RFQ USMMA Women's Locker Rooms Renovation
Solicitation number
6923G226Q000017
Issued by
Nassau County, New York

About this file

Summary

This is a Request for Proposal (RFP) and Solicitation/Contract Form (SF-1449) issued by the U.S. Merchant Marine Academy (USMMA), a component of the Maritime Administration under the U.S. Department of Transportation, for renovation services at the Tomb Field Women's Locker Room located at 300 Steamboat Road, Kings Point, New York 11024. The scope of work encompasses comprehensive renovation of multiple areas including the entrance hallway, women's locker room, visitors locker room, visitor bathroom, and women's shower facilities. Work includes flooring installation (rubber flooring with vinyl cove base), replacement of 59 total lockers (34 in women's locker room and 25 in visitors locker room), masonry repairs, painting, HVAC work including pipe insulation and fan controls, electrical upgrades (lighting fixture replacement and GFCI receptacle installation), ceiling installation, plumbing work, and bathroom fixtures/accessories. A tentative site visit is scheduled for June 15, 2026 at 10:00 AM EST, with questions due by June 18, 2026 at 6:00 PM. Offers are due on June 25, 2026 by 1:00 PM EST via email submission. The Period of Performance runs from July 1, 2026 to February 1, 2027, with possible extension for locker delivery based on manufacturer lead times and Contracting Officer approval.

This is a Total Small Business Set-Aside contract under NAICS code 236220 (Commercial and Institutional Building Construction) with a Firm-Fixed-Price (FFP) structure requiring separate pricing for two Contract Line Item Numbers: CLIN 00001 for locker room renovations and CLIN 00002 for new lockers. Award will be made based on best value methodology, with technical factors (understanding of scope, work plan and execution strategy, and technical experience) weighted more heavily than price. Offerors must provide proof of certification to perform general construction work in New York, submit minimum three project references with similar scope and complexity, and provide comprehensive pricing breakdowns including fully burdened labor rates, indirect costs, and equipment specifications. Insurance requirements include General Liability coverage of $500,000 per occurrence and $100,000 per person for bodily injury, Automobile Liability of $200,000 per person and $500,000 per occurrence, and Workers' Compensation as required by law. The contracting team includes Theodore Nigro as Contracting Officer, Amit Narine as Administrative Contracting Officer, and Charles F. McInnis as the Contracting Officer's Representative for technical oversight. All invoices must be submitted electronically through the Department of Transportation's Delphi eInvoicing web portal, and contractors are required to provide one-year warranties on materials and labor plus manufacturer warranties on equipment.

View the file

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

SEE ADDENDUMIS CHECKED

CODE 18a. PAYMENT WILL BE MADE BY

CODE

FACILITYCODE

17b. CHECK IF REMITTANCE IS DIFFERENT AND PUT SUCH ADDRESS IN OFFER

OFFEROR

6923G2

KINGS POINT NY 11024-1699

300 STEAMBOAT ROAD

USMMA PROCUREMENT

MARITIME ADMINISTRATION

MARAD-00095 CODE 16. ADMINISTERED BYCODE

X

X

X

236220

SIZE STANDARD:

100.00 % FOR:SET ASIDE:UNRESTRICTED OR6923G2

REQUEST FOR

PROPOSAL

(RFP)

INVITATION

FOR BID (IFB)

10. THIS ACQUISITION ISCODE

REQUEST FOR

QUOTE (RFQ)

14. METHOD OF SOLICITATION

13b. RATING

NORTH AMERICAN INDUSTRY

CLASSIFICATION STANDARD

(NAICS):

SMALL BUSINESS

06/25/2026 1300 ET

06/11/2026

516-726-6032AMIT NARINE

(No collect calls)

INFORMATION CALL:

FOR SOLICITATION 8. OFFER DUE DATE/LOCAL TIMEb. TELEPHONE NUMBER a. NAME

4. ORDER NUMBER3. AWARD/ 6. SOLICITATION

6923G226Q000017

5. SOLICITATION NUMBER

SOLICITATION/CONTRACT/ORDER FOR COMMERCIAL ITEMS 1. REQUISITION NUMBER PAGE OF

1 47 MMAPR520726000132OFFEROR TO COMPLETE BLOCKS 12, 17, 23, 24, & 30

TELEPHONE NO.

17a. CONTRACTOR/

KINGS POINT NY 11024-1699

300 STEAMBOAT ROAD

US DOTMARITIME ADMINISTRATION

USMERCHANT MARINE ACADEMY PROCURE

15. DELIVER TO

KINGS POINT NY 11024-1699

300 STEAMBOAT ROAD

USMMA PROCUREMENT

9. ISSUED BY

7.

2. CONTRACT NO.

EFFECTIVE DATE

$45

18b. SUBMIT INVOICES TO ADDRESS SHOWN IN BLOCK 18a UNLESS BLOCK BELOW

ISSUE DATE

DELIVERY FOR FREE ON BOARD

(FOB) DESTINATION UNLESS

BLOCK IS MARKED

11.

SEE SCHEDULEX

12. DISCOUNT TERMS THIS CONTRACT IS A RATED

ORDER UNDER THE DEFENSE

PRIORITIES AND ALLOCATIONS

SYSTEM - DPAS (15 CFR 700)

13a.

SERVICE-DISABLED

VETERAN-OWNED

SMALL BUSINESS

(SDVOSB)

HUBZONE SMALL

BUSINESS

8(A)

MARITIME ADMINISTRATION

WOMEN-OWNED SMALL

BUSINESS (WOSB)

ECONOMICALLY DISADVANTAGED

WOMEN-OWNED SMALL

BUSINESS (EDWOSB)

24.

AMOUNT

23.

UNIT PRICE

22.

UNIT

21.

QUANTITY

20.

SCHEDULE OF SUPPLIES/SERVICES

19.

ITEM NO.

The purpose of this solicitation is to award a Firm-Fixed-Price (FFP) Contract to renovate the Tomb Field Women¿s Locker Room and provide new lockers located on the campus of the U.S.

Merchant Marine Academy (USMMA), 300 Steamboat Road, King's Point, New York 11024.

All work must be in accordance with the attached Statement of Work (SOW) and the contract terms, conditions, and clauses included herein.

Period of Performance: 07/01/2026 to 02/01/2027

(Use Reverse and/or Attach Additional Sheets as Necessary)

HEREIN, IS ACCEPTED AS TO ITEMS:

XX

DATED

Theodore J. Nigro

. YOUR OFFER ON SOLICITATION (BLOCK 5),

INCLUDING ANY ADDITIONS OR CHANGES WHICH ARE SET FORTH

COPIES TO ISSUING OFFICE. CONTRACTOR AGREES TO FURNISH AND DELIVER

ARE

ARE

31c. DATE SIGNED

27b. CONTRACT/PURCHASE ORDER INCORPORATES BY REFERENCE FAR 52.212-4. FAR 52.212-5 IS ATTACHED. ADDENDA

31a. UNITED STATES OF AMERICA (SIGNATURE OF CONTRACTING OFFICER)

30c. DATE SIGNED 31b. NAME OF CONTRACTING OFFICER (Type or print)

ALL ITEMS SET FORTH OR OTHERWISE IDENTIFIED ABOVE AND ON ANY ADDITIONAL

SHEETS SUBJECT TO THE TERMS AND CONDITIONS SPECIFIED.

