DRYDOCKING AND REPAIR FB-214 DECK BARGE
Solicitation number
6933A223Q000015
Issued by

About this file

This statement of work outlines the requirements for drydocking and repairing a 110-foot deck barge owned by the Maritime Administration. The contractor will be required to provide drydocking facilities in the Hampton Roads area and perform various repairs and services over a 45-day period, including drydocking the vessel; performing ultrasonic testing; replacing hull plating and structural members; cleaning and painting the hull; replacing sacrificial zinc anodes; replacing the crane mat; and miscellaneous items such as cleats, bollards, and deck fittings. The statement of work also includes optional additional labor hours and materials that are subject to funding availability.

View the file

Other files

File Type Posted
6933A223Q000015 00003.pdf PDF
FB 214 Pricing sheet 8-8-23.xlsx XLSX spreadsheet
Final Price sheet 8-7-23.xlsx XLSX spreadsheet
new Pricing sheet.xlsx XLSX spreadsheet
Amendment 00002 SF30.pdf PDF
Amendment 00001 SF30.pdf PDF
FINAL SOW.docx DOCX document
Crane Mat Specs.pdf PDF
Amendment 00002.pdf PDF
mat 3.jpg JPG image
Amendment 00001.pdf PDF
mat 2.jpg JPG image
mat 1.jpg JPG image
FB214 SOW 5.23.23.pdf PDF
Mantis Crane Checks.pdf PDF
Old question and answers from Previous soliciation - FB-214.xlsx XLSX spreadsheet
James River Reserve Fleet - Crane Barge Solicitation.pdf PDF
6933A223Q000015 Pricing.xlsx XLSX spreadsheet
214b.pdf PDF
6933A223Q000015.pdf PDF
15010-technical-specs Mantis.pdf PDF
214.pdf PDF
Show all 22

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

STATEMENT OF WORK

DRYDOCKING AND REPAIR

FB-214 DECK BARGE

LENGTH OVERALL: 110 FEET

BREADTH: 30 FEET

DEPTH: 8 FEET

STEEL HULL

STATEMENT OF WORK

The subject vessel is owned by the United States of America acting through the Maritime

Administration, Department of Transportation (herein after called MARAD).

1. SERVICES:

1.1. Contractor is to provide all labor and material required to perform a dry docking of FB-214

Crane Barge according to the Statement of Work. Barring any weather related or unforeseeable delays, MARAD intends for the barge to be delivered and tendered to the contractor facility within three working days of notice to proceed. MARAD will deliver the FB-214 to the contractor’s facility which shall be located in the Hampton Roads area, such area to include the

James River, all branches of the Elizabeth River, York River, Mobjack Bay and tributaries. The dry-docking POP will be 45 days upon completion of delivery and tender. MARAD will assume custody and take re-delivery of the craft at the same contractor’s facility after all work is performed and accepted. MARAD intends to have a representative on site during most production days while the craft is at the contractor’s facility. The contractor will provide the following services to support this project:

1.2. The contractor shall provide line handlers to moor the vessel (including a gangway) upon arrival, to cast off the vessel during the final departure, and during all shifts within the

Contractor’s facility.

1.3. Contractor shall provide services of a crane, crane operator, and rigger to assist in the performance of all work items required by this contract (if required).

1.4. In addition, contractor shall provide fire protection to the vessel upon arrival at Contractor’s facility. Fire Protection shall comply with the National Fire Protection Association, “Standard for

Fire Protection of Vessels during Construction, Repair, and Lay-up”, NFPA 312.

1.5. Contractor shall also provide sufficient compressed air during the entire period of performance of the contract. The compressed air shall be free of moisture and oil; furnish all labor, material, and equipment to set-up temporary lighting in all spaces and tanks where work is to be carried out. Contractor shall furnish labor and material to connect and supply power in quantity sufficient to light the vessel and operate any equipment needed to accomplish the specification while vessel is berthed at the Contractor’s facility.

1.6. The contractor shall provide all labor, material, and equipment necessary to make all removals and restorations; remove and replace interference’s; rig and unrig; make all disassembles and subsequent reassembly to accomplish the work specified herein. All work shall be in compliance with the latest Regulatory Body requirements. The term, “Regulatory Bodies” includes the United States Coast Guard, American Boat and Yacht Council, United States Public

Health Service, the Department of Labor Occupational Safety and Health Administration, and the Institute of Electrical and Electronic Engineers.

