This document is a Questions and Answers log for federal contract opportunity Project No. WA ERFO NPS OLYM 2022-1(3), related to Olympic National Park Emergency Restoration and Forest Operations repairs on Road 107.
Question 1 addresses a technical concern from a potential bidder regarding Schedule B requirements for engineered log jam with textured dolosse. The bidder reported that adding a bark finish to the dolo formwork causes reduced product quality, reduced weight, formwork damage, and difficulty removing textured pieces from the mold. The bidder requested changing line-item B0580 from "Engineered Log Jam with Dolosse-Textured" to "Engineered Log Jam with Dolosse." The government response, dated 11/19/26, directed bidders to submit bids per the solicitation documents without accommodating the requested modification. Question 2, answered on 11/24/26, clarifies that the deadline for submitting questions is the close of business on Tuesday, November 24, 2026, as Friday, November 27, 2026, is a non-business day. The bid due date is Thursday, December 3, 2026, and the question deadline of five business days before that due date was affected by the Thanksgiving holiday on November 26, 2026.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| QandA_11-23-2026.pdf | ||
| QandA_11-26-2026.pdf | ||
| IFB_69056727B000002.pdf | ||
| wa-ep-olym2022-1-3_plans_IFB.pdf | ||
| Physical Data_WA ERFO NPS OLYM 2022-1(3).zip | ZIP file |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Project No. WA ERFO NPS OLYM 2022-1(3)
Project WA ERFO NPS OLYM 2022-1(3)
# General Technical Question Answer Date
1 X
Our company recently received quote requests for project OLYMPIC NPS ERFO REPAIRS 2022
Road 107 MP 0.3 TO 0.5 & MP 0.8 for 8-ton dolos. The request was for Schedule A (140 plain concrete grey dolos) and Schedule B (140 grey dolos with bark finish). It is simple enough to address Schedule A request; however, it is difficult to fulfill Schedule B request. Adding a bark finish to the dolo formwork causes multiple issues including reduced product quality, reduced overall weight, damage to formwork and an and inability to remove the textured piece from the formwork. Is it possible to change line-item B0580 from “ENGINEERED
LOG JAM WITH DOLOSSE-TEXTURED” to
“ENGINEERED LOG JAM WITH DOLOSSE”? I
would be happy to answer any questions the design team may have regarding the formwork or manufacturing of the dolo product.
Please bid per the solicitation documents. 11/19/26
Check General or Technical
2 X
Page A-3 of the IFB states that questions will be accepted until close of business five (5) business days before the due date. With bids due
Thursday, December 3, 2026, and the
Thanksgiving holiday on November 26, please confirm if the last day to submit questions is
Wednesday, November 25, 2026.
The deadline to submit questions is the close of business today, Tuesday, November 24, 2026, as Friday, November
27, 2026, is a non-business day.
11/24/26