27a. SOLICITATION INCORPORATES BY REFERENCE (FEDERAL ACQUISITION REGULATION) FAR 52.212-1, 52.212-4. FAR 52.212-3

AND 52.212-5 ARE ATTACHED. ADDENDA

26. TOTAL AWARD AMOUNT (For Government Use Only)

OFFER

STANDARD FORM 1449 (REV. 11/2021)

Prescribed by GSA - FAR (48 CFR) 53.212

ARE NOT ATTACHED.

ARE NOT ATTACHED.

AUTHORIZED FOR LOCAL REPRODUCTION

PREVIOUS EDITION IS NOT USABLE

30b. NAME AND TITLE OF SIGNER (Type or print)

30a. SIGNATURE OF OFFEROR/CONTRACTOR

28. CONTRACTOR IS REQUIRED TO SIGN THIS DOCUMENT AND RETURN

25. ACCOUNTING AND APPROPRIATION DATA

29. AWARD OF CONTRACT: REFERENCE

32e. MAILING ADDRESS OF AUTHORIZED GOVERNMENT REPRESENTATIVE

32c. DATE 32b. SIGNATURE OF AUTHORIZED GOVERNMENT REPRESENTATIVE

ACCEPTED, AND CONFORMS TO THE CONTRACT, EXCEPT AS NOTED:

32a. QUANTITY IN COLUMN 21 HAS BEEN

RECEIVED INSPECTED

40. PAID BY39. S/R VOUCHER NUMBER38. S/R ACCOUNT NUMBER

37. CHECK NUMBER

FINALPARTIAL

36. PAYMENT

FINALPARTIAL

35. AMOUNT VERIFIED

CORRECT FOR

34. VOUCHER NUMBER33. SHIP NUMBER

COMPLETE

32g. E-MAIL OF AUTHORIZED GOVERNMENT REPRESENTATIVE

42d. TOTAL CONTAINERS42c. DATE REC'D (YY/MM/DD)

42b. RECEIVED AT (Location)

42a. RECEIVED BY (Print)

41c. DATE41b. SIGNATURE AND TITLE OF CERTIFYING OFFICER

41a. I CERTIFY THIS ACCOUNT IS CORRECT AND PROPER FOR PAYMENT

STANDARD FORM 1449 (REV. 11/2021) BACK

24.

AMOUNT

23.

UNIT PRICE

22.

UNIT

21.

QUANTITY

20.

SCHEDULE OF SUPPLIES/SERVICES

19.

ITEM NO.

00001 DELIVERABLES

The Contractor is responsible for all the work areas outlined in the below Sections:

1. ENTRANCE HALLWAY - Preparation

A) Flooring

B) Masonry (Walls & Columns)

C) Painting (Walls & Doors)

D) HVAC

E) Electrical

F) Miscellaneous

2. WOMEN'S LOCKER ROOM

A) Flooring

B) Lockers (Replacement)

C) Masonry (Walls & Columns)

D) Painting (Walls)

E) HVAC

F) Electrical

G) Miscellaneous

2. VISITORS LOCKER ROOM

A) Flooring

B) Lockers (Replacement)

C) Masonry (Walls & Columns)

D) Painting (Walls & Doors)

E) HVAC

F) Electrical

Continued ...

32f. TELEPHONE NUMBER OF AUTHORIZED GOVERNMENT REPRESENTATIVE

32d. PRINTED NAME AND TITLE OF AUTHORIZED GOVERNMENT REPRESENTATIVE

47 2 of

ITEM NO. SUPPLIES/SERVICES QUANTITY UNIT UNIT PRICE AMOUNT

NAME OF OFFEROR OR CONTRACTOR

3 47

CONTINUATION SHEET

REFERENCE NO. OF DOCUMENT BEING CONTINUED PAGE OF

(A) (B) (C) (D) (E) (F)

6923G226Q000017

G) Miscellaneous

4. VISTOR'S BATHROOM

A) Flooring

B) Masonry (Walls)

C) Painting

D) HVAC

E) Electrical

F) Ceiling

G) Miscellaneous

5. WOMEN'S SHOWER

A) Flooring

B) Tile Walls

C) Masonry

D) HVAC

E) Electrical

F) Ceiling

G) Plumbing

H) Miscellaneous

00002 Purchase of New Lockers IAW SOW:

QUANTITY, UNIT OF ISSUE & PRICE

Please include total cost of all lockers.

NSN 7540-01-152-8067 OPTIONAL FORM 336 (4-86)

Sponsored by GSA

FAR (48 CFR) 53.110

6923G226Q000017 PAGE 4 OF 47

Section A SOLICITATION/CONTRACT FORM See SF-1449 Form (Pages 1-3)

Section B SUPPLIES OR SERVICES AND PRICE/COSTS.

All services and supplies shall be performed, delivered, and invoiced via a Firm-Fixed-Price (FFP) contract against one of the two (2) Contract Line Item Numbers (CLIN) shown below.

CLIN 00001 LOCKER ROOMS RENOVATION

CLIN 00002 NEW LOCKERS

6923G226Q000017 PAGE 5 OF 47

Section C STATEMENT OF WORK (SOW)

BACKGROUND

The United States Merchant Martine Academy (USMMA) is an agency of the Maritime Administration (MARAD) managed by the United States Department of Transportation.

The USMMA is listed on the National Register of Historic Places. Therefore, all work shall be consistent with the Secretary of the Interior's Standards for the Treatment of Historic Properties (36 CFR part 68) http://www.nps.gov/tps/standards/four-treatments/treatment-guidelines.pdf.

All work shall meet or exceed the standards provided in the Secretary of the Interior’s Standards for Rehabilitation and guidelines for applying the standards published by the National Park Service, U.S. Department of the Interior 36 CFR 67.7

- Standards for rehabilitation.

The contractor shall be aware of the potential presence of hazardous materials, specifically lead-based paint, and/or asbestos, in any buildings located at the USMMA. It is the responsibility of the contractor to act appropriately in accordance with all local, state, and federal environmental and occupational safety and health laws and regulations.

SCOPE

The USMMA seeks a qualified, experienced, and insured contractor to provide labor, material, transportation, tools, equipment, and supervision to perform renovations and repairs at the Tomb Memorial Field Women’s Locker Room.