1.7. If, in the performance of any work required in these Specifications, it becomes necessary to remove or disturb any structural part of the vessel, the contractor shall, upon completion of that work, reinstall or renew, if necessary, any affected structural part and restore to original conditions of durability, appearance, and seaworthiness. All temporary removals in the way of the work are to be replaced in good order.

1.8. All removed equipment or parts remain the property of the government and is to be left aboard the vessel. The contractor shall re-deliver the vessel in the same clean and orderly condition as when received.

1.9. All work specified shall be accomplished and completed in conformity with the highest standards of shipbuilding practices. All items contained in these Specifications must be proved to the satisfaction of the Contracting Officer’s Representative (COR).

1.10. The term “or equal” means that components, equipment, or material shall be equivalent in terms of performance, services required, compatibility with interrelated systems and arrangements and supportability over the service life of the components or equipment. In the case of component or equipment substitution for those components or equipment noted on the

Contract Guidance Drawings or Specification, the Contractor shall submit a written request delineating the design and the performance data on both the specified and substituted piece of equipment for COR approval and if approved, the Contractor shall take full contractual and technical responsibility for ensuring installation of components or equipment’s or both and compatibility with interrelated systems.

1.11. The terms “Replace” or “Renew” mean to remove the existing unit, equipment, or systems, including all interferences and to install a new unit, equipment or system which is either identical to or equal to that which was removed; the installation shall include at a minimum all hook-up, supports, and adapters which are required to affect a fully operational installation complete in all respects.

1.12. Any repairs or other work resulting from recommendations or other discoveries after the vessel is docked are to be brought to the attention of the COR immediately by use of a contractor generated inspection report. Any such additional work will be subject to a delivery order.

Additional work to be accomplished ONLY WHEN AUTHORIZED IN WRITING.

1.13. The contractor shall gas-free or inert all spaces affected by the work described in this specification and is responsible for determining all spaces requiring gas freeing. All safety precautions contained in the United States Department of Labor Safety and Health Regulations for Ship Repairing, Title 29 CFR Parts 1501.10, 1501.11, 1501.12, 1501.14, and 1501.15 must be strictly observed. A copy of the gas-free certificate is to be presented to the COR before beginning work on the repairs. Initial Certificates are to be issued by a Certified Marine Chemist, as will recertification if conditions change which will affect the Certificate. Gas-Free Certificates shall be updated daily by competent persons.

1.14. All welding shall meet ABS and USCG requirements and conform to American Welding

Society (AWS) standards. All welds shall be cleaned prior to painting. All surfaces which have been cut, drilled, welded, or otherwise modified shall be cleaned, free of grease, slag and foreign matter; and painted in accordance with the coating sections of these Specifications. Prior to any surface preparations the contractor will conduct a joint inspection of the welding repairs with the

COR.

1.15. Contractor shall provide an office space near the dry dock or marine railway for use by the

Owner’s representative or representatives during the course of this contract with a desk and three chairs. Contractor shall supply internet access and local landline phone in the office.

1.16. Except when specified in writing from the Owner’s Representative, the Contractor shall not use any of the vessel’s spare parts, equipage, material, or equipment in the performance of specifications, including mooring lines, etc. Any spare parts, equipage, material, etc. authorized for use by the Owners Representative to the contractor are to be replaced, at the Contractor’s expense, prior to the completion of the contract. The Contractor shall be responsible for all deficiencies and the prompt and proper restoration of same and all deficiencies arising from the

Contractor’s use of the vessel equipage, machinery, etc.

1.17. Some of the vessel’s crew will be onboard the craft periodically and shall have free access to and from shore. The vessels crew will not be feeding and sleeping aboard, but the crew shall be free to do regular maintenance and repairs to all machinery and equipment. By no means will crew work be allowed to interfere with contract work.

1.18. All dirt and debris resulting from the work required by these Specifications shall be removed from the vessel and disposed of at contractor’s expense. All affected areas shall be left clean and in good order at the end of the dry-docking period.

2. DRYDOCKING

2.1.1. Provide the required drydocking facilities as outlined in "General Requirements" section of this specification and drydock the vessel.

