Results of Bid Opening - NP-SER PMS FY19(1).pdf
PDF 111 KB Posted
- Solicitation number
- 693C73-20-B-000001
About this file
This document summarizes the bid opening for the Mammoth Cave National Park - Southeast Region Pavement Preservation federal contract opportunity. The solicitation number is 693C73-20-B-000001 and involves pavement preservation treatment, asphalt patching, crack cleaning and sealing, pavement marking, and other miscellaneous work on identified paved roads and parking areas within the park located in Barren, Edmonson, and Hart Counties, Kentucky. The project will be split into multiple work schedules with the total cost expected to fall between $5 million and $10 million. Six contractors submitted bids ranging from $5,091,669.70 to $6,950,400.00. The engineer's estimate was $6,460,140.00. The performance period if all schedules are combined would be 205 calendar days. Sealed bids from certified Small Business Concerns only were accepted by the Federal Highway Administration Eastern Federal Lands Highway Division by November 14, 2019 at 2:00 p.m. at their office in Sterling, Virginia.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Amendment_0001_-_NP-SER_PMS_FY19(1).pdf | ||
| ADV_Bidder's_Qualifications_Form.doc | DOC document | |
| IFB_Solicitation_-_NP-SER_PMS_FY19(1).pdf | ||
| VETS-4212_-_Form_-_2019.pdf | ||
| Plans_-_NP-SER_PMS_FY19(1).pdf | ||
| FP14_Eng.pdf | ||
| NEPA_(Categorical_Exclusion_Form).pdf | ||
| Synopsis_-_NPS_SER_PMS_FY19(1).doc | DOC document |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Federal Highway Administration Eastern Federal Lands Highway Division
Bid Opening for
Southeast Region Pavement Preservation
PROJECT: NP-SER PMS FY19(1)
SOLICITATION NO. 693C73-20-B-000001
November 14, 2019 at 2:00 p.m.
Sterling, VA
FEDERAL HIGHWAY ADMINISTRATION
EASTERN FEDERAL LANDS HIGHWAY DIVISION
BID OPENING for SOLICITATION NO. 693C73-20-B-000001 Project: NP-SER PMS FY19(1)
November 14, 2019, 2:00 p.m. local time
BIDDERS BID TOTALS DAYS TOTAL PRICE
Central Southern Construction SCHEDULE A SCHEDULE B $4,168,700.00 $582,650.00
SCHEDULE C SCHEDULE D
$518,290.00 $146,729.00
SCHEDULE E
$868,310.00
SCHEDULE A + SCHEDULE B +
SCHEDULE C + SCHEDULE D +
SCHEDULE E =
$6,284,679.00
Howard W. Pence, Inc. SCHEDULE A SCHEDULE B $3,241,056.00 $412,419.90
SCHEDULE C SCHEDULE D
$516,143.80 $172,068.00
SCHEDULE E
$749,982.00
SCHEDULE A + SCHEDULE B +
SCHEDULE C + SCHEDULE D +
SCHEDULE E =
$5,091,669.70
Kovilic Construction Co., Inc. SCHEDULE A SCHEDULE B $4,586,665.00 $557,500.00
SCHEDULE C SCHEDULE D
$632,095.00 $192,600.00
SCHEDULE E
$981,540.00
SCHEDULE A + SCHEDULE B +
SCHEDULE C + SCHEDULE D +
SCHEDULE E =
$6,950,400.00
If the Government awards the contract as Schedules A + B + C + D + E, the performance period will be 205 calendar days.
If separate: Schedule A will be 115 calendar days; Schedule B will be 25 calendar days; Schedule C will be 25 calendar days; Schedule D will be 10 calendar days;
Schedule E will be 30 calendar days
FEDERAL HIGHWAY ADMINISTRATION
EASTERN FEDERAL LANDS HIGHWAY DIVISION
BID OPENING for SOLICITATION NO. 693C73-20-B-000001 Project: NP-SER PMS FY19(1)
November 14, 2019, 2:00 p.m. local time
BIDDERS BID TOTALS DAYS TOTAL PRICE
Lee Construction Group, Inc. SCHEDULE A SCHEDULE B $3,709,120.95 $514,008.00
SCHEDULE C SCHEDULE D
$594,247.50 $173,054.00
SCHEDULE E
$869,518.00
SCHEDULE A + SCHEDULE B +
SCHEDULE C + SCHEDULE D +
SCHEDULE E =
$5,859,948.45
Bryant’s Land & Development Industries, Inc.
SCHEDULE A SCHEDULE B
$3,603,589.19 $523,654.81
SCHEDULE C SCHEDULE D
$568,468.05 $209,960.24
SCHEDULE E
$772,032.59
SCHEDULE A + SCHEDULE B +
SCHEDULE C + SCHEDULE D +
SCHEDULE E =
$5,677,704.88
Engineer’s Estimate SCHEDULE A SCHEDULE B $4,220,000.00 $530,000.00
SCHEDULE C SCHEDULE D
$530,000.00 $140,140.00
SCHEDULE E
$1,040,000.00
SCHEDULE A + SCHEDULE B +
SCHEDULE C + SCHEDULE D +
SCHEDULE E =
$6,460,140.00
If the Government awards the contract as Schedules A + B + C + D + E, the performance period will be 205 calendar days.
If separate: Schedule A will be 115 calendar days; Schedule B will be 25 calendar days; Schedule C will be 25 calendar days; Schedule D will be 10 calendar days;
Schedule E will be 30 calendar days
| Slide Number 1 |
| �FEDERAL HIGHWAY ADMINISTRATION�EASTERN FEDERAL LANDS HIGHWAY DIVISION�BID OPENING for SOLICITATION NO. 693C73-20-B-000001� Project: NP-SER PMS FY19(1)�November 14, 2019, 2:00 p.m. local time � |
| �FEDERAL HIGHWAY ADMINISTRATION�EASTERN FEDERAL LANDS HIGHWAY DIVISION�BID OPENING for SOLICITATION NO. 693C73-20-B-000001� Project: NP-SER PMS FY19(1)�November 14, 2019, 2:00 p.m. local time � |
File details come from the government source that posted it. Updated .