Although Lead Abatement or Asbestos Abatement work is not projected to be required, it is within the scope of this contract to perform necessary abatement if identified. If the Contractor identifies suspected lead paint, asbestos or other hazardous materials, the contractor shall immediately report the particulars to the Contracting Officer’s Representative (COR) and Administrative Contracting Officer (ACO) for further action.

SCOPE DESCRIPTION AND DELIVERABLES

The Contractor is responsible to perform and deliver all specified services and supplies stated below.

1. Entrance Hallway

1.1 Flooring

1.1.1 Remove existing rubber flooring and base completely .

1.1.2 Remove all existing floor coverings, adhesives, coatings, sealers, and contaminants from the concrete substrate.

1.1.3 Adhesive removal shall be performed mechanically (e.g., grinding, shot blasting, or scarifying).

1.1.4 Chemical adhesive removers are not permitted.

1.1.5 Thoroughly clean the concrete surface following mechanical preparation.

1.1.6 Remove all dust, debris, oils, soap residue, and loose material using HEPA vacuuming and approved cleaning methods.

1.1.7 Concrete shall be left clean, sound, and dry prior to testing and repairs.

1.1.8 If moisture levels exceed acceptable limits, provide and install a manufacturer-approved moisture mitigation system compatible with the specified rubber flooring.

1.1.9 Moisture mitigation materials shall be installed strictly per manufacturer instructions and allowed to cure as required.

1.1.10 Retesting shall be performed as necessary prior to flooring installation.

1.1.11 Repair all cracks, spalled areas, holes, and surface defects using compatible patching or crack-repair materials.

1.1.12 Feather and smooth repairs to provide a uniform substrate.

6923G226Q000017 PAGE 6 OF 47

1.1.13 Mechanically prepare the concrete to achieve a suitable surface profile for rubber flooring adhesive bonding

(ICRI CSP 1–2).

1.1.14 Over-polishing of the slab is not permitted.

1.1.15 Perform final vacuuming and cleaning immediately prior to flooring installation.

1.1.16 Ensure the substrate is dry, dust-free, and within required temperature and humidity ranges.

1.1.17 Acclimate new rubber flooring materials and adhesives in the installation area for a minimum of 48–72 hours prior to installation. Maintain space at normal operating temperature and humidity during acclimation and installation.

1.1.18 Furnish and install new Regupol Aktiv 3/8 flooring, 48” wide AK10103 Blue Streak with Reguseal sealer.

Approximately 60 sq ft. Contractor to verify.

1.1.19 Furnish and install new 6” black vinyl cove base on the full perimeter. Approximately 40 linear feet. Contractor to verify.

1.1.20 After the rubber floor installation is complete and sealant adequately dry, install complete floor protection for the duration of the project until locker installation. The floor protection shall be per manufactureres recommended best practices, to include two overlapping layers of protection, masonite for high traffic areas and no use of duct tape on the new flooring or walls.

1.2 Masonry

1.2.1 Repair and patch all holes, surface imperfections, and missing masonry units in existing block walls to the ceiling, in order to provide a smooth, uniform finish

1.2.2 Grind all abandoned pipe sleeves and protrusions flush with the finished wall surface, and patch the resulting openings with cementitious fill to achieve a smooth, uniform finish.

1.2.3 Remove all excess spray foam insulation and patch affected areas to match the surrounding wall finish.

1.1.1 Repair all column bases

1.3 Painting

1.3.1 Remove all rust and thoroughly clean exposed steel joists and framing. Clean, sand, and otherwise prepare the doors and door frames to receive paint, including removal of dirt, grease, and loose or peeling coatings.

1.3.2 Apply one full coat of Benjamin Moore Fresh Start® Rust-Inhibitive Primer (oil based) No 094, or approved equivalent, to all steel joists, metal doors and metal frames.

1.3.3 Apply one full coat of Benjamin Moore Fresh Start® High Hiding All Purpose Primer No. 046 00 to the ceiling, Kindorf framing and electrical conduits.

1.3.4 Apply two full finish coats of Benjamin Moore Super Hide Latex Flat White #282.01, or approved equivalent, to the ceiling, steel joists, kindorf framing, and electrical conduits.

1.3.5 Repair, patch, and smooth all holes, cracks, and surface imperfections in the walls. Caulk all perimter panel gaps and open joints. Clean all wall surfaces to ensure proper paint adhesion.

1.3.6 Apply one full coat of Benjamin Moore Fresh Start® Primer No. 046 00, or approved equivalent, to all walls.

1.3.7 Apply two full finish coats of Sherwin Williams Classic French Gray – Suburban Modern Eggshell, SW 0077, to north and south walls.

1.1.2 Apply two full finish coats of Sherwin-Williams Blue Chip Eggshell, SW 6959, to the east and west walls.

1.1.3 Apply two full finish coats of Sherwin Williams Classic French Gray – Suburban Modern, oil based paint, SW

0777, to all sides of the doors and frames.

6923G226Q000017 PAGE 7 OF 47

1.2 HVAC

1.2.1 Secure all piping with Kindorf or approved equivalent support systems, installed in accordance with applicable codes, manufacturer requirements, and standard industry practices.

1.2.2 Install fiberglass insulation on all exposed piping using a professional pipe-wrapping method. Installation shall be performed by a qualified pipe wrapper to achieve a smooth, uniform, and code-compliant finish.

Hand-wrapped, makeshift, or non-professional installations are not acceptable. All work shall comply with applicable codes, manufacturer requirements, and standard industry practices.

1.2.3 Existing insulation may remain in place where it is intact and in good condition. Repair, patch, or re wrap insulation as necessary to restore full coverage and performance.

1.3 Electric

1.3.1 Remove and properly dispose of three (3) existing ceiling-mounted light fixtures

1.3.2 Furnish and install three (3) new LED ceiling-mounted light fixtures, Lithonia Lighting 4 ft 4188 Lumen Neutral

White LED Wraparound Light, or approved equivalent. Contractor shall provide a detailed lighting layout and fixture placement plan for review and approval by the Contracting Officer Representative (COR) prior to installation.

1.3.3 Provide emergency lighting and exit signage throughout the locker room and all required means of egress in full compliance with NFPA 101, IBC, NEC Article 700, and applicable local amendments.

1.3.4 Inspect all existing electrical switches, receptacles, conduit, juncture boxes, and wiring within the area. Repair or replace components as necessary to ensure full compliance with NFPA 70 (National Electrical Code) requirements.

1.4 Miscellaneous

1.4.1 Remove board on hallway wall for wall preparation and painting. COR to verify if board to be rehung after painting.

1.4.2 Existing steel locker room front door with piano hinge shall remain in place where found to be structurally sound and operational. Contractor shall repair surface corrosion, prepare, prime, and repaint door and frame.

Replace door assembly only if existing door is damaged, inoperable, or non-compliant with applicable code requirements.