2.1.2. The vessel shall be blocked sufficiently to prevent stress and strain on vessel's hull.

2.1.3. The line of flotation shall be established by the Contractor prior to drydocking vessel.

2.1.4. Shift the vessel on the blocks for 100 percent cleaning and painting.

2.2. Drydocking Report:

2.2.1. Contractor shall provide a drydocking report.

2.3. Undocking: Upon completion of all related repairs and satisfactory inspection by the

Contractor and the GOV COR, refloat the vessel.

2.4. Contractor and GOV COR Checkpoints:

2.4.1. Inspect blocking of the vessel.

2.4.2. Inspect each compartment for leakage when vessel is shifted and when undocked.

2.4.3. Witness the undocking of the vessel.

3. PLATE RENEWAL AND STRUCTURAL REPAIRS

3.1. Scope of Work:

3.1.1. Furnish and replace plating and required structural members in areas indicated by the COR.

3.1.2. The price for this item shall include the necessary labor to remove and reinstall, as original, all interferences in way of access to remove and replace defective and deteriorated plate, guards, and structural members.

3.1.3. Such interferences shall include liquid in tanks, ballast of all descriptions, structural members, piping and valves, insulation, machinery and components, stored items, and equipment, and drydock or marine railway blocks used to support the vessel while docked for underwater repairs.

3.1.4. Materials replacement shall include flat, rolled, bent, formed or other designed shapes applicable to the vessel.

3.1.5. Structural members replacement shall include longitudinal and transverse bulkheads, support stanchions, pillars, frames, stringers, stiffeners, I beams, H beams, channels, tees, zees, or other designed shapes applicable to the vessel.

3.1.6. All steel furnished for use in this item shall conform to material requirements of the applicable vessel drawings to the areas being repaired. Plate types shall include, but not be limited to: A131 hull plating, A36 plating, structural members, and foundations, and/or other materials specified in vessel drawings.

3.2. Requirements:

3.2.1. In the performance of any burning, heating, or welding required to accomplish the repairs specified in this item, it shall be the responsibility of the Contractor to provide a "gas free" or "safe for hot work" certificate to the COR, certifying that all tanks and other adjacent areas in the way of repairs and alterations are free of gas and other fire hazards.

3.2.2. In the performance of this item, the Contractor shall dispose of all waste products in accordance with Federal, state, and local regulations.

3.2.3. Cost of performing the above parts of this item shall be included in the price of this item.

3.3. Removals:

3.3.1. Remove interferences required to provide access to the areas of deteriorated plating identified for renewal.

3.3.2. Crop out and remove all defective plating and any structural members or interferences as indicated by the COR.

3.3.3. All material edges in the way of removals shall be faired and cleaned free to receive new materials.

3.4. Installation:

3.4.1. All new materials shall conform to original vessel design. Actual type and size material requirements shall be obtained from the vessel by the Contractor.

3.4.2. All new materials shall be abrasive blasted to white metal (SSPC SP5) and primer paint applied prior to installation.

3.4.3. All new materials installed to the vessel shall be welded in place to conform with vessel's original construction.

3.5. Painting: All new materials and disturbed areas shall be primed and painted.

3.6. Repairs:

3.6.1. Areas and Locations:

3.6.1.1. Underwater plate and related structural members are defined as all original configuration of plating and fixed appendages from the vessel's deep load line down to and including the keel.

3.6.1.2. Above deep load line plate and related structural members are defined as all original configuration of plating, guards, and rub rails from the deep load line up to and including the main deck.

3.6.1.3. Estimated Quantity:

3.6.1.3.1. Underwater Plate: 2000 pounds medium grade steel.

3.6.1.3.2. Above deep load line Plate: approximately 1400sq ft17,600 pounds forof main deck.

3.6.1.3.3. Void 5, bottom, port side, repair dent/damage 200 pounds.

4. ULTRASONIC TESTING

4.1. Scope of Work: Contractor shall perform ultrasonic testing in areas indicated by the

COR.

4.2. Applicable Areas: All areas of the vessel's hull plating, shell plating, decks, bulkheads, tank tops, ballast tanks, all structural framing, and any other areas as indicated by the

COR.

4.3. Preparation:

4.3.1. The Contractor shall include in the price of this item the removal and reinstallation of all interferences required for access to areas to be tested.

4.3.2. Prior to taking readings, all areas shall be ground smooth as required for attaining satisfactory testing conditions.

