 ALL LPSM $
15501-0000 Line 0070 ALL LPSM $
20100-0000 Line 0080 2.95 Cuerda $ $
20100-2000 Line 0090 40 Each $ $
20100-3000 Line 0100 4 Each $ $
20200-1000 Line 0110 ALL LPSM $
20300-1000 Line 0120 2,100 m3 $ $
20300-4000 Line 0130 154 m3 $ $
20300-5000 Line 0140 3,400 m3 $ $
20300-7000 Line 0150 125 m3 $ $
20300-8000 Line 0160 175 m2 $ $
20500-1000 Line 0170 75 m3 $ $
20600-1000 Line 0180 4,000 m3 $ $
20600-5000 Line 0190 ALL LPSM $
Construction Survey and Staking
Mobilization
Reimbursement for Municipal Tax Payments
Contractor Testing
Contractor Testing (Biological Species Monitoring)
Contractor Testing (Cultural Resources Protection and Monitoring Plan)
Temporary Shoring and Bracing (HWY-227)
Borrow Class A
Borrow Class B
Borrow Class D
Construction Schedule
Clearing and Grubbing
Cutting and Removing Trees, Small
Cutting and Removing Trees, Large
Removal of Structures and Obstructions
Unclassified Excavation
Proof Rolling
Trench Excavation, Unclassified
Unclassified Excavation for Structures
PR-144, HWY-203, 205; PR-146, HWY-218, 220, 221, 224; PR-149, HWY-227, 228
Submitted by: __________________________
Schedule Total: _________________________
610,000.00
B-1
SCHEDULE: A Account: ALL
PROJECT NO: PR ER DOT PRMNT RPR(18)
PROJECT NAME:
CQ = "Contract Quantity"
Item No. Quantity Unit Unit Price Amount
Submitted by: __________________________
PR-144, HWY-203, 205; PR-146, HWY-218, 220, 221, 224; PR-149, HWY-227, 228
20600-6000 Line 0200 ALL LPSM $
20700-1000 Line 0210 675 m3 $ $
21000-1000 Line 0220 1,030 M $ $
21000-2000 Line 0230 110 Each $ $
21000-3000 Line 0240 6 Each $ $
21001-1000 Line 0250 8 Each $ $
21002-1000 Line 0260 ALL LPSM $
30100-1000 Line 0270 1,150 m3 $ $
30100-2000 Line 0280 50 m3 $ $
30400-2000 Line 0290 210 m3 $ $
30500-1000 Line 0300 295 m2 $ $
40300-1000 Line 0310 2,270 m2 $ $
42101-3000 Line 0320 400 TON $ $
42101-4000 Line 0330 380 TON $ $
42101-6000 Line 0340 490 TON $ $
60200-1000 Line 0350 57,400 lb $ $
60300-3000 Line 0360 32 M $ $
60300-4000 Line 0370 20 M $ $
60301-1000 Line 0380 2 Each $ $
Cold Milling Bituminous Concrete Pavement, Variable Depth (0.050m to 0.075m)
Hot Plant Mix Asphalt Concrete, Type S (75)(12)
Hot Plant Mix Asphalt Concrete, Type B (75)(12)
Temporary Shoring and Bracing (HWY-228)
Foundation Fill
Stabilized Construction Exit
Temporary Erosion Control Measures (HWY-218, 220, 224)
Subbase Course, Class A
Subbase Course, Class B
Aggregate Base Course, Class A
Lean Concrete Base
Silt Fence
Straw Bales
Fiber Rolls (Sediment Log)
36" Reinforced Concrete Pipe Class-III
12" End Section (RCP)
Hot Plant Mix Asphalt Concrete, Type B (75)(34)
Reinforcing Steel
30" Reinforced Concrete Pipe Class-III
1,650.00
10,300.0010.00
15.00
B-2
PROJECT NO: PR ER DOT PRMNT RPR(18)
PROJECT NAME:
CQ = "Contract Quantity"
Item No. Quantity Unit Unit Price Amount
Submitted by: __________________________
PR-144, HWY-203, 205; PR-146, HWY-218, 220, 221, 224; PR-149, HWY-227, 228
60301-2000 Line 0390 22 M $ $
60301-3000 Line 0400 5 M $ $
60301-4000 Line 0410 90 M $ $
60301-6000 Line 0420 2 Each $ $
60301-8000 Line 0430 1 Each $ $
60402-1000 Line 0440 1 Each $ $
60402-4000 Line 0450 1 Each $ $
60403-2000 Line 0460 1 Each $ $
60403-3000 Line 0470 1 Each $ $
60403-6000 Line 0480 1 Each $ $
60403-7000 Line 0490 1 Each $ $
60500-4000 Line 0500 110 M $ $
60500-6000 Line 0510 66 M $ $
60500-7000 Line 0520 100 M $ $
