Results of Bid Opening - NP SER PMS FY21(1).pdf

PDF 90 KB Posted

Attached to
Everglades National Park
Solicitation number
693C73-22-B-000005
Issued by

About this file

This document outlines the results of a bid opening for a federal contract to provide pavement preservation services at Everglades National Park. Five contractors submitted bids for the project, which includes crack cleaning and sealing, asphalt patching, pavement marking installation, and other miscellaneous work split into multiple schedules. Bid totals ranged from $5,860,755.56 to $8,471,166.80. The independent government estimate for all work was $6,078,000.00. The solicitation seeks certified small businesses to address pavement preservation needs at the park under solicitation number 693C73-22-B-000005, with work expected to fall between $5-10 million. The contractor selection period is not stated. The contract will be awarded by the Federal Highway Administration Eastern Federal Lands Highway Division.

View the file

Other files

File Type Posted
Plans - NP SER PMS FY21(1).pdf PDF
EVER_C6_RipReport.pdf PDF
FP14_Eng.pdf PDF
IFB Solicitation - NP SER PMS FY21(1).pdf PDF
ADV Bidders Qualifications Form.doc DOC document
EVER_C6_RouteID.pdf PDF
VETS-4212 Form.pdf PDF
Categorical Exclusion Form (NEPA).pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Federal Highway Administration

Eastern Federal Lands Highway Division

Bid Opening for

Everglades National Park

PROJECT: NP SER PMS FY21(1)

SOLICITATION NO. 693C73-22-B-000005

March 24, 2022 at 2:00 p.m. EST

Ashburn, Virginia

FEDERAL HIGHWAY ADMINISTRATION

EASTERN FEDERAL LANDS HIGHWAY DIVISION

BID OPENING for SOLICITATION NO. 693C73-22-B-000005

Project: NP SER PMS FY21(1)

March 24, 2022, 2:00 p.m. EST

If the Government awards the contract as Schedules A through D, the performance period to complete all contract work will be 213 calendar days. If separate: Schedule A will be 73 calendar days; Schedule B will be 47 calendar days; Schedule C will be 73 calendar days; and Schedule D will be 98 calendar days.

BIDDER’S BID TOTALS DAYS TOTAL PRICE

Bryant’s Land and

Development Industries, Inc.

SCHEDULE A

$1,614,723.00

SCHEDULE B (GOVERNMENT OPTION 1)

$362,851.00

SCHEDULE C (GOVERNMENT OPTION 2)

$870,559.00

SCHEDULE D (GOVERNMENT OPTION 3)

$3,850,209.20

SCHEDULE A + OPTION 1 +

OPTION 2 + OPTION 3 =

$6,698,342.20

Central Southern Construction

Corp.

SCHEDULE A

$1,481,059.00

SCHEDULE B (GOVERNMENT OPTION 1)

$869,045.30

SCHEDULE C (GOVERNMENT OPTION 2)

$1,256,169.50

SCHEDULE D (GOVERNMENT OPTION 3)

$2,724,228.50

SCHEDULE A + OPTION 1 +

OPTION 2 + OPTION 3 =

$6,330,502.30

BID OPENING for SOLICITATION NO. 693C73-22-B-000005

Project: NP SER PMS FY21(1)

March 24, 2022, 2:00 p.m. EST

If the Government awards the contract as Schedules A through D, the performance period to complete all contract work will be 213 calendar days. If separate: Schedule A will be 73 calendar days; Schedule B will be 47 calendar days; Schedule C will be 73 calendar days; and Schedule D will be 98 calendar days.

BIDDER’S BID TOTALS DAYS TOTAL PRICE

Construction Solutions Group, LLC

SCHEDULE A

$1,009,877.15

SCHEDULE B (GOVERNMENT OPTION 1)

$323,832.22

SCHEDULE C (GOVERNMENT OPTION 2)

$903,304.59

SCHEDULE D (GOVERNMENT OPTION 3)

$3,623,741.60

SCHEDULE A + OPTION 1 +

OPTION 2 + OPTION 3 =

$5,860,755.56

Justin J. Reeves, LLC SCHEDULE A

$1,692,854.70

SCHEDULE B (GOVERNMENT OPTION 1)

$852,846.35

SCHEDULE C (GOVERNMENT OPTION 2)

$2,381,912.82

SCHEDULE D (GOVERNMENT OPTION 3)

$1,671,357.00

SCHEDULE A + OPTION 1 +

$6,598,970.87

BID OPENING for SOLICITATION NO. 693C73-22-B-000005

Project: NP SER PMS FY21(1)

March 24, 2022, 2:00 p.m. EST

If the Government awards the contract as Schedules A through D, the performance period to complete all contract work will be 213 calendar days. If separate: Schedule A will be 73 calendar days; Schedule B will be 47 calendar days; Schedule C will be 73 calendar days; and Schedule D will be 98 calendar days.

BIDDER’S BID TOTALS DAYS TOTAL PRICE

LEE Construction Group, Inc. SCHEDULE A

$1,215,090.72

SCHEDULE B (GOVERNMENT OPTION 1)

$498,569.64

SCHEDULE C (GOVERNMENT OPTION 2)

$1,425,262.70

SCHEDULE D (GOVERNMENT OPTION 3)

$5,332,243.12

SCHEDULE A + OPTION 1 +

OPTION 2 + OPTION 3 =

$8,471,166.8

ENGINEER’S ESTIMATE SCHEDULE A

$960,000.00

SCHEDULE B (GOVERNMENT OPTION 1)

$468,000.00

SCHEDULE C (GOVERNMENT OPTION 2)

$1,310,000.00

SCHEDULE D (GOVERNMENT OPTION 3)

$3,340,000.00

SCHEDULE A + OPTION 1 +

$6,078,000.00