This document is a Questions and Answers (Q&A) document related to Solicitation Number 692M15-24-R-00001 for COD Supplemental Engineering & Technical Support Services. The solicitation is a follow-on contract to an existing IDIQ contract with the Federal Aviation Administration (FAA) Technical Center.
The Q&A clarifies details about the required labor categories, including education and experience requirements, as well as work schedules, telework allowances, pricing templates, and proposal submission instructions. Key details include that the contract will have a mix of new task areas as well as additional effort in existing task areas. There are SCA-covered labor categories, and the pricing template has been revised to address discrepancies between the solicitation and the template. The solicitation will use a tradeoff source selection process, and the incumbent contractor is BACIK Group LLC.
View the file
Other files for this federal contract opportunity
Show all 17
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
692M15-24-R-00001
| 04/04/2024 | |
| COD Supplemental Engineering & Technical Support Services |
SIR Questions and Answers
SOW Questions
| No. |
| Question |
Section/Para.
| Question |
| Answer |
| 1 |
| 2.2.1.2 |
What are the Definitions of Inspection Codes 1 - 4?
Inspection Codes define criticality of equipment and percent of inspection to those types of equipment. Ex. Inspection code 1- critical equipment, all equipment assigned to an inspector with this inspection code must be inspected 50%. So if there is 10 of these issued then 5 must be inspected.
| 2 |
| 2.2.1.2 |
| Can historical data be provided regarding the type and # of inspections per an identified time period? |
No. Inspections are typical of Operations and Maintenance which include ensuring preventive maintenance and service call tasks were completed in accordance with the requirements. See above question and section 2.2.1 in its entirety.
| 3 |
| C 2.2 |
Please provide a list of existing product and service contracts types.
The reference to contract management in this section is to describe the duties of the FAA Facilities Operation Branch. The information requested is not relevant for proposal purposes.
| 4 |
| C 2.2 |
| What are the existing software systems and respective functionalities currently under development or in-use? |
| CostWorks is used for estimating. |
Archibus is the facilities management software used by the Center Operations Division.
| 5 |
| C 2.2 |
| What are the tasks and deliverables required by contract support in regards to the metal shop? |
The Metal Shop is staffed by federal employees. No contract support is required at this time for work assigned specifically to the metal shop.
| 6 |
| C 2.2 |
| What is the current platform used for communications infrastructure at the WJHTC? |
The FAA utilizes fiber optic and CAT 5 cable. However, no direct support for communications is required under this contract, other than interfacing with those responsible for the infrastructure when a project could affect it.
| 7 |
| 2.2.1.6 |
| Is RCR equivalent to a Change Order Request? If not please define. |
| Record of Change Report- used to update equipment inventory and preventive maintenance procedures in our Archibus database |
| 8 |
| 8 |
What BAS(s) or BMS is FAA WJHTC currently using? (Johnson Controls, Schneider Electric, Crestron, Lutron, Siemens, Honeywell, others?)
Building Automation System- Andover
| 9 |
| 8 |
| The solicitation documents include increased planned hours when compared to the actual level of effort for the current contract for these services. Are there new task areas or is additional effort anticipated in the same task areas for this solicitation when compared to the current contract? |
| There are both new task areas and additional effort anticipated in the same task areas. |
New task areas include:
CLIN 1:
Space Management Coordinator (Management Analyst) – 1880 hours/year for years one through five;
Civil/Structural Engineer Senior – 1880 hours/year for year five;
Fire Protection Engineer Senior – 1880 hours/year for year five.
CLIN 2:
Fire Suppression Technician Senior – 1880 hours/year for years one through five.
Additional effort in the same task areas include:
CLIN 1:
Electrical Engineer Senior – additional 1880 hours/year for years one through five;
Architect Senior – additional 1880 hours/year for years three through five;
Mechanical Engineer Senior – additional
| 10 |
| 8 |
| Senior Electrical Engineering Technician Surge Support hours are listed twice. Please confirm that the total potential surge requirement for this position is (80) hours as documented. |
| The total potential surge requirement for this position is 80 hours. |
SIR Questions
| No. |
| Reference |
Section/Para.
| Question |
| Answer |
| 11 |
| 8 |
What is the full list of key personnel for this opportunity?