4.4. Tests:

4.4.1. Furnish the services of a certified nondestructive testing agency approved by the

American Bureau of Shipping. Perform ultrasonic tests and record thicknesses in all applicable areas as required by the American Bureau of Shipping. A micrometer depth gauge shall be used in conjunction with ultrasonic tests to determine the depth of excessively deep pits.

4.4.2. Prepare a report chart showing the location of each test, existing thickness, vessel designed thickness and percentage of wastage. Additionally, prepare a sketch of the vessel's applicable areas showing average thickness readings of each plate.

4.4.3. Immediately upon completion of test readings, furnish the COR with one (1) rough copy of test readings.

4.4.4. Within ten (10) days after completion of ultrasonic testing, furnish the COR an original, an electronic, and two (2) printed copies of the finished report showing test readings as specified, date readings were taken, vessel's name, place of test, testing agency and type of equipment used for test.

4.4.5. Estimated Quantity: Five hundred (500) test readings.

5. HULL ZINC REPLACEMENTS

5.1. Renew Approximately twenty-four (24) twenty-three-pound 12" x 6" x 1¼", sacrificial anodes.

5.2. Surface prep and paint any coating disturbed in during the replacement.

6. HULL CLEANING AND PAINTING

6.1. Scope of Work: Adhere to listed requirements and wet abrasive blast, clean and paint the below designated surfaces using materials of the listed specifications. Line of flotation shall be established prior to the commencement of abrasive blasting and painting.

6.2. Requirements:

6.2.1. Prior to any abrasive blasting as specified in this item, all hull openings, hatches, vents, or other openings to the interior of the vessel shall be blanked off and sealed to prevent entry of abrasive blasting material.

6.2.2. Prior to abrasive blasting, weld all hull markings for permanent identification, to include draft marks and vessel name.

6.2.3. Precautions shall be taken to prevent damage to electrical wiring, fixtures, data and name plates, glass of port lights and windows, instruments or any other components not intended to be blasted. Any components damaged on the vessel in the performance of this item shall be repaired or replaced at the expense of the

Contractor.

6.2.4. No abrasive blasting shall be performed until the GOV COR has approved the installed methods of protection.

6.2.5. No work shall be performed on the interior of the vessel during abrasive blasting operations.

6.2.6. These precautions shall be adhered to during the entire time of abrasive blasting operations on the vessel and when the vessel is in the vicinity of blasting operations where the possibility exists of abrasive blasting material entering the vessel due to wind conditions or force of the blast.

6.2.7. NOTE: Requests to deviate from the specified paint system shall be submitted in writing to the Contracting Officer with all applicable documentation. Written authorization shall be received from the Contracting Officer prior to proceeding with any deviation. Inclusion of a paint system in the referenced technical bulletin is not authorization to deviate from the specification requirements.

6.2.8. Bared surfaces shall not be allowed to stand overnight without application of primer paint.

6.2.9. In the performance of this item, the Contractor shall dispose of all waste products in accordance with Federal, state, and local regulations.

6.3. Removals:

6.3.1. Line of flotation shall be established prior to commencement of abrasive blasting and painting.

6.3.2. Make the required disconnections and removals prior to performance of this item.

Reinstall any removals upon completion of blasting/painting.

6.3.3. Unbolt and remove exterior D rubber fendering from exterior of vessel.

6.4. Cleaning and Wet Abrasive Blasting:

6.4.1. Prior to the commencement of abrasive blasting, the Contractor shall perform high pressure water cleaning at 5,000 – 10,000 psi (SSPC HP WC) of entire surface to be abrasive blasted.

6.4.2. Abrasive blast or wet abrasive blast listed areas to near white metal (SSPC TR2 or

SSPC-SP10).

6.4.3. Abrasive blasted surfaces shall conform to the standards set forth in Seaguard

5000 HS Epoxy Application Bulletin.

6.5. Areas to be Wet Abrasive Blasted:

6.5.1. Abrasive blast all exterior hull plate surfaces from the keel up to the main deck.

6.5.2. Abrasive blast main deck.

6.6. Inspection: Prior to application of any paints, prepared surfaces will be inspected and approved by the GOV COR.

6.7. Paint Application:

6.7.1. Apply paint only to clean, dry surfaces prepared as specified, using the designated paint and coating thicknesses as specified.

6.7.2. Paint coatings shall be free of runs and sags with borderlines struck clean, clear, and precise.

6.7.3. The Contractor shall comply with the temperature, wind and humidity requirements stated in the referenced technical bulletin.

