About this file
This document is a Questions and Answers (Q&A) file for a federal highway project, specifically MT FLAP DOT 236 (20), located at Winifred North. The document contains 10 technical questions from potential contractors, with consistent responses from the government directing bidders to refer to solicitation documents. Key questions addressed include rail section removal and reset specifications, material sourcing, project personnel requirements, period of performance, on-site work logistics, and vendor list access. Most government responses indicate they will not provide additional information and instruct bidders to submit bids according to the solicitation documents. For the bidders list, the government directs potential subcontractors to SAM.gov and provides contact information for the Federal Service Desk if additional assistance is needed.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| BidTabs_MT FLAP DOT 236(2) Winifred North.pdf | ||
| BidSum_MT FLAP DOT 236(2)_Winifred North.pdf | ||
| QA_10_15_2025.pdf | ||
| QA_10_14_2025.pdf | ||
| mta-dot236-2_WinifredNorth_Grizzly_Bear_Sightings_Log.docx | DOCX document | |
| mta-dot236-2_WinifredNorth_plans.pdf | ||
| mta-dot236-2_WinifredNorth_Final Geotechnical Report-Signed.pdf | ||
| mta-dot236-2_WinifredNorth_Hydraulics_Memo_Final.pdf | ||
| mta-dot236-2_WinifredNorth_control-points.xlsx | XLSX spreadsheet | |
| IFB_69056725B000010_MT FLAP DOT 236(2).pdf |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
MT FLAP DOT 236 (20),
Winifred North
# General Technical Question Answer Date
1 X
Line Item WE2320 Remove and Reset, Rail
Section, 240 Each
What is the length of the rail sections to be removed and reset.
Please submit bids according to the solicitation documents. Reference is made to sheets C.6 and D.2 for the estimated length included in the guardrail remove and reset item.
10/8/25
2 X Are there any existing pits nearby we can use for the stone?
The Government does not intend to provide additional information on this. See the Notice to Bidders, Section IV -
Specifications and Permits and SCR Section
105 - Control of Materials. Please submit bids according to the solicitation documents.
10/9/25
3 X
Please further define the requirements for the pricing line as called out for "unclassified borrow".
Comply with the requirements of SCR
Section 204 - Excavation and Embankment and SCR Section 704 – Soil. please submit bids according to the solicitation documents.
10/9/25
4 X Do the Superintendent, SSHO and QC Manager need to be 3 separate individuals?
The Government does not intend to provide additional information on this.
Comply with the requirements of SCR
Division 100 – General Requirements and the Standard Specifications for
Construction of Roads and Bridges on
Federal Highway Projects, FP-14, U.S.
Customary Units. Please submit bids according to the solicitation documents.
10/9/25
5 X
Can the period of performance be extended after award once the material/equipment lead times are confirmed due to current market conditions for the equipment for this project?
The Government does not intend to provide additional information on this. See
Block 11 of the Notice to Bidders
(Continuation SF 1442) for the required period of performance. Please submit bids according to the solicitation documents.
10/9/25
6 X
Is there a bulk water fill i.e. a hydrant or water source we can pump from for grading operations in close proximity?
The Government does not intend to provide additional information on this. See
Notice to Bidders, Section IV -
Specifications and Permits. Please submit bids according to the solicitation documents.
10/9/25
7 X Does this project require phasing?
The Government does not intend to provide additional information on this.
Please submit bids according to the solicitation documents.
10/9/25
Check General or Technical
8 X Is this project tax exempt?
The Government does not intend to provide additional information on this.
Please submit bids according to the solicitation documents.
10/9/25
9 X When do you anticipate on site work starting?
The Government does not intend to provide additional information on this. See
Block 11 of the Notice to Bidders
(Continuation SF 1442) for the expected notice to proceed. Please submit bids according to the solicitation documents.
10/9/25
10 X
I am a sub contractor trying to find prime bidders, can you help me find the bidders list for this project?
You may obtain the registered vendors list
(aka planholders list) from SAM.gov after linking your entity to your SAM.gov registration. If you are signed into
SAM.gov with your registered entity and you cannot see the Interested Vendors List, you will need to be assigned the Contract
Opportunities Administrator role for your entity in SAM.gov.
If you need additional assistance, you can reach the Federal Service Desk at 866-606-