The SIR doesn’t have any key personnel evaluation factors.
| 12 |
| 8 |
| What documentation and details must be submitted regarding key personnel? |
| See revised SIR Section C 7.0, (Transition Period). |
| 13 |
| 8 |
| In what section of the response should key personnel documentation be provided? |
| See response to question 12. |
| 14 |
| F.2 |
| Are all resources identified with 1880 planned hours per year expected to be on-site at the WJHTC full-time during the period of performance during NHO? |
| See revised SIR Section C 1.2, (Work Schedules), paragraph 2 last sentence.: Contractor personnel with planned hours of 1880 are expected to be on-site during NHO. However, SIR Section H, H.9, (Telework) addresses that Situational Telework may be authorized to perform the work activities in this contract on a case-by-case basis for emergencies such as hazardous road conditions in the winter months, building closures, public transportation concerns, and in some instances-government shut-downs. |
| 15 |
| F.2 |
| Do any of the current resources support this effort partially through telework? |
| No labor category supports the requirement effort partially through telework. |
| 16 |
| F.2 |
| What positions and on average what proportion of time is spent in telework vs. on-site time? |
| All labor categories are on-site at the FAA, William J. Hughes Technical Center. |
| 17 |
| L.1c |
| Can an extension beyond 3/25/24 be provided so that respondents can incorporate information provided from question responses? |
| Amendment no. 0002 was uploaded to SAM.gov to extend the SIR until April 09, 2024. |
| 18 |
| 8 |
| What is the reference for a single "*" preceding role titles as found on pages: 12 for Electrical Engineer, 13 for Electrical Engineer, 15 for Electrical Engineering Technician, 16 for Fire Protection Engineering Technician, and 16 Mechanical Engineering Technician; |
| The single asterisks are Key Personnel Labor categories, see amendment no. 0004, revised Section C 9.0, (Labor Categories and Qualifications). |
| 19 |
| 8 |
| Confirm that the only SCA applicable Labor Categories are Civil Engineering Technician, Electrical Engineering Technician, Fire Protection Engineering Technician, Mechanical Engineering Technician, and Structural Engineering Technician |
| Yes, these are the applicable SCA labor categories for this SIR. |
| 20 | |
| B.2 | |
| Historically how many hours have been invoiced by position on an average month across the Period of Performance? | |
| Historical Number of Hours Invoiced Monthly by Position: |
CLIN 1 - Facilities Engineering
| Task Area Lead |
| 50.00 |
| Electrical Engineer Sr. |
| 143.87 |
| Civil Engineering Technician Sr. |
| 143.31 |
| Architect |
| 151.75 |
| Electrical Engineering Tech Sr |
| 152.41 |
| Electrical Engineering Tech Jr |
| 136.40 |
| Senior Planner/Scheduler |
| 152.14 |
| Construction Inspector |
| 467.61 |
| Mechanical Engineer Sr. |
| 152.10 |
CLIN II - Facilities Operations
| Task Area Lead |
| 6.00 |
| Mechanical Engineering Tech Sr |
| 302.13 |
| Structural Engineering Tech Jr |
| 148.80 |
| Electrical Engineering Tech Sr |
| 142.67 |
| Structural Engineering Tech Sr |
| 144.46 |
| 21 |
| 1.2 |
| Is 100% redundancy required for each position or only coverage of responsibilities during times of normal short-term absences? |
| The government does not require 100% redundancy for each position. |
| 22 |
| SIR, pg. 81. 1st para. |
| In reference to "Offerors are invited to submit questions in response to this SIR. Any questions or clarifications that an Offeror has regarding the content of the SIR package must be prepared and submitted to the Contracting Officer and Contract Specialist by the dates and times set forth above." Please confirm the proposal is to be submitted to the CO AND CS or just the CO? |
Please submit proposal to the Contract Specialist.
| 23 |
| SIR, L.9.3.2, pg. 85. 5th para |
| Is the Past Performance Point of Contract Summary Chart required if the Offeror is submitting CPARs? |
| Yes, see revised SIR Section L, L.9.3.2, (Part B: Contractor Performance Customer Survey Responses). |
| 24 |
| SIR, L.9.3.2, pg. 85. 5th para. |
| Is the Past Performance Point of Contract Summary Chart included in the 2-page page count? And is this info a separate section outside of Part A and Part B? |
The past performance summary chart is not included in the 2-page count for this section. As stated on page 90 “The Offeror must provide within the Past Performance proposal a summary chart that reflects each Past Performance reference.” The contract summary chart is outside of Part B.
| 25 |
| SIR, L.5, Table L5, pg. 81. |
Is there a page limit for each contract submitted in Attachment J-2?