6.7.4. Drying time between paint coatings shall be as recommended by the paint manufacturer using the referenced technical bulletin as a guide.

6.7.5. The basic color requirements are:

6.7.5.1. Keel to waterline- DARK RED

6.7.5.2. Freeboard- BLACK

6.7.5.3. Main Deck- DECK GRAY

6.7.5.4. Names, Drafts, ETC. – BLACK or WHITE

6.8. Painting (Line of Flotation and Below): Including freeboard up to main deck.

6.8.1. To all bared surfaces, apply one (1) coat of Sherwin Williams Seaguard, 5000 HS

Epoxy Gray for a DFT of 5-7mils.

6.8.2. To all primer coated surfaces, apply a second (2) coat of Sherwin Williams

Seaguard, 5000 HS Epoxy Gray for a DFT of 5-7mils.

6.8.3. Second coat must be tacky when applying next Antifouling coat, per application bulletin.

6.8.4. To all tacky gray surfaces, apply one (1) coat of Sherwin Williams Seaguard

Ablative Antifouling Coating Red to a DFT of 2.5-4.0 mils.

6.8.5. To all Red surfaces, apply a second coat of Sherwin Williams Seaguard Ablative

Antifouling Coating Red to a DFT of 2.5-4.0 mils.

6.9. Painting (Line of Flotation and Above to include freeboard to main deck):

6.9.1. To all bared surfaces, apply one (1) coat Sherwin Williams MIL-DTL-24441/19C

Type III F159 Epoxy Polyamide Zinc Rich Primer to a DFT of 3-4mils.

6.9.2. To all primed surfaces apply one (1) coat of Sherwin Williams Seaguard, 5000

HS Epoxy Gray for a DFT of 5-7mils.

6.9.3. To all primer coated surfaces, apply a second (2) coat of Sherwin Williams

Seaguard, 5000 HS Epoxy Gray for a DFT of 5-7mils.

6.9.4. Apply 2 coats of a black paint

6.10. Painting (main deck):

6.10.1. Prime and apply 2 coats with a non-skid, deck gray

6.11. Reinstallation: Reinstall all removals. Contractor shall replace all missing, defective, and incorrect securements.

6.12. Hull Markings: Strike in the vessel's draft markings and names as original with white or black GOV COR approved, as required, for a DFT of 2-3 mils.

6.13. Vessel Undocking:

6.13.1. A minimum drying period of 24 hours, preferably longer, is necessary between final coat of antifouling paint and undocking to ensure solvent release.

6.13.2. Undock the vessel within 30 days after application of final coat of anti-fouling paint.

7. MANTIS CRANE MAT REPLACEMENT

7.1. Any operation of crane must be performed by qualified crane operator.

7.2. Complete all ‘daily’ maintenance checks before operating crane.

7.3. Mark and reference exact location of crane and crane mat on barge.

7.3.1. Remove crane from barge.

7.4. Replace crane matting with new matting per spec sheet.

7.5. Replace crane tie downs with new tie downs of same rating or higher.

7.6. Return crane to same location from where it was removed.

8. MISCELLANIOUS ITEMS AND REPAIRS

8.1. Replace eight (8) Kevel Chocks.

8.2. Replace six (6) double bitts.

8.3. Replace one (1) open chock on aft end.

8.4. Install one (1) recessed/flush mounted tie down fitting under crane hook stowed position.

8.5. Deck kevels, bitts and chocks shall be primed and painted black.

8.6. Remove all GOV identified raised and sharp protrusions on main deck.

8.7. Inspect all voids

8.7.1. Power or hand tool prep all areas that require preservation.

8.7.2. Prime and paint prepared areas with GOV approved void coating system.

8.7.3. Press up void 2 with fresh water prior to return delivery to GOV

9. OPTIONAL ADDITIONAL LABOR HOURS

9.1. Labor Hours: The Contractor shall provide a fully burdened labor rate for an estimated amount of labor hours for additional work required by a line item(s) and/or new work discovered during the performance of the contract.

9.2. Subject to the availability of funds

10. OPTIONAL ADDITIONAL MATERIALS

10.1. Materials: The Contractor shall provide materials and repairs for additional work by a line item(s) and/or new work discovered during the performance of the contract.

10.2. Subject to the availability of funds.