60500-8000 Line 0530 80 M $ $
60600-1000 Line 0540 550 M $ $
60600-4000 Line 0550 20 M $ $
60600-6000 Line 0560 2 Each $ $
60600-7000 Line 0570 1 Each $ $
66" Reinforced Concrete Pipe Class V
15" Reinforced Concrete Pipe Class-III
6" PVC Pipe, SCH 40
Special Headwall (HWY-218)
Inlet, Type I, Depth 4.18m
6 inch Pipe Underdrain, Type PVC
8 inch Pipe Underdrain, Perforated, Type PVC
12 inch Pipe Underdrain, Perforated, Type PVC
4 inch Pipe Underdrain, Perforated, Type PVC (Weep Holes)
W-Beam Guardrail, Single Face
36" Headwall, Type A
Inlet, Type I, Depth 4.3m
Inlet Adjustments
Inlet, Type Custom
Inlet, Type I, Depth 1.74m
Double Grate Inlet, Type 1, Depth 1.7m
Removal, Storage and Delivery of Existing Guardrail
Crashworthy End Terminal, Type 1, TL-3
ThrieBeam Transition Section, Type I
B-3
PROJECT NO: PR ER DOT PRMNT RPR(18)
PROJECT NAME:
CQ = "Contract Quantity"
Item No. Quantity Unit Unit Price Amount
Submitted by: __________________________
PR-144, HWY-203, 205; PR-146, HWY-218, 220, 221, 224; PR-149, HWY-227, 228
60700-1000 Line 0580 150 M $ $
61000-6000 Line 0590 15 m $ $
61100-1000 Line 0600 24 mo $ $
61314-1000 Line 0610 3 m2 $ $
61314-2000 Line 0620 1 m2 $ $
61400-1000 Line 0630 1,120 m3 $ $
61701-2000 Line 0640 75 m2 $ $
61800-2000 Line 0650 1,110 M $ $
61800-3000 Line 0660 215 M $ $
62000-4000 Line 0670 1 Each $ $
62101-2000 Line 0680 25 Each $ $
62200-2000 Line 0690 444 m3 $ $
62200-4000 Line 0700 60 m3 $ $
62200-8000 Line 0710 595 m3 $ $
62200-9000 Line 0720 80 m3 $ $
62500-1000 Line 0730 70 m3 $ $
63504-2000 Line 0740 1 CTSM $
63504-6000 Line 0750 ALL LPSM $
63600-1000 Line 0760 215 M $ $
Traffic Sign Assembly, Code 1
Traffic Sign Assembly, Code 2
Gabions
Concrete Paved Waterway (Swale)
Thermoplastic Pavement Marking Stripes, White
Thermoplastic Pavement Marking Stripes, Yellow
Barbed Wire Fence, Type A
Concrete Barrier, Type F
Field Office
Furnishing and Placing Loamy Topsoil
Utility Company Compensation (PREPA)
Adjustment of Facilities (PREPA)
4" PVC Pipe, DR 14
Traffic Impact Attenuation Module, Type 4
Right-of-way Marker
Dumped Riprap, Class I
Dumped Riprap, Class III
Filter Blanket
Dumped Riprap, Class VII
30,000.00
B-4
PROJECT NO: PR ER DOT PRMNT RPR(18)
PROJECT NAME:
CQ = "Contract Quantity"
Item No. Quantity Unit Unit Price Amount
Submitted by: __________________________
PR-144, HWY-203, 205; PR-146, HWY-218, 220, 221, 224; PR-149, HWY-227, 228
63600-4000 Line 0770 4 Each $ $
63604-8000 Line 0780 1 CTSM $
63801-1000 Line 0790 ALL LPSM $
64000-7000 Line 0800 7 Each $ $
64000-8000 Line 0810 37 Each $ $
64000-9000 Line 0820 69 Each $ $
66100-1000 Line 0830 3 Each $ $
92600-0000 Line 0840 190 m2 $ $
93400-1000 Line 0850 99 m3 $ $
93400-2000 Line 0860 35 m3 $ $
93400-3000 Line 0870 309 m3 $ $
93501-0000 Line 0880 8 Each $ $
4" Gate Valve
Utility Company Compensation (PRASA)
Structural Concrete, Class III (General Use)
Structural Concrete, Class IV (General Use)
Structural Concrete, Class V (General Use)
Locate Utility, Test Pit
Maintenance of Traffic (MOT)
Reflective Raised Pavement Markers, Two way, Yellow-Yellow
Reflective Raised Pavement Markers, Two way, Clear-Red
Reflective Raised Pavement Markers, Two way, Clear-Clear
Project Funding Sign
Mechanically Stabilized Earth Wall (MSE)
30,000.00
B-5
B-6
BID SUMMARY
Project PR ER DOT PRMNT RPR(18)
(1) Schedule A (Base Contract) Bid Total (from Page B-1) = (1) $____________________