No page limit for attachment J-2 Past Performance Evaluation Data Form.
| 26 |
| SIR, L.5, Table L5, pg. 81, and L.9.1 Annex #1 - executive Summary, pg. 83 |
| Is the preference for Annex #1 to be titled SIR Documentation or Executive Summary? |
| Annex #1 preference should read “Executive Summary”, see amendment no. 0004. |
| 27 |
| SIR, Price Proposal, L.9.4, pg. 90. Price Volume Content. |
| To confirm, is the Price Volume to consist of Attachment J-1 and a separate price document for submittal of "first page" and other information? |
| Yes |
| 28 |
| SIR, L.6, pg. 87, 2nd para. |
| In reference to "All pages should be numbered with section and page numbers," is the Offeror required to include the heading level 1 section number as part of the page number, or is this a requirement to include the factor or volume number? |
| This section only requires the Volume number and evaluation factor, see example below: |
Solicitation No.: 692M15-24-R-00001 Volume No.: II Factor 4: Past Performance Page:
| 29 |
| Attachment J-2 |
| Considering that corporate experience in relation to the SOW is discussed in Volume I, Factor 1 Corporate Experience, is SOW alignment also required as part of the last cell in Attachment 2 (i.e., "Contract Work Description"), or is this table cell in Attachment J-2 to focus only on the other items: "Quality of Service, Timeliness of Performance, Customer Satisfaction and Business Relations/ Integrity/ Effective Management and Ability to Manage Cost/Control Cost)"? |
| Per SIR Section L, L.9.3.1 (Part A: Past Performance Descriptions), the information provided on Attachment J-2 Past Performance Evaluation Data Form-Contract Work Description must address Quality of Service: Describe past compliance with contract requirements, accuracy of reports, appropriateness of personnel, technical excellence. •Timeliness of Performance: Detail how it met milestones, provided reliable delivery and continuity of services, was responsive to technical direction, and completed work on time. •Customer Satisfaction: Describe satisfaction of customers with the contractor’s service and product. •Business Relations/Integrity/Effective Management: Detail its business relations with the customer on previous contracts with emphasis on its effectiveness to manage the contract requirements, subcontracts and personnel while completing work on time. •Ability to Manage Cost/Control Cost: Describe past efforts to control costs under previous contracts |
| 30 |
| Attachment J-2 |
| Does Attachment 2 have a page limit? |
| Attachment J-2 Past Performance Evaluation Data Form doesn’t have a page limit. |
| 31 |
| SIR, Sec. F, pg. 21, para (2)(a) |
| In reference to "...whose resumes or other personal qualification were submitted with its offer…," are resumes to be submitted with the proposal? If so, are all staff resumes to be submitted or just key personnel? |
| Resumes are not required to be submitted with proposals, however, resumes for all personnel will be required during the transition period so the FAA can confirm personnel meet the contract requirements. |
There are a few differences between the number of hours in the solicitation versus those in the Excel budget template. Examples include the number of hours in CLIN 3 (Years 3 through 5) for the Electrical Engineering Technician Senior labor category, and the number of hours for the Mechanical Engineering Technician Senior labor category in CLIN 3 in Y3. This also affects the total number of hours (for example, in the solicitation tables on pp.17-18, CLIN 3 has 240 total hours in Y3, whereas in the budget template the total number of hours is 1040; this leads to an overall mismatch in the total number of hours in the solicitation vs the Excel budget). Please confirm if we should use the budget template as is or if the FAA will update the template to match the solicitation.
The number of hours in CLIN 3, years 3 through five, for the Electrical Engineering Technician Senior labor category is 80 per year.
The number of hours in CLIN 3, year 3, for the Mechanical Engineering Technician Senior labor category is 40. Total hours per year under CLIN 3 for years one through five is 240.
The template has been updated. See Amendment 0004, revised attachment J-1 Pricing Schedule Spreadsheet.
There is a discrepancy between a number of position/labor category titles in the solicitation detailed descriptions beginning on p. 10 vs those in the solicitation tables beginning on p. 17 vs those in the Excel budget template (e.g., Civil Engineering Technician vs Civil Engineering Technician Sr. vs Civil Technician Sr.). Some position titles also don't exactly match the titles in Attachment J.4 (Wage Determination). Will the FAA update the titles in the Excel budget template and/or in the solicitation tables starting on p. 17 to make sure that there is no accidental mismatch?
All Labor Categories have been updated in the SIR and Excel budget template. See Amendment 0004, revised attachment J-1 Pricing Schedule Spreadsheet.
Please read the conformance process section in the (J-4 Wage Determination) on SCA labor categories that don’t crosswalk the wage determination.
The solicitation states at the bottom of p. 90: "The Offeror must provide the following information on the first page of the Offeror’s pricing proposal:
1) Solicitation number.
2) Name and address of Offeror, CAGE code(s) and DUNS Number(s).
3) Total offered price (fully burdened rates times FAA-provided hours, plus NTE amounts provided for Materials and ODCs)
4) Name, address, telephone and email address of the Government cognizant contract audit office for the prime and each subcontractor, if available.
5) Name, address, telephone and email address of the Government cognizant contract administration office for the prime and each subcontractor, if available."
Since Vol. 3 (Price Volume) is only the Excel workbook with no additional write-up, can Offerors provide the 5 pieces of information pasted above in a new tab on the Excel workbook, instead of in a separate PDF or Word document? If so, since the current budget template is locked, can FAA issue a new budget template which is unlocked, or a new budget template with an additional unpopulated tab to allow for the entry of this information?
