Appendix_B_6913G619Q300177.pdf
PDF 423 KB Posted
- Attached to
- Backup Global Positioning System (GPS) Technical Consulting Services - Technology Demonstration Federal contract opportunity
- Solicitation number
- 6913G619Q300177
About this file
Appendix B
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| Amendment_000002.pdf | ||
| 6913G619Q300177_Amendment_00001_9.20.19.pdf | ||
| Appendix_C_Amended_09.20.19.pdf | ||
| Amendment_00001.pdf | ||
| 6913G619Q300177_v2_dated_9.16.19.pdf | ||
| 6913G619Q300177.pdf | ||
| Appendix_A_Pricing_Sheet_6913G619Q300177.pdf | ||
| Appendix_C_6913G619Q300177.pdf |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Appendix B - 6913G619Q300177
Table 1: Statement of Work
Pre-Demonstration Technical Support
Sub-Task Objective
Site Visit Contractor will conduct a site visit at the assigned Demonstration Site to prepare for technology setup and install activities.
UE Integration Verification
Contractor will provide User Equipment (UE) and associated support to establish compatibility of the UE with the Government furnished data collection system.
UE Installation and Configuration
Contractor will provide the Volpe Center access to the Contractor’s UE, and will provide installation and configuration support with the data collection system.
Technology Setup, Installation, and Configuration
Setup, install, and configure any necessary equipment/systems/items (transmitters, antennas, receivers, etc.) that are necessary for a successful demonstration of the Contractor’s system at a DOT furnished site.
Demonstration Technical Support
Sub-Task Objective
Dry Run Provide support at Demonstration Site for a dry run of the demonstration to ensure the Solution is properly configured and providing useable data.
Demonstration Support
Provide support at Demonstration Site during the demonstration to ensure the Solution is properly configured and providing useable data. Removal of UE and Solution equipment will be completed after the Demonstration is concluded.
Post-Demonstration Technical Support
Sub-Task Objective
Documentation of Demonstration
Contractor will review and provide feedback on the portion of the Government’s final report that applies to their Solution. The Government will consider all feedback and may incorporate as necessary.
Closeout Final closeout teleconference to discuss lessons learned and address any outstanding items.
Figure 1: Demonstration Site at JBCC
Figure 2: Demonstration Site at NASA LaRC
Figure 3: Example of a dynamic position scenario at JBCC
Table 2: Execution timeframe for the demonstration tasks
Pre-Demonstration
Sub-Task Timeframe On-Site Site Visit November-December 2019 1 Day UE Compatibility Check Out November-December 2019 2 Days UE Installation December 2019-February 2020 2 Days Solution Setup, Installation, and Configuration
December 2019-February 2020 1 Week
Demonstration
Sub-Task Timeframe On-Site Dry Run February 2020 1 Week Demonstration March 2020 2 Weeks Post-Demonstration
Sub-Task Timeframe On-Site Documentation of Demonstration June 2020 N/A Closeout August 2020 N/A
Table 3: Deliverables
Deliverable Description Place of Performance
Due Date
CLIN 00100 – Pre Demonstration Technical Support
Kick-Off Call This kick-off meeting will review the initiative and contract administration in further detail.
Teleconference Two weeks after award
UE Integration Verification
Provide User Equipment (UE) and engineering support to establish compatibility of the UE with the Government furnished data collection system
Support / Meeting location is To Be Determined
Four weeks after award
UE Hardware Provide UE to the Government for use in the demonstration
To Be Determined
Six weeks after award
Demonstration Site Plan
Provide the Government with specific requirements (that can be reasonably met) necessary to setup the Solution
Delivered via e-mail
Four weeks after award
Demonstration Site Installation
Install necessary equipment and work with the Government to obtain any temporary licenses necessary for the proper operation of the UE and Solution during the demonstration
Demonstration Site
Twelve weeks after award
CLIN 00200 – Demonstration Technical Support
Dry Run Provide assistance to the Government to ensure successful dry run of the demonstration of the Solution
Demonstration Site
Sixteen weeks after award
Demonstration Support
Provide assistance to the Government to ensure a successful operation of the Solution and the UE during the demonstration
Demonstration Site
Twenty weeks after award
CLIN 00300 – Post Demonstration Technical Support
Documentation of Demonstration
Provide feedback on the portion of the Government’s final report that applies to their Solution. The Government will consider all feedback and may incorporate as necessary.
Delivered via e-mail
Thirty two weeks after award
Demonstration Closeout
Closeout teleconference. Teleconference Forty two weeks after award
File details come from the government source that posted it.