1.4.3 Remove and replace three (3) existing metal interior doors with like-kind door leaves. Existing frames shall remain where serviceable; repair or replace frames as required to ensure proper fit and operation. Provide and install new hinges, closers, locksets, kick plates, door stops, and door holder(s) as required. Door holder(s) shall allow doors to remain in the open position while maintaining proper floor clearance. All work shall comply with applicable codes and manufacturer requirements.

1.4.4 Exterior plywood panel adjacent to the front door shall be prepared for painting by scraping and removing all loose and failing paint, sanding smooth, cleaning the surface, and repairing minor defects with exterior‑grade wood filler. All bare wood and repaired areas shall be primed with an exterior‑grade bonding primer compatible with the finish coat. Contractor shall apply two coats of exterior acrylic latex paint, color and sheen as directed, to achieve a uniform, durable, weather‑resistant finish free of runs, peeling, or overspray; paint samples shall be submitted to the COR for approval prior to application.

6923G226Q000017 PAGE 8 OF 47

6923G226Q000017 PAGE 9 OF 47

2. Women’s Locker Room

2.1 Flooring

2.1.1 Remove existing rubber flooring and base completely .

2.1.2 Remove all existing floor coverings, adhesives, coatings, sealers, and contaminants from the concrete substrate.

2.1.3 Adhesive removal shall be performed mechanically (e.g., grinding, shot blasting, or scarifying).

2.1.4 Chemical adhesive removers are not permitted.

2.1.5 Thoroughly clean the concrete surface following mechanical preparation.

2.1.6 Remove all dust, debris, oils, soap residue, and loose material using HEPA vacuuming and approved cleaning methods.

2.1.7 Concrete shall be left clean, sound, and dry prior to testing and repairs.

2.1.8 If moisture levels exceed acceptable limits, provide and install a manufacturer-approved moisture mitigation system compatible with the specified rubber flooring.

2.1.9 Moisture mitigation materials shall be installed strictly per manufacturer instructions and allowed to cure as required.

2.1.10 Retesting shall be performed as necessary prior to flooring installation.

2.1.11 Repair all cracks, spalled areas, holes, and surface defects using compatible patching or crack-repair materials.

2.1.12 Feather and smooth repairs to provide a uniform substrate.

2.1.13 Mechanically prepare the concrete to achieve a suitable surface profile for rubber flooring adhesive bonding

(ICRI CSP 1–2).

2.1.14 Over-polishing of the slab is not permitted.

2.1.15 Perform final vacuuming and cleaning immediately prior to flooring installation.

2.1.16 Ensure the substrate is dry, dust-free, and within required temperature and humidity ranges.

2.1.17 Acclimate new rubber flooring materials and adhesives in the installation area for a minimum of 48–72 hours prior to installation. Maintain space at normal operating temperature and humidity during acclimation and installation.

6923G226Q000017 PAGE 10 OF 47

2.1.18 Furnish and install new Regupol Aktiv 3/8 flooring, 48” wide AK10103 Blue Streak with Reguseal sealer.

Approximately 518 sq ft. Contractor to verify.

2.1.19 Furnish and install new 6” black vinyl cove base on the full perimeter. Approximately 90 linear feet. Contractor to verify.

2.1.20 After the rubber floor installation is complete and sealant adequately dry, install complete floor protection for the duration of the project until locker installation. The floor protection shall be per manufactureres recommended best practices, to include two overlapping layers of protection, masonite for high traffic areas and no use of duct tape on the new flooring or walls.

2.2 Lockers

2.2.1 Remove and dispose of 33 existing metal lockers

2.2.2 Furnish and install thirty-four (34) new lockers to match the Tomb Field Men’s Lockers installed in 2025. Locker configuration and layout shall conform to the proposed layout attached.

2.2.3 Final locker layout and configuration to be approved by Contracting Officer Representative (COR) prior to manufacture of the lockers.

2.2.4 Relocate existing electrical conduits, HVAC controllers, piping, and/or outlets as required to accommodate the approved locker layout.

2.3 Masonry

2.3.1 Repair and patch all holes, surface imperfections, and missing masonry units in existing block walls to the ceiling, in order to provide a smooth, uniform finish.

2.3.2 Grind all abandoned pipe sleeves and protrusions flush with the finished wall surface, and patch the resulting openings with cementitious fill to achieve a smooth, uniform finish.

2.3.3 Remove all excess spray foam insulation and patch affected areas to match the surrounding wall finish.

2.3.4 Repair all coloumn bases

2.4 Painting

2.4.1 Remove all rust and thoroughly clean exposed steel joists and framing. Clean, sand, and otherwise prepare the entrance door and door frame to receive paint, including removal of dirt, grease, and loose or peeling coatings.

2.4.2 Apply one full coat of Benjamin Moore Fresh Start® Rust-Inhibitive Primer (oil based) No 094, or approved equivalent, to all steel joists, metal doors and metal frames.

2.4.3 Apply one full coat of Banjamin Moore Fresh Start® High-Hiding All-Purpose Primer No. 046-00 to the ceiling, Kindorf framing, electrical conduits, and ductwork.

2.4.4 Apply two full finish coats of Benjamin Moore Super Hide Latex Flat White #282.01, or approved equivalent, to the ceiling, steel joists, kindorf framing, electrical conduits, and ductwork.

2.4.5 Repair, patch, and smooth all holes, cracks, and surface imperfections in the walls. Caulk all perimter panel gaps and open joints. Clean all wall surfaces to ensure proper paint adhesion.

2.4.6 Apply one full coat of Benjamin Moore Fresh Start® Primer No. 046-00, or approved equivalent, to all walls.

2.4.7 Apply two full finish coats of Sherwin-Williams Classic French Gray – Suburban Modern Eggshell, SW 0077, to north and south walls.

2.4.8 Apply two full finish coats of Sherwin-Williams Blue Chip Eggshell, SW 6959, to the east and west walls.

2.4.9 Apply two full finish coats of Sherwin-Williams Classic French Gray – Suburban Modern, oil-based paint, SW

0777, to all sides of the entrance door and door frame.

6923G226Q000017 PAGE 11 OF 47

2.5 HVAC

2.5.1 Secure all piping with Kindorf or approved equivalent support systems, installed in accordance with applicable codes, manufacturer requirements, and standard industry practices.

2.5.2 Install fiberglass insulation on all exposed piping using a professional pipe-wrapping method. Installation shall be performed by a qualified pipe wrapper to achieve a smooth, uniform, and code-compliant finish.

Hand-wrapped, makeshift, or non-professional installations are not acceptable. All work shall comply with applicable codes, manufacturer requirements, and standard industry practices.

2.5.3 Existing insulation may remain in place where it is intact and in good condition. Repair, patch, or re-wrap insulation as necessary to restore full coverage and performance.