See revised attachment J-1 Pricing Schedule Spreadsheet Tab 1 Offeror Data Information Sheet.
The Excel budget template tabs are labeled CY24, CY25, etc. Yet the dates at the top do not correspond to calendar years (e.g., "5/1/2024-4/30/2025"). Can FAA confirm the performance period and will it relabel the tabs for clarity (e.g., PY1, PY2, etc. for "project year")
See revised attachment J-1 Pricing Schedule Spreadsheet, see amendment 0004.
Section B.3 states "The total estimated price for each CLIN is the sum of the total price labor, travel and ODCs from Attachment J-1." Section M.3.5 also refers to "2. CLINs with FAA provided Not-to-Exceed (NTE) amounts." The travel and ODC amounts are blank in the budget template. Please confirm.
See revised attachment J-1 Pricing Schedule Spreadsheet, see amendment 0004.
| Please confirm that, in accordance with the budget template, FAA will not evaluate the price associated with a potential 6-month extension per 3.2.4-34 OPTION TO EXTEND SERVICES (OCT 2019). |
| The Government is not evaluating pricing for a 6-month extension. |
| As a redundancy measure during submission, will the FAA provide a second email address for the final submission files? |
| See response to question 22. |
| 39 |
| Labor Rates |
Row 23, Cell E-F It appears that escalation is not being properly calculated in the referenced cells. Are offerors permitted to modify the escalation formula to correct any discrepancies we find when preparing our price?
See revised attachment J-1 Pricing Schedule Spreadsheet, see amendment 0004.
| 40 |
| 8.0 Labor Categories and Qualifications |
Education and Experience Requirements:
Section 8.0 of the SOW defines education and experience requirements for multiple labor categories, however not all of these labor category levels are included in Attachment J-1, the “Pricing Schedule Spreadsheet”. We have two questions which relate:
A.) Given that the government has already defined different levels in multiple labor categories, can Offerors expand the “Pricing Schedule Spreadsheet” to include rates for additional levels within each labor category?
B.) Can offerors expand the labor category and levels priced within Attachment J-1 to include additional labor category levels beyond Senior and Journeyman – e.g. “Development” and “Master”?
The Government only has requirements for either senior or journeyman levels within each category as stated on pages 17-18 of the SIR, which corresponds with the Pricing Schedule Spreadsheet.
| 41 |
| 8.0 Labor Categories and Qualifications |
*Electrical Engineer *Mechanical Engineer *Electrical Engineering Technician *Fire Protection Engineering Technician *Mechanical Engineering Technician
| Multiple labor categories within Section 8.0 of the SOW include an asterisk in front of the name. Will the government please explain the purpose of the asterisk notation in front of these labor categories? |
| See response to question 18. |
Miscellaneous Questions
| No. |
| Reference |
Section/Para.
| Question |
| Answer |
Is this contract a continuation/rebidding of an existing contract?
This requirement is a follow-on contract.
Is there any specific problem/situation that led to this acquisition request? – I notice in the SIR section 1.1, “normally accomplished by FAA employees,” is it then a shift of civil servant to contractor for the work?
This requirement is not a shift from Civil Servant to Contractor for this requirement.
Can you confirm there’s currently been no bid related to this listing? I see on sam.gov "0 Total number of Awards | 0 Total Number of Recipients" which I assume is my answer, but I want to be certain.
See response to question #42.
The LPTA methodology is renowned for its ability to streamline the procurement process, ensuring that all proposals meet predefined minimum technical standards while leveraging competitive pricing to secure the best value for the government. This approach not only simplifies the evaluation process but also encourages a wider range of competitors, potentially including innovative small businesses and service-disabled veteran-owned small businesses, to participate by focusing on technical competency and cost-effectiveness rather than subjective criteria that may inadvertently favor incumbents or larger entities with more extensive past performance portfolios.
Could you kindly detail the rationale behind the chosen procurement strategy, particularly in terms of how it aligns with the overarching goal of achieving the best possible outcome for the government and the taxpayer, while ensuring a fair and open competition that encourages diversity and innovation among service providers?
In accordance with AMS Procurement Guidance the FAA has determined that the tradeoff process is appropriate, because the day-to-day requirements do not lend themselves to being fully defined, and there is greater performance risk. The technical considerations play a dominant role in this source selection.
Is there an incumbent contract? If so what are the contract and/or task order numbers? Who is the awardee? Are there any other follow-ons released in tandem to 692M15-24-R-00001?
1. Yes, there is an incumbent.
2. IDIQ no. DTFACT-17-D-00009/692M15-18-F-00417.
3. Awardee is BACIK Group LLC.
4. No other follow-on will be released in tandem with SIR 692M15-24-R-00001.