PROJECT DESCRIPTION_IN NP INDU PMS(1).pdf
PDF 145 KB Posted
- Solicitation number
- 69056725R000016
About this file
This document is a solicitation for a pavement preservation project located in Indiana Dunes, covering 5.96 miles across Lake, Porter, and Laporte Counties. The project, identified by solicitation number 69056725R000016, involves crack sealing, patching, chip seal and micro surface treatments, and pavement marking with a tentative fixed completion date in Summer 2026 and an estimated price range of $5 million to $10 million.
The solicitation includes a detailed description of work across multiple divisions, with base requirements and three optional scopes (Option X, Option Y, Option Z). Key work elements include 550-850 cubic yards of waste management, full depth reclamation, asphalt concrete work, chip sealing, micro surfacing, pavement crack sealing, and pavement patching. Additional scope covers temporary traffic control, construction signs, cones, flagging, and permanent pavement markings. The project requires contractor quality control, sampling, testing, and construction schedule management, with varying quantities specified for each project option.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| 01_IN NP INDU PMS(1)_Plans_Pre-Final_PRESOLICITATION.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
IN NP INDU PMS(1),
Pavement Preservation Indiana Dunes
69056725R000016
This work consists of crack sealing, patching, application of chip seal and micro surface treatments and pavement marking.
Project length: 5.96 Miles
Tentative Fixed Completion Date: Summer 2026
Estimated Price Range: $5 million to $10 million
Location: 4 miles North of Chesterton, Indiana. Lake, Porter, and Laporte Counties.
DESCRIPTION OF WORK in US CUSTOMARY UNITS
FP-24
B A
S E
O P
T
IO
N X
T
IO
Y
T
IO
Z
DIVISION 150 – Project Requirements
152 Construction Survey & Staking (yes/no) No No No No
153 Contractor Quality Control and Assurance (yes/no) Yes Yes Yes Yes
154 Contractor Sampling & Testing (yes/no) Yes Yes Yes Yes
155 Schedules for Construction Contracts (construction schedules) (yes/no) Yes Yes Yes Yes
DIVISION 200 – Earthwork
204 Waste 550 CUYD 850 CUYD
DIVISION 300 – Aggregate and Base Courses
302 Roadway Aggregate 16 TON
304 Full Depth Reclamation 1,900 SQYD
B A
S E
T
IO
X
T
IO
Y
T
IO
Z
DIVISION 400 – Asphalt Pavements & Surface Treatments
403 Asphalt Concrete 410 TON
407 Chip Seal 40 TON
409 Micro Surfacing 179,000
SQYD
26,000
SQYD 11,600 SQYD
414 Asphalt Pavement Crack Sealing & Filling 11 MILE 0.65 MILE 1.05 MILE
418 Asphalt Concrete Pavement Patching 1970 SQYD 280 SQYD 70 SQYD
DIVISION 600 – Incidental Construction
609 Curb & Gutter (Wheel stop) 18 EACH
622 Rental Equipment (yes/no) Yes No No No
623 General Labor (yes/no) Yes No No No
634 Permanent Pavement Markings (traffic pavement markings)
164,000
LNFT
17,000
LNFT 650 LNFT 40 LNFT
635 Temporary Traffic Control – Flagger 2,000 HOUR 200 HOUR 90 HOUR 320 HOUR
635 Temporary Traffic Control – Pavement Markings
48,000
LNFT
635 Temporary Traffic Control – TCS 75 DAY 6 DAY 6 DAY 8 DAY
635 Temporary Traffic Control – Construction Sign 210 SQFT
635 Temporary Traffic Control – Cone 220 EACH