2.5.4 Provide, install, and commission a standalone digital programmable timer/control for the main exhaust fan, capable of scheduled automatic operation during occupancy sensors/hours. (Same scope to be performed for Men’s Locker Room Exhaust Fan – See Miscellaneous)

2.5.5 Remove and replace two (2) existing metal duct vent covers.

2.6 Electric

2.6.1 Remove and properly dispose of six (6) existing ceiling-mounted light fixtures

2.6.2 Furnish and install six (6) new LED ceiling-mounted light fixtures, Lithonia Lighting 4-ft 4188-Lumen Neutral

White LED Wraparound Light, or approved equivalent. Contractor shall provide a detailed lighting layout and fixture placement plan for review and approval by the Contracting Officer Representative (COR) prior to installation.

2.6.3 Remove and replace the existing electrical outlet near the entrance door with a new tamper-resistant (TR), GFCI-protected, damp-location-rated quad receptacle, installed complete and operable

2.6.4 Furnish and install one (1) additional GFCI-protected, damp-location-rated quad receptacle on the opposite side of the locker room at a location approved by the COR.

2.6.5 Relocate existing electrical conduits, HVAC control devices, and/or electrical outlets as required to accommodate the finalized and approved locker room layout.

2.6.6 Provide emergency lighting and exit signage throughout the locker room and all required means of egress in full compliance with NFPA 101, IBC, NEC Article 700, and applicable local amendments.

2.6.7 Inspect all existing electrical switches, receptacles, conduit, juncture boxes, and wiring within the area. Repair or replace components as necessary to ensure full compliance with NFPA 70 (National Electrical Code) requirements.

2.7 Miscellaneous

2.7.1 Inspect, repair, and clean two (2) existing windows as required

2.7.2 In the Men’s Locker Room, provide, install, and commission a standalone digital programmable timer/control for the main exhaust fan, capable of scheduled automatic operation during occupancy sensors/hours.

6923G226Q000017 PAGE 12 OF 47

6923G226Q000017 PAGE 13 OF 47

3. Visitors Locker Room

3.1 Flooring

3.1.1 Remove existing rubber flooring and base completely .

3.1.2 Remove all existing floor coverings, adhesives, coatings, sealers, and contaminants from the concrete substrate.

3.1.3 Adhesive removal shall be performed mechanically (e.g., grinding, shot blasting, or scarifying).

3.1.4 Chemical adhesive removers are not permitted.

3.1.5 Thoroughly clean the concrete surface following mechanical preparation.

3.1.6 Remove all dust, debris, oils, soap residue, and loose material using HEPA vacuuming and approved cleaning methods.

3.1.7 Concrete shall be left clean, sound, and dry prior to testing and repairs.

3.1.8 If moisture levels exceed acceptable limits, provide and install a manufacturer-approved moisture mitigation system compatible with the specified rubber flooring.

3.1.9 Moisture mitigation materials shall be installed strictly per manufacturer instructions and allowed to cure as required.

3.1.10 Retesting shall be performed as necessary prior to flooring installation.

3.1.11 Repair all cracks, spalled areas, holes, and surface defects using compatible patching or crack-repair materials.

3.1.12 Feather and smooth repairs to provide a uniform substrate.

3.1.13 Mechanically prepare the concrete to achieve a suitable surface profile for rubber flooring adhesive bonding

(ICRI CSP 1–2).

3.1.14 Over-polishing of the slab is not permitted.

3.1.15 Perform final vacuuming and cleaning immediately prior to flooring installation.

3.1.16 Ensure the substrate is dry, dust-free, and within required temperature and humidity ranges.

3.1.17 Acclimate new rubber flooring materials and adhesives in the installation area for a minimum of 48–72 hours prior to installation. Maintain space at normal operating temperature and humidity during acclimation and installation.

3.1.18 Furnish and install new Regupol Aktiv 3/8 flooring, 48” wide AK10103 Blue Streak with Reguseal sealer.

Approximately 225 sq ft. Contractor to verify.

3.1.19 Furnish and install new 6” black vinyl cove base on the full perimeter. Approximately 75 linear feet. Contractor to verify.

3.1.20 After the rubber floor installation is complete and sealant adequately dry, install complete floor protection for the duration of the project until locker installation. The floor protection shall be per manufactureres recommended best practices, to include two overlapping layers of protection, masonite for high traffic areas and no use of duct tape on the new flooring or walls.

3.2 Lockers

3.2.1 Remove and dispose of 24 existing metal lockers

3.2.2 Furnish and install twenty five (25) new lockers to match the Tomb Field Men’s Lockers installed in 2025. Locker configuration and layout shall conform to the proposed layout attached.

3.2.3 Final locker layout and configuration to be approved by Contracting Officer Representative (COR) prior to manufacture of the lockers.

3.2.4 Relocate existing electrical conduits, HVAC controllers, piping, and/or outlets as required to accommodate the approved locker layout.

6923G226Q000017 PAGE 14 OF 47

3.3 Masonry

3.3.1 Repair and patch all holes, surface imperfections, and missing masonry units in existing block walls to the ceiling, in order to provide a smooth, uniform finish.

3.3.2 Grind all abandoned pipe sleeves and protrusions flush with the finished wall surface, and patch the resulting openings with cementitious fill to achieve a smooth, uniform finish.

3.3.3 Remove all excess spray foam insulation and patch affected areas to match the surrounding wall finish.

3.3.4 Repair all column bases

3.4 Painting

3.4.1 Remove all rust and thoroughly clean exposed steel joists and framing. Clean, sand, and otherwise prepare doors and door framea to receive paint, including removal of dirt, grease, and loose or peeling coatings.

3.4.2 Apply one full coat of Benjamin Moore Fresh Start® Rust-Inhibitive Primer (oil based) No 094, or approved equivalent, to all steel joists, metal doors and metal frames.

3.4.3 Apply one full coat of Banjamin Moore Fresh Start® High-Hiding All-Purpose Primer No. 046-00 to the ceiling, Kindorf framing, electrical conduits, and ductwork.

3.4.4 Apply two full finish coats of Benjamin Moore Super Hide Latex Flat White #282.01, or approved equivalent, to the ceiling, steel joists, kindorf framing, electrical conduits, and ductwork.

3.4.5 Repair, patch, and smooth all holes, cracks, and surface imperfections in the walls. Caulk all perimter panel gaps and open joints. Clean all wall surfaces to ensure proper paint adhesion.

3.4.6 Apply one full coat of Benjamin Moore Fresh Start® Primer No. 046-00, or approved equivalent, to all walls.

3.4.7 Apply two full finish coats of Sherwin-Williams Classic French Gray – Suburban Modern Eggshell, SW 0077, to north and south walls.

3.4.8 Apply two full finish coats of Sherwin-Williams Blue Chip Eggshell, SW 6959, to east and west walls.

3.4.9 Apply two full finish coats of Sherwin-Williams Classic French Gray – Suburban Modern, oil-based paint, SW

0777, to all sides of the entrance door and the three door frames (2 perimeter frames do not have doors).

