Results_of_Bid_(ROBO)_-_NP-EVER_10(5),_900(1).pdf

PDF 111 KB Posted

Attached to
Everglades National Park - NP-EVER 10(5), 900(1)
Solicitation number
693C73-19-B-000033
Issued by

About this file

Results of Bid (ROBO) - NP-EVER 10(5), 900(1)

View the file

Other files

File Type Posted
ADV_Bidder's_Qualifications_Form.doc DOC document
FP14_Eng.pdf PDF
VETS-4212_-_Form_-_2018.pdf PDF
NEPA_CE.pdf PDF
Plans_-_NP-EVER_10(5),_900(1).pdf PDF
IFB_Solicitation_-_NP-EVER_10(5),_900(1).pdf PDF
Pavement_report.pdf PDF
Synopsis_-_NP-EVER_10(5),_900(1).doc DOC document

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Federal Highway Administration Eastern Federal Lands Highway Division

Bid Opening for

Everglades National Park

PROJECT: NP-EVER 10(5), 900(1)

SOLICITATION NO. 693C73-19-B-000033

August 06, 2019 at 2:00 p.m.

Sterling, VA

FEDERAL HIGHWAY ADMINISTRATION

EASTERN FEDERAL LANDS HIGHWAY DIVISION

BID OPENING for SOLICITATION NO. 693C73-19-B-000033 Project: NP-EVER 10(5), 900(1) August 06, 2019, 2:00 p.m. local time

BIDDER’S BID TOTALS DAYS TOTAL PRICE

Baker Construction Services

LLC

SCHEDULE A

$3,995,107.89

SCHEDULE B (OPTION 1)

$1,711,350.50

SCHEDULE C (OPTION 2)

$1,866,424.03

SCHEDULE D (OPTION 3)

$1,147,633.25

SCHEDULE E (OPTION 4)

$470,060.66

SCHEDULES A THRU E SCHEDULES A THRU E

$9,190,576.33

Bryant’s Land & Development Industries, Inc.

SCHEDULE A

$2,034,944.00

SCHEDULE B (OPTION 1)

$830,968.00

SCHEDULE C (OPTION 2)

$1,051,926.00

SCHEDULE D (OPTION 3)

$731,995.00

SCHEDULE E (OPTION 4)

$209,260.00

SCHEDULES A THRU E SCHEDULES A THRU E

$4,858,093.00

Central Southern Construction SCHEDULE A $3,205,225.00

SCHEDULE B (OPTION 1)

$1,047,138.00

SCHEDULE C (OPTION 2)

$1,183,838.00

SCHEDULE D (OPTION 3)

$702.889.00

SCHEDULE E (OPTION 4)

$206,700.00

SCHEDULES A THRU E SCHEDULES A THRU E

$6,345,790.00

If the Government awards the contract as Schedules A + B + C + D + E, the performance period to complete all contract work will be 220 calendar days.

FEDERAL HIGHWAY ADMINISTRATION

EASTERN FEDERAL LANDS HIGHWAY DIVISION

BID OPENING for SOLICITATION NO. 693C73-19-B-000033 Project: NP-EVER 10(5), 900(1) August 06, 2019, 2:00 p.m. local time

If the Government awards the contract as Schedules A + B + C + D + E, the performance period to complete all contract work will be 220 calendar days.

BIDDER’S BID TOTALS DAYS TOTAL PRICE

H&R Paving, Inc. SCHEDULE A $2,387,381.00

SCHEDULE B (OPTION 1)

$1,286,206.00

SCHEDULE C (OPTION 2)

$1,425,614.90

SCHEDULE D (OPTION 3)

$1,788,534.50

SCHEDULE E (OPTION 4)

$566,873.00

SCHEDULES A THRU E SCHEDULES A THRU E

$7,454,609.40

Pigott Asphalt and Sitework, LLC

SCHEDULE A

$3,416,725.00

SCHEDULE B (OPTION 1)

$750,686.50

SCHEDULE C (OPTION 2)

$897,570.50

SCHEDULE D (OPTION 3)

$534,714.00

SCHEDULE E (OPTION 4)

$236,400.00

SCHEDULES A THRU E SCHEDULES A THRU E

$5,836,097.00

Engineer’s Estimate SCHEDULE A $2,600,000.00

SCHEDULE B (OPTION 1)

$1,140,000.00

SCHEDULE C (OPTION 2)

$1,280,000.00

SCHEDULE D (OPTION 3)

$660,000.00

SCHEDULE E (OPTION 4)

$180,000.00

SCHEDULES A THRU E SCHEDULES A THRU E

$5,860,000.00

Slide Number 1
FEDERAL HIGHWAY ADMINISTRATION�EASTERN FEDERAL LANDS HIGHWAY DIVISION�BID OPENING for SOLICITATION NO. 693C73-19-B-000033 Project: NP-EVER 10(5), 900(1)�August 06, 2019, 2:00 p.m. local time �
FEDERAL HIGHWAY ADMINISTRATION�EASTERN FEDERAL LANDS HIGHWAY DIVISION� BID OPENING for SOLICITATION NO. 693C73-19-B-000033 Project: NP-EVER 10(5), 900(1)�August 06, 2019, 2:00 p.m. local time �If the Government awards the contract as Schedules A + B + C + D + E, the performance period to�complete all contract work will be 220 calendar days.

File details come from the government source that posted it.