Results of Bid Oepning - TX FTFW SAMA 10(1).pdf
PDF 108 KB Posted
- Attached to
- San Marcos Aquatic Resources Center - Rehabilitation and Realignment of the Entrance Road
- Solicitation number
- 693C73-21-B-000019
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Amendment 0001 - TX FTFW SAMA 10(1).pdf | ||
| VETS-4212 Form.pdf | ||
| NEPA_CE.pdf | ||
| Authorization to Construct an On-Site Sewage Facility.pdf | ||
| ADV_Bidders Qualifications Form.doc | DOC document | |
| FP14_Eng.pdf | ||
| SWPPP.pdf | ||
| Plans - TX FTFW SAMA 10(1).pdf | ||
| Final Pavement Report.pdf | ||
| Plans - City of San Marcos.pdf | ||
| IFB Solicitiation - TX FTFW SAMA 10(1).pdf |
Show all 11
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Federal Highway Administration Eastern Federal Lands Highway Division
Bid Opening for
San Marcos Aquatic Resources Center
REHABILITATION AND REALIGNMENT
OF ENTRANCE ROAD (RTE 10)
PROJECT: TX FTFW SAMA 10(1)
SOLICITATION No. 693C73-21-B-000019
September 14, 2021 at 2:00 p.m. EST Ashburn, Virginia
FEDERAL HIGHWAY ADMINISTRATION
EASTERN FEDERAL LANDS HIGHWAY DIVISION
BID OPENING for SOLICITATION No. 693C73-21-B-000019 Project: TX FTFW SAMA 10(1) September 14, 2021, 2:00 p.m. EST
BIDDER’S BID TOTALS TOTAL PRICE
Construction Solutions Group SCHEDULE A $1,481,925.00
SCHEDULE A =
$1,481,925.00
Idea Contracting, LLC SCHEDULE A $1,261,693.00
SCHEDULE A =
$1,261,693.00
LaForge and Budd Construction Co., Inc.
SCHEDULE A
$2,246,225.00
SCHEDULE A =
$2,246,225.00
AR6 Construction & Engineering, LLC
SCHEDULE A
$1,657,905.36
SCHEDULE A =
$1,657,905.36
The performance period for the completion of Schedule A is 200 calendar days.
FEDERAL HIGHWAY ADMINISTRATION
EASTERN FEDERAL LANDS HIGHWAY DIVISION
BID OPENING for SOLICITATION No. 693C73-21-B-000019 Project: TX FTFW SAMA 10(1) September 14, 2021, 2:00 p.m. EST
BIDDER’S BID TOTALS TOTAL PRICE
Montoya Anderson Construction, Inc. dba MAC, Inc.
SCHEDULE A
$1,509,645.00
SCHEDULE A =
$1,509,645.00
Alamo City Constructors, Inc. SCHEDULE A $1,790,545.90
SCHEDULE A =
$1,790,545.90
Engineer’s Estimate SCHEDULE A $1,580,000.00
SCHEDULE A =
$1,580,000.00
The performance period for the completion of Schedule A is 200 calendar days.
| Slide Number 1 |
| �FEDERAL HIGHWAY ADMINISTRATION�EASTERN FEDERAL LANDS HIGHWAY DIVISION�BID OPENING for SOLICITATION No. 693C73-21-B-000019� Project: TX FTFW SAMA 10(1)�September 14, 2021, 2:00 p.m. EST� |
| �FEDERAL HIGHWAY ADMINISTRATION�EASTERN FEDERAL LANDS HIGHWAY DIVISION�BID OPENING for SOLICITATION No. 693C73-21-B-000019� Project: TX FTFW SAMA 10(1)�September 14, 2021, 2:00 p.m. EST� |
File details come from the government source that posted it. Updated .