3.5 HVAC

3.5.1 Secure all piping with Kindorf or approved equivalent support systems, installed in accordance with applicable codes, manufacturer requirements, and standard industry practices.

3.5.2 Install fiberglass insulation on all exposed piping using a professional pipe-wrapping method. Installation shall be performed by a qualified pipe wrapper to achieve a smooth, uniform, and code-compliant finish.

Hand-wrapped, makeshift, or non-professional installations are not acceptable. All work shall comply with applicable codes, manufacturer requirements, and standard industry practices.

3.5.3 Existing insulation may remain in place where it is intact and in good condition. Repair, patch, or re-wrap insulation as necessary to restore full coverage and performance.

3.5.4 Remove and replace four (4) existing metal duct vent covers.

3.6 Electric

3.6.1 Remove and properly dispose of seven (7) existing ceiling-mounted light fixtures

3.6.2 Furnish and install seven (7) new LED ceiling-mounted light fixtures, Lithonia Lighting 4-ft 4188-Lumen Neutral

White LED Wraparound Light, or approved equivalent. Contractor shall provide a detailed lighting layout and fixture placement plan for review and approval by the Contracting Officer Representative (COR) prior to installation.

3.6.3 Remove and replace the existing electrical outlet in the corner near the old sink, with a new tamper-resistant (TR), GFCI-protected, damp-location-rated quad receptacle, installed complete and operable

6923G226Q000017 PAGE 15 OF 47

3.6.4 Furnish and install one (1) additional GFCI-protected, damp-location-rated quad receptacle near the room entrance at a location approved by the COR.

3.6.5 Relocate existing electrical conduits, HVAC control devices, and/or electrical outlets as required to accommodate the finalized and approved locker room layout.

3.6.6 Provide emergency lighting and exit signage throughout the locker room and all required means of egress in full compliance with NFPA 101, IBC, NEC Article 700, and applicable local amendments.

3.6.7 Inspect all existing electrical switches, receptacles, conduit, juncture boxes, and wiring within the area. Repair or replace components as necessary to ensure full compliance with NFPA 70 (National Electrical Code) requirements.

3.7 Miscellaneous

3.7.1 Inspect existing window(s) and repair, clean, or replace as required to restore proper operation, appearance, and performance.

3.7.2 Remove two (2) existing exterior plywood panel patches installed within former door openings and frames.

Remove and replace damaged or deteriorated plywood with AZEK white trim boards, cut to fit existing openings. Secure panels with appropriate exterior-grade fasteners and seal all perimeter joints with weatherproof caulking to provide a continuous, watertight seal and a clean, finished appearance.

3.7.3 Remove abandoned sink drain piping back to the nearest active connection. Cap and secure piping in accordance with plumbing code. Patch wall penetration using cementitious masonry material to restore wall integrity. Prepare, prime, and paint patched area to match adjacent CMU surfaces.

3.7.4 Secure existing water supply piping serving the exterior hose spigot to the CMU wall. Install approved pipe clamps, straps, or hangers at required intervals to prevent movement and strain on fittings. Anchor supports to masonry substrate and seal wall penetrations as required. All work shall comply with applicable plumbing codes and manufacturer requirements.

6923G226Q000017 PAGE 16 OF 47

6923G226Q000017 PAGE 17 OF 47

6923G226Q000017 PAGE 18 OF 47

4. Vistor Bathroom

4.1 Flooring

4.1.1 Remove existing mosaic floor tile assembly and base (tile, setting bed, and any existing waterproofing as encountered) in restroom areas, including within toilet partitions; dispose of debris in accordance with local and Nassau County regulations.

4.1.2 Inspect existing concrete substrate; perform necessary repairs and install new mortar bed with appropriate slope toward floor drains (where applicable) in accordance with ANSI A108 and applicable TCNA methods to ensure proper drainage.

4.1.3 Install waterproofing membrane system complying with ANSI A118.10 (e.g., LATICRETE Hydro Ban, Schluter Kerdi, or approved equal) at wet areas, including penetrations and terminations, in accordance with manufacturer requirements.

4.1.4 Furnish and install slip-resistant porcelain mosaic floor tile (≤2" size) using ANSI A118.4 or A118.15 thin-set mortar, ensuring proper alignment, uniform joints, and coordination with fixtures, partitions, and drains.

4.1.5 Grout with 100% solids epoxy grout (ANSI A118.3) or approved antimicrobial grout; seal penetrations, clean finishes, and provide final inspection to confirm durability, water resistance, and proper drainage.

4.1.6 Remove and replace existing stone or composite door saddle/threshold with new unit of similar size and finish;

submit for COR review and approval prior to installation.

4.1.7 Submit product data and samples for tile, grout, and waterproofing system; obtain COR approval prior to commencement of work.

6923G226Q000017 PAGE 19 OF 47

4.2 Masonry

4.2.1 Repair and patch all holes, surface imperfections, and missing masonry units in existing block walls to the ceiling, in order to provide a smooth, uniform finish.

4.2.2 Grind all abandoned pipe sleeves and protrusions flush with the finished wall surface, and patch the resulting openings with cementitious fill to achieve a smooth, uniform finish.

4.2.3 Remove all excess spray foam insulation and patch affected areas to match the surrounding wall finish.

4.3 Painting

4.3.1 Clean, sand, and otherwise prepare door and door frame to receive paint, including removal of dirt, grease, and loose or peeling coatings.

4.3.2 Apply one full coat of Benjamin Moore Fresh Start® Rust-Inhibitive Primer (oil based) No 094, or approved equivalent, to metal door and metal frame.

4.3.3 Repair, patch, and smooth all holes, cracks, and surface imperfections in the walls. Clean all wall surfaces to ensure proper paint adhesion.

4.3.4 Apply one full coat of Benjamin Moore Fresh Start® Primer No. 046-00, or approved equivalent, to all walls.

4.3.5 Apply two full finish coats of Sherwin-Williams Classic French Gray – Suburban Modern Eggshell, SW 0077, to north and south walls.

4.3.6 Apply two full finish coats of Sherwin-Williams Blue Chip Eggshell, SW 6959, to east and west walls.

4.3.7 Apply two full finish coats of Sherwin-Williams Classic French Gray – Suburban Modern, oil-based paint, SW

0777, to all sides of the metal entrance door.

4.4 HVAC

4.4.1 Secure all piping with Kindorf or approved equivalent support systems, installed in accordance with applicable codes, manufacturer requirements, and standard industry practices.

4.4.2 Install fiberglass insulation on all exposed piping using a professional pipe-wrapping method. Installation shall be performed by a qualified pipe wrapper to achieve a smooth, uniform, and code-compliant finish.

Hand-wrapped, makeshift, or non-professional installations are not acceptable. All work shall comply with applicable codes, manufacturer requirements, and standard industry practices.