The performance period for the completion of Schedule A is 535 Calendar Days.
SCR Changes 1 of 2
Special Contract Requirement (J Pages) Changes
1. Add the following after subsection 206-1.01(c):
206-1.01(d). Follow OSHA safety regulations 29 CFR, Part 1926, Subpart P, Excavations for sloping the sides of excavations, using shoring and bracing, and using other safety features. When sides of excavations are sloped for safety considerations, submit one copy of the design that demonstrates conformity with OSHA regulations.
Where support systems, shield systems, or other protective systems are to be used, design the shoring according to Section 690. Submit drawings and construction details according to Subsection 104.03. In addition, design and install shoring and bracing for excavation operations as required to implement the maintenance of traffic plans or as otherwise required in the contract. Provide a cost breakdown of the lump sum pay item by site for payment purposes prior to commencing work.
2. Add the following after subsection 206-4.02:
206-4.03. Temporary Shoring and Bracing - Only measure temporary shoring and bracing for the construction of retaining walls that is required to provide for safe excavation operations, to maintain traffic at all times, or as required by the CO.
3. Delete subsection 206-5.02 and substitute with the following:
206-5.02 Cofferdams, Sheet Piling, and Temporary Shoring and Bracing
a. Cofferdams, when included as a separate item, will be paid for at the lump sum contract price which price will be full compensation for all the work required including furnishing, constructing, maintaining and removal.
b. Sheet piling, when included as a separate pay item, will be paid under Specification 615 - Piling.
c. Temporary Shoring and Bracing when included as a separate pay item, will be paid as follows:
(i) 20 percent of the pay item amount allocated to each site as shown in the cost breakdown will be paid when the design submittal is approved.
(ii) (ii) An additional 30 percent of the pay item amount allocated to each site as shown in the cost breakdown will be paid when 50 percent of the shoring and bracing construction is complete.
SCR Changes 2 of 2
(iii) (iii) Payment of the remaining portion of the pay item amount allocated to each site as shown in the cost breakdown will be paid when 100 percent of the shoring and bracing is complete for the site.
4. Add the following to subsection 206-5.05:
Temporary Shoring and Bracing………………………………. Lump Sum
Questions/Clarifications
Questions/Clarifications
Bidders can send written questions or inquiries for clarification to: eflhd.contracts@dot.gov.
Questions can be submitted at any time, but questions submitted within 10 days of the bid opening may not be answered in time for the bidder to properly incorporate the responses into their bid.
The following questions and issues were asked via email. The Government response or clarification is provided. Due to the repetitive nature of several questions and issues, the wording of the questions may have been revised, and some questions not have been included.
The Government’s direct response to the sender may also have been updated below for better clarity.
1. Please provide clarification to the following questions regarding ER Site HWY-224 PR-146
KM 14.11
a. Pag. DR-B-2: The new double inlet detail is not included.
