This document outlines a federal contract opportunity for construction services at Isle Royale National Park. The US Department of Transportation is seeking a contractor to repair and expand the Rock Harbor dock to accommodate vessel traffic and address congestion issues. Required work includes installation of siltation barriers, removal and replacement of dock components, installation of new decking and fender systems, and repair or replacement of structural timbers. The project will be conducted in one phase with minimal disruption during peak seasons. The contract is set aside for small businesses with a value between $1-5 million. Offerors must register in SAM to access the solicitation, which will provide additional details on pricing, evaluation criteria, and a 120 day period of performance starting in January 2021.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Attachment 7

CLINDescriptionUnit of MeasureQuantityUnit PriceTotal Price
00100Preconstruction Documentation: HASP: The Contractor shall develop a Health and Safety Plan (HASP), including COVID precautions (PSC =Y1PZ) Period of Performance = Time of Award through 31 July 2021.EA1
00200The Contractor shall prepare the existing Rock Harbor dock crib sections and other components of the existing dock (PSC =Y1PZ) Period of Performance = Time of Award through 31 July 2021.EA1
00300Install the new dock upgrades in accordance with the provided Technical Design Package (Reference 1) and permits (PSC =Y1PZ) Period of Performance = Time of Award through 31 July 2021.EA1
Total BASE CLINS Amount

OPTION CLIN Description Totals

00400Emergency Sewage Pump-out Station (PSC =Y1PZ) Period of Performance = 30 Days after Award through 31 July 2021.EA1
00500Install a new wheelchair accessible ramp between the Rock Harbor dock and the private boat fueling dock (PSC =Y1PZ) Period of Performance = 30 Days after Award through 31 July 2021.EA1
00600Contractor Provided Housing (PSC =X1FA?) Period of Performance = 30 Days after Award through 31 July 2021.EA1
00700Replace/Repair any structural timbers, loose or missing crib structure & ice plate hardware showing signs of damage/degradation (PSC =Y1PZ) Period of Performance = 30 Days after Award through 31 July 2021.EA1
Total OPTION CLINs Amount

Total Contract Price (Inclusive of Base and all Options): ERROR:#VALUE!