4.4.3 Existing insulation may remain in place where it is intact and in good condition. Repair, patch, or re-wrap insulation as necessary to restore full coverage and performance.

4.4.4 Remove and replace existing metal duct vent covers.

4.4.5 Furnish and install, including all required electrical connections, one (1) high-performance horizontal deluxe heating fan coil unit with bottom supply and return. Unit size and model shall be subject to government approval. Provide and install a new thermostat control compatible with the fan coil unit. Provide and install a complete steam trap assembly, including isolation valve and strainer.

4.5 Electric

4.5.1 Remove and properly dispose of existing ceiling-mounted light fixtures

4.5.2 Furnish and install eight (8) new 13” LED Ceiling Flush Mount Disk Lights, wet location rated. Contractor shall provide a detailed lighting layout and fixture placement plan for review and approval by the Contracting Officer Representative (COR) prior to installation.

4.5.3 Remove and replace the existing electrical outlet above sinks and replace with a new tamper resistant (TR), GFCI protected, damp location rated quad receptacle, installed complete and operable.

6923G226Q000017 PAGE 20 OF 47

4.5.4 Provide emergency lighting and exit signage throughout the locker room and all required means of egress in full compliance with NFPA 101, IBC, NEC Article 700, and applicable local amendments.

4.5.5 Inspect all existing electrical switches, receptacles, conduit, juncture boxes, and wiring within the area. Repair or replace components as necessary to ensure full compliance with NFPA 70 (National Electrical Code) requirements.

4.6 Ceiling

4.6.1 Remove existing ceiling system. Furnish and install a new suspended (dropped) ceiling utilizing Trusscore PVC ceiling panels, or approved equivalent, including all required suspension components, trims, and accessories.

Ceiling system shall be moisture‑resistant and suitable for locker room environments. Coordinate installation with existing and new light fixtures, diffusers, and other ceiling‑mounted equipment.

4.6.2 Provide access panels as required for maintenance of above‑ceiling utilities. Panel type, layout, and finish shall be subject to COR approval prior to installation.

4.7 Miscellaneous

4.7.1 Mirrors

4.7.1.1 Remove existing mirrors and associated mounting hardware as required. Furnish and install new heavy‑duty mirrors above sinks suitable for school athletic locker room use. Mirrors shall be vandal‑resistant, moisture‑resistant, and designed for high‑traffic institutional environments.

4.7.1.2 Provide mirrors constructed of stainless steel reflective material or tempered glass with full perimeter stainless steel frames, subject to COR approval. Mirrors shall be securely mechanically anchored to masonry walls using concealed or tamper‑resistant fasteners. Adhesive‑only mounting is not acceptable.

4.7.1.3 Mirror size, type, finish, and mounting height shall coordinate with sinks, shelves, and other wall‑mounted accessories. Submit product data and shop drawings to the COR for review and approval prior to installation.

4.7.1.4 Plastic, acrylic, frameless glass, or residential‑grade mirrors are not acceptable.

4.7.2 Remove existing hand soap trough. Furnish and install two (2) stainless steel wall‑mounted shelves, with one shelf installed above each sink. Shelves shall be securely anchored to the masonry wall using appropriate heavy‑duty anchors to provide rigid, durable support suitable for institutional restroom use.

4.7.3 Inspect and repair existing toilets exhibiting leakage during flushing. Replace worn or defective internal components, seals, or connections as required to eliminate leaks and restore proper operation.

4.7.4 Inspect and repair sink with non‑functional hot water supply. Restore hot water service by repairing or replacing defective faucets, valves, supply lines, or controls as required. Verify proper operation upon completion.

4.7.5 Remove and dispose of existing bathroom partitions.

4.7.6 Furnish and install heavy‑duty black toilet partitions with doors suitable for athletic locker room use. Partitions shall be HDPE construction and floor‑anchored into the structural concrete slab using heavy‑duty stainless steel anchors. No attachment to suspended ceiling systems is permitted. Provide reinforced pilasters and wall‑mounted brackets anchored to masonry walls to prevent racking or movement and ensure rigid, stable performance under heavy use. Provide a continuous anti‑grip headrail connecting partitions for added rigidity;

headrail shall not attach to ceiling framing or suspended ceiling components.

6923G226Q000017 PAGE 21 OF 47

6923G226Q000017 PAGE 22 OF 47

6923G226Q000017 PAGE 23 OF 47

5. Women’s Shower

5.1 Flooring

5.1.1 Remove existing mosaic floor tile assembly (tile, mortar bed, and waterproofing) and dispose of debris in accordance with local regulations.

5.1.2 Inspect concrete substrate; perform required repairs and install new sloped mortar bed to drains in compliance with TCNA methods (B415/B421) and ANSI A108 standards to ensure positive drainage.

5.1.3 Install ANSI A118.10 compliant waterproofing membrane system (e.g., LATICRETE Hydro Ban, Schluter Kerdi, or equal) with proper drain integration and flood test prior to tile installation.

5.1.4 Furnish and install slip-resistant porcelain mosaic tile (≤2" size) using ANSI A118.4/A118.15 thin-set mortar;

maintain required slope, alignment, and integration with trench and point drains.

5.1.5 Grout with 100% solids epoxy grout (ANSI A118.3), seal penetrations, clean and finish installation, and provide final inspection to confirm watertight performance and proper drainage.

5.1.6 Remove and replace existing stone door saddle with new saddle of similar material, size, and finish, subject to

COR review and approval prior to installation.

5.1.7 COR to approve proposed tile and waterproofing membrane assemebly prior to start of work.

5.2 Tile Walls

5.2.1 Remove existing ceramic wall tile and base, setting materials, and backer substrate as required; dispose of all debris in accordance with local regulations.

5.2.2 Inspect wall substrate; repair or replace damaged areas and in accordance with ANSI A108 and manufacturer specifications.

5.2.3 Install waterproofing membrane system meeting ANSI A118.10 (e.g., LATICRETE Hydro Ban or equal) at all wet wall areas, including penetrations and transitions.

5.2.4 Furnish and install new ceramic wall tile using ANSI A118.4/A118.15 thin-set mortar; align with existing layout and coordinate with all plumbing fixtures and penetrations.

5.2.5 Grout with antimicrobial or epoxy grout (ANSI A118.3), seal joints as required, clean surfaces, and perform final inspection to ensure watertight, durable installation.

5.2.6 COR to approve proposed tile and waterproofing membrane assemebly prior to start of work.

5.3 Masonry

5.3.1 Repair and patch all holes, surface imperfections, and missing masonry units in existing block walls to the ceiling, in order to provide a smooth, uniform finish.

5.3.2 Grind all abandoned pipe sleeves and protrusions flush with the finished wall surface, and patch the resulting openings with cementitious fill to achieve a smooth, uniform finish.