Response: The detail of the proposed double inlet is specified as Type-1 on pages RW-B/1 (Sheet 49) and RW-B/2 (Sheet 50) of the plan sheets.
b. Pag. RW-B-2: There is a discrepancy in the spacing between bars on the detail and the Reinforcing Steel Schedule and Bar Diagram. For instance, detail bar RW401 has a spacing of 0.30 m, whereas in the table, it is listed as 0.18 m.
Response: Plan sheet RW-B-2 (sheet 50) has been revised in this Amendment to show the correct the reinforcing steel spacing.
2. Please provide clarification to the following question regarding ER Site HWY-220 PR-146
KM 16.40.
a. Pag. GR-C-4: The typical detail section indicates a concrete swale labeled as number 1, but number 1 is identified as asphalt.
Response: Plan sheet GR-C-4 (Sheet 55) has been revised in this Amendment to remove callout number 1. The concrete swale has been already labeled in the plans.
3. ER Site HWY-227 PR-149 KM 42.80, and ER HWY-228 PR-149 KM 42.90: Upon visiting the project site, we have noticed that the space available for traffic flow post-maintenance implementation will be insufficient for heavy equipment traffic. Considering this, the road will need to be closed during construction.
a. Please provide a Maintenance of Traffic (MOT) plan that addresses our concern regarding
Response: To address the MOT's concerns regarding insufficient space for construction equipment, Temporary Shoring and Bracing pay items were included for each site, HWY-227 and HWY-228. Additionally, the Special Contract Requirements (SCR) were amended to include provisions for Temporary Shoring and Bracing.
4. To ensure that we can thoroughly address these queries and incorporate the proposed addition, we kindly request an extension of 2 weeks beyond the original deadline.
Response: The bid due date has been extended to May 23, 2024.
5. Please provide clarification to the following questions:
a. ER-227 PR-149 KM 42.8, ER-228 PR-149 KM 42.9: Borrow material is defined as having a classification of A-2-4 or better and an angle of internal friction of 27 degrees, as mentioned on pages GR-A-4 and RW-A-3, respectively. However, specification 203- 2.03(b)(1) defines the borrow material with an angle of internal friction greater than 34 degrees.
i. Could you please clarify the correct specifications for the angle of internal friction required for borrow material?
Response: SCR 203-2.03(b)(1) governs over the Contract Plans as specified in Section 104.04. Therefore, the Borrow Class B material must meet 203- 2.03(b)(1) specifications.
b. ER-220 PR-146 KM 16.4: Page RW-C-2 specifies that the material for fill behind the gabion wall is to be Selected Backfill, which has an internal friction angle of 34 degrees, effective cohesion of 0, and a unit weight of 130 pcf when moist.
i. Could you please clarify the pay item for this material?
Response: The pay item for the “Fill/Backfill” material behind the gabion wall is Borrow Class B. Refer to pay item 20300-5000, Borrow Class B, in the Bid Schedule.
ii. Is it categorized as granular material or as borrow B?
Response: Plan Sheet RW-C-1, under “Fill/Backfill”, Note 2, specifies that the backfill material must be classified as A-2-4 or better. “Select Backfill” can be classified as Borrow Class B.
iii. Please consider postponing the bid for two weeks after we receive the answers to these questions.
Response: The bid due date has been extended to May 23, 2024.
6. Please provide clarification on the following questions regarding ER Site HWY-224 PR-146
KM 14.10.
a. Pag. DR-B-2: The profile specifies a 30-inch RCP Class V pipe. However, there is no 30-inch RCP Class V pipe included in the proposal.
Response: The 30-inch RCP pipe Class III is shown in the Hydraulic Structure Table on page GR-B-7 as Class III. Refer to pay item 60300-3000, 30-inch Reinforced Concrete Pipe Class III, in the Bid Schedule.
b. Pag RW-B-2: Ret. Wall Detail shows a Structural Concrete Class A-4. However, there is no Structural Concrete Class A-4 included in the proposal.
Response: According to the SCR 934, Structural Concrete A-4 (4,000 psi) is equivalent to Class IV (General Use) (4,000 psi). Refer to SCR 934-1.01(c) and the footnote of Table 934-1.
The Bid Schedule has been updated to revise the quantities of Structural Concrete for pay item 93400-3000 and to include pay item 93400-2000, Structural Concrete, Class IV (General Use). Refer to the amended Bid Schedule.
File details come from the government source that posted it. Updated .