This is a Vendor Questions and Answers document for Solicitation No. 69056726Q000036 concerning Post-Construction Environmental Compliance Monitoring Services in support of WA NP LARO 208(1) Hawk Creek Road Stabilization and WA FLAP LINCOL 57860(1) Hawk Creek Road Improvements. All questions were submitted on 25-Aug-2026.

The document addresses six technical questions regarding contract scope and pricing uncertainty. Question 1 concerns Task 1 maintenance requirements, which present significant pricing challenges due to unpredictable weather and site conditions affecting effort levels. The contractor asked whether additional work would be addressed under Task 5, and the government responded that assumptions for Task 1 maintenance are the same as Task 5 and will be addressed in an upcoming amendment. Question 2 requests confirmation that contractors are not required to include costs for major repairs, replacement or reconstruction of controls, significant sediment removal, extensive erosion repair, or specialized equipment in base bids; the government cited Task 5 language excluding such work. Question 3 addresses Task 3 turbidity monitoring requirements exceeding 25 NTU, requesting either a separate bid item with estimated quantities or revision allowing contract modifications for corrective actions; the government stated same assumptions as Tasks 1 and 5 will be addressed in an upcoming amendment. Question 4 asks for estimated sediment removal quantities under Task 4; the government stated this is not possible to provide and noted hand tools only should be used. Question 5 requests confirmation that corrective work exceeding Task 5 limitations requires separate written authorization and compensation through contract modification; the government clarified the SOW requires notification to the TPOC requesting determination regarding modification but does not commit to modifying scope. Question 6 asks whether Task 8's "complete ESCP of record" includes documentation from both original construction and post-construction stabilization phases or only post-construction work performed under this contract; the government responded that records from the post-construction phase and documentation of inspections and maintenance performed under this contract should be provided.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

VENDOR QUESTIONS AND ANSWERS

Solicitation No.: 69056726Q000036 Project Name:

# General Technical Question Answer Date

1 X

The maintenance required under Task 1 presents a significant pricing challenge because the level of effort will depend on unpredictable weather and site conditions. If additional work is required, will that work be addressed under Task 5?

Because the quantity and severity of potential deficiencies cannot reasonably be determined before award, this requirement could involve substantial and unpredictable work, including replacing failed measures, repairing erosion damage, removing accumulated sediment, installing additional controls, or correcting pre-existing noncompliant conditions. These costs cannot reliably be included in a competitively bid lump-sum price.

Would WFLHD consider revising this work to an “Each” bid item so the Contractor can bill for each event as it occurs? The anticipated number and extent of these events cannot reasonably be predicted.

The assumptions for maintenance under Task 1 are the same as those for Task 5. Will be addressed in an upcoming amendment.

25-Aug-2026

2 X

Please confirm that the Contractor is not required to include costs in its base bid for major repairs;

replacement or reconstruction of controls; significant sediment removal; extensive erosion repair; or work requiring machinery or specialized equipment.

Task 5 specifically states "This statement of work does not cover more extensive repairs or use of specialized equipment." See also the response to Question #1

25-Aug-2026

Post-Construction Environmental Compliance Monitoring Services in support of WA NP LARO 208(1) Hawk Creek Road Stabilization and WA FLAP LINCOL 57860(1) Hawk Creek Road Improvements

VENDOR QUESTIONS AND ANSWERS

3 X

Task 3 states “If turbidity exceeds 25 NTU or higher, notify TPOC immediately. Take immediate action to address cause of exceedance. Continue to monitor until the stormwater discharge is measured at less than 25

NTU.”

This requirement cannot reasonably be priced as a lump-sum item because the number, duration, and severity of potential turbidity exceedance events are unknown.

Would WFLHD consider establishing a separate bid item with an estimated quantity for each turbidity-monitoring or corrective-action event

Alternatively, could the requirement be revised to state:

“Notify the TPOC, and a contract modification will be issued if corrective action is required”?

Use the same assumptions as the maintenance and corrective actions under Tasks 1 and 5. Will be addressed in an upcoming amendment.

25-Aug-2026

4 X

Task 4 – Sediment Removal: Please provide an estimated quantity of sediment or soil to be removed under Task 4 so the Contractor can determine and price the anticipated level of effort. As currently written, the quantity of material, removal effort, and disposal requirements are undefined, making the task difficult to price competitively.

This is not possible to provide. Based on the assumption of maintenance and corrective action being completed during the day of the site inspection with hand tools only, then this uncertainty can be addressed.

Disposal of sediment should be outside of riparian areas and surface waters, but can be redistributed in the project area.

25-Aug-2026

5 X

Task 5 – Work Exceeding the Stated Limitation: Please confirm that corrective work exceeding the Task 5 limitation will require separate written authorization and will be compensated through a contract modification/change order. Clearly defining the level of effort included in the base task, with additional work handled by modification, will allow bidders to price the base requirement consistently.

The SOW specifically states If damage or failure is found which is so extensive that it cannot be repaired as stated above, immediately notify the TPOC to request a determination regarding a modification to increase the scope.. It does not state that we will modify.

25-Aug-2026

6 X

Task 8 – Complete ESCP: Does the “complete ESCP of record” required under Task 8 include documentation from both the original construction phase and the post-construction stabilization phase, or only the post-construction stabilization work performed under this contract?

This task is to provide any records that are done as part of the post-construction phase and documenting inspections and maintenance done as part of this contract.

25-Aug-2026