5.3.3 Remove all excess spray foam insulation and patch affected areas to match the surrounding wall finish.

5.4 HVAC

5.4.1 Secure all piping with Kindorf or approved equivalent support systems, installed in accordance with applicable codes, manufacturer requirements, and standard industry practices.

5.4.2 Install fiberglass insulation on all exposed piping using a professional pipe wrapping method. Installation shall be performed by a qualified pipe wrapper to achieve a smooth, uniform, and code compliant finish. Hand

6923G226Q000017 PAGE 24 OF 47

wrapped, makeshift, or non professional installations are not acceptable. All work shall comply with applicable codes, manufacturer requirements, and standard industry practices.

5.4.3 Existing insulation may remain in place where it is intact and in good condition. Repair, patch, or re wrap insulation as necessary to restore full coverage and performance.

5.4.4 Remove and replace existing metal duct vent covers. Adjust and install vents to align flush with the new ceiling height and layout.

5.5 Electric

5.5.1 Remove and properly dispose of existing ceiling-mounted light fixtures

5.5.2 Furnish and install thirteen (13) new 13” LED Ceiling Flush Mount Disk Lights, wet location rated. Contractor shall provide a detailed lighting layout and fixture placement plan for review and approval by the Contracting Officer Representative (COR) prior to installation.

5.5.3 Provide and install a second shower light control switch located on the bathroom side of the shower area.

Switch shall be wet-location rated, code-compliant, and suitable for use in humid and splash-prone environments.

5.5.4 Inspect all existing electrical switches, receptacles, conduit, juncture boxes, and wiring within the area. Repair or replace components as necessary to ensure full compliance with NFPA 70 (National Electrical Code) requirements.

5.6 Ceiling

5.6.1 Remove existing ceiling system.

5.6.2 Furnish and install a new suspended (dropped) ceiling utilizing Trusscore PVC ceiling panels, or approved equivalent, including all required suspension components, trims, and accessories. Ceiling system shall be moisture‑resistant and suitable for locker room environments. Coordinate installation with existing and new light fixtures, diffusers, and other ceiling‑mounted equipment.

5.6.3 Provide access panels as required for maintenance of above‑ceiling utilities. Panel type, layout, and finish shall be subject to COR approval prior to installation.

5.7 Plumbing

5.7.1 Completely remove exisitng shower fixtures. Furnish and install seven (7) new shower fixtures and associated plumbing. See attached photo of Men’s Locker Room - Sample Shower Set Up.

5.7.2 Furnish and install bath accessories including Nameeks Model NFA024 General Hotel Bath and Shower

Accessories, or approved equal, suitable for locker room use per shower. Accessories shall be corrosion‑resistant and designed for wet, high‑use environments. Plastic, residential‑grade, or adhesive‑mounted shower accessories are not acceptable.

5.7.3 Remove and replace five (5) existing floor drains with heavy‑duty drains including hair catching basins.

Thoroughly clean each drain and remove all residual debris from the drain pocket to restore proper function.

5.7.4 Provide and install one (1) heavy‑duty hook per shower stall for hanging towels or personal items. Hooks shall be stainless steel or corrosion‑resistant metal, vandal‑resistant, and securely mechanically anchored to masonry walls or approved blocking.

5.7.5 All accessories shall be installed plumb, level, and at heights coordinated with shower controls and accessibility requirements where applicable. Adhesive‑only mounting is not permitted.

5.8 Miscellaneous

6923G226Q000017 PAGE 25 OF 47

5.8.1 Furnish and install seven (7) heavy‑duty black shower stall partitions with doors suitable for athletic locker room use. Partitions shall be HDPE construction, resistant to moisture, impact, and corrosion, and designed for wet, high‑traffic environments.

5.8.2 Provide partitions that are floor‑anchored into the structural concrete slab using heavy‑duty stainless steel anchors. No attachment to suspended ceiling systems is permitted.

5.8.3 Provide reinforced pilasters and wall‑mounted support brackets securely anchored to masonry walls to prevent racking, deflection, or movement and to ensure rigid, stable performance under heavy use.

5.8.4 Provide a continuous anti‑grip headrail connecting shower partitions for added rigidity. Headrail shall be mechanically fastened to partition components on both sides and shall not attach to ceiling framing or suspended ceiling components.

5.8.5 All components, fasteners, and fittings shall be non‑corrosive and suitable for continuous exposure to moisture.

6923G226Q000017 PAGE 26 OF 47

Men’s Locker Room - Sample Shower Set Up

6923G226Q000017 PAGE 27 OF 47

PROJECT ACTIVITIES

1. Pre-Submission Site Visit

2. Contractor Proposal Submission

3. Award

4. Post Award Kick Off Meeting

5. Submission of Equipment Cut Sheets, Materials Safety Data Sheets, and schedule.

6. Approval of Materials, Equipment, and schedule

7. Notice to Proceed

8. Work commencement

9. Weekly Progress Meeting & Report

10. Final Inspection

11. Acceptance

12. Operations and Maintenance Manuals submitted.

13. Warranty Verification

14. Final Payment

SUBMITTALS

1. Project Schedule

2. Samples of all paint colors

3. Sample of vinyl six-inch wall base

4. Sample PVC ceiling panels

5. Sample of rubber floor tiles

6. Sample Vent covers.

7. Sample tile threshold.

8. Sample floor tile

9. Sample wall tile

10. Shower waterproofing assembly

11. Cut Sheet for Shower Room drain cover.

12. Cut Sheet for mirror and shelves.

13. Cut Sheet for proposed Light Fixtures

14. Cut Sheet for Bathroom Toilet Dividers

15. Cut Sheet for Shower Room Dividers

16. MSDS and specifications for pipe insulation

17. MSDS for tile floor cleaner and polish

GOVERNMENT FURNISHED PROPERTY, MATERIAL, EQUIPMENT, OR INFORMATION.

N/A

6923G226Q000017 PAGE 28 OF 47

CONSIDERATIONS

Maintain communication with the COR (and immediately inform the COR of any unforeseen issues or problems that arise).

Inform COR of any anticipated disruption in services for construction at least three (3) days in advance.

PLACE OF PERFORMANCE

The contractor will perform the task located at Tomb Field Women’s Locker Room on the campus of USMMA, 300 Steamboat Road, Kings Point, N.Y. 11024

PERIOD OF PERFORMANCE

The Period of Performance (POP) is stated in the solicitation/contract SF-1449 Form. Delivery and installation of lockers may be granted additional time, subject to manufacturer lead times and approval by the Contracting Officer. Work shall be performed during normal business hours, 0700 to 1630, Monday through Friday, unless otherwise authorized in writing by the Contracting Officer.

ADDITIONAL NOTES

1. A full work plan must be prepared in advance and submitted to the Contracting Officer Representative (COR) for approval. The plan must be approved at least one (1) week prior to commencement of work.

2. The Contractor shall be responsible for quality control of all work and shall conduct regular…