Updated_Bid_Sheet.pdf

PDF 158 KB Posted

Attached to
Replace & Install Steel Grating Covers Federal contract opportunity
Solicitation number
6923G5B0005
Issued by
Department of Transportation Saint Lawrence Seaway Development Corporation

About this file

Revised Bid Sheet

View the file

Other files for this federal contract opportunity

Other files attached to Replace & Install Steel Grating Covers, newest first.
File Type Posted
Amendment_0004.pdf PDF
Amendment_0003.pdf PDF
SLS-370-243_3_R1dwg.pdf PDF
Amendment_0002.pdf PDF
SLS_370_243_3_(1).pdf PDF
Amendment_0001.pdf PDF
327-C-20-134.pdf PDF
Wage_Determination_NY190009.pdf PDF
SLS_370_243_1_(1).pdf PDF
SLS_370_243_3_(1).pdf PDF
327-C-20-130.pdf PDF
326-C-20-130.pdf PDF
SLS_370_243_2_(1).pdf PDF
IFB_Gratings_Final.pdf PDF
326-C-20-135.pdf PDF
SLS_370_243_2_(1).pdf PDF
Show all 16

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

IFB # 6923G5B0005 Page 4 of 38

PART I

SECTION B

SUPPLIES OR SERVICES AND PRICES/COSTS

BID SCHEDULE

Furnish all plant, labor, equipment and materials and perform all work at Eisenhower and Snell Locks to replace existing culvert valve bulkhead recess gratings with new gratings rated for AASHTO H-20 traffic loading. The work includes furnishing and installing new frames in the recess openings to fit the increased depth of the new gratings. All work shall be performed in accordance with the contract drawings and specifications.

BASIC REQUIREMENT-EISENHOWER AND SNELL LOCKS-NORTH SIDE.

Item No.

Description Quantity Unit Unit Price Total

1. Mobilization and Demobilization For The Job $__________ $__________

2. Provide all plant, equipment and labor to remove existing gratings and frames, enlarge the seat recesses around the bulkhead recess opening perimeter to fit the increased size of the frames for the new gratings, furnish new larger frames and install these frames in culvert valve bulkhead recess openings at Eisenhower and Snell Locks, all in accordance with the contract drawings and specifications.

For The Job $__________ $__________

3. Place new H-20 gratings into the new frames installed in the culvert valve bulkhead recess openings at Eisenhower and Snell Locks per Item No. 2 above.

For The Job $__________ $__________

4. Modify and fill in with concrete the side beam pocket recesses at downstream Eisenhower Lock recess gratings to accommodate new gratings.

2 Each $__________ $__________

5. Furnish new “Type A” H-20 rated gratings in accordance with the contract drawings.

2 Each $__________ $__________

6. Furnish new “Type B” H-20 rated gratings in accordance with the contract drawings.

6 Each $__________ $__________

TOTAL-BASIC REQUIREMENT $___________

IFB # 6923G5B0005 Page 5 of 38

OPTIONAL REQUIREMENT-EISENHOWER AND SNELL LOCKS-SOUTH SIDE.

Item No.

Description Quantity Unit Unit Price Total

7. Mobilization and Demobilization For The Job $__________ $___________

8. Provide all plant, equipment and labor to remove existing gratings and frames, enlarge the seat recesses around the bulkhead recess opening perimeter to fit the increased size of the frames for the new gratings, furnish new larger frames and install these frames in culvert valve bulkhead recess openings at Eisenhower and Snell Locks, all in accordance with the contract drawings and specifications.

For The Job $__________ $___________

9. Place new H-20 gratings into the new frames installed in the culvert valve bulkhead recess openings at Eisenhower and Snell Locks per Item No. 2 above.

For The Job $__________ $___________

10. Modify and fill in with concrete the side beam pocket recesses at downstream Eisenhower Lock recess gratings to accommodate new gratings.

2 Each $__________ $___________

11. Furnish new “Type A” H-20 rated gratings in accordance with the contract drawings.

2 Each $__________ $___________

12. Furnish new “Type B” H-20 rated gratings in accordance with the contract drawings.

6 Each $__________ $___________

TOTAL-OPTIONAL REQUIREMENT $___________

INSTRUCTIONS FOR BIDDERS:

1. SLSDC will evaluate offers for award purposes by adding the prices for all the Basic and Optional Requirement Line Items.

2. Offerors must include bid prices for all Basic and Optional Requirement items to be considered responsive.

3. SLSDC may, or may not award any or all line items dependent upon the availability of funds.

4. The Mobilization and Demobilization line item cannot exceed 5% of the respective requirement total for both the basic and optional requirement.

Signature ______________________________ Date:

END OF SECTION B