This document is an Amendment to a Solicitation for a federal construction project ID FLAP IDAHO NF17(1), Mt. Idaho Grade Road Rehabilitation. The amendment revises the pre-bid information date, bid opening date, and contract clauses related to the commencement, prosecution, and completion of work.

The solicitation is being offered as full and open competition with a Price Evaluation Factor for HUBZone Small businesses. It is issued by the Department of Transportation Federal Highway Administration. The project involves rehabilitation of the Mt. Idaho Grade Road, with two bid schedules (A and B). Offers must be submitted by October 8, 2024 and the work is required to be completed by October 22, 2025 for Schedule A and November 14, 2025 for Schedule B. Liquidated damages will be assessed for late completion.

View the file

Other files

Show all 21

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT

1. CONTRACT ID CODE

N/A

PAGE

2. AMENDMENT/MODIFICATION NO. 3. EFFECTIVE DATE 4. REQUISITION/PURCHASE NO. 5. PROJECT NO. (If applicable)

A001 08/22/2024 N/A ID FLAP IDAHO NF17(1)

Mt. Idaho Grade Road Rehabilitation

6. ISSUED BY CODE N/A 7. ADMINISTERED BY (If other than Item 6) CODE N/A

Department of Transportation Federal Highway Administration 610 East Fifth Street Vancouver WA 98661-3801

8. NAME AND ADDRESS OF CONTRACTOR (No., street, county, State and Zip Code) 9A. AMENDMENT OF SOLICITATION NO.

X

69056724B000014

9B. DATED (SEE ITEM 11)

08/21/2024

10A. MODIFICATION OF CONTRACT/ORDER NO.

N/A

10B. DATED (SEE ITEM 13)

CODE: N/A FACILITY CODE: N/A

N/A

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

| X | The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers

(__ ) is extended, ( x ) is not extended.

Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods:

(a) By completing Items 8 and 15, and returning 1 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted; or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

12. ACCOUNTING AND APPROPRIATION DATA (If required)

N/A

13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS,

IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.

A THIS CHANGE ORDER IS ISSUED PURSUANT TO (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT ORDER NO. IN

ITEM 10A.

N/A

B THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (Such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).

C THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D OTHER (Specify type of modification and authority)

N/A

E. IMPORTANT: Contractor n/a is not, n/a is required to sign this document and return n/a copies to the issuing office.

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

ID FLAP IDAHO NF17(1), Mt. Idaho Grade Road Rehabilitation

See page 2

Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

15a. NAME AND TITLE OF SIGNER (Type or print) 15a. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)

N/A

15B. CONTRACTOR/OFFEROR 15C. DATE SIGNED 16B. UNITED STATES OF AMERICA 16C. DATE SIGNED

BY_________________________________________ BY N/A___________________________ N/A (Signature of person authorized to sign) (Signature of Contracting Officer)

NSN 7540-01-152-8070

PREVIOUS EDITION NOT USABLE

30-105 STANDARD FORM 30 (REV. 10-83)

Prescribed by GSA

FAR (48 CFR) 53.243

Amendment No. A001, dated 08/22/2024 Project No: ID FLAP IDAHO NF17(1)

Solicitation No. 69056724B000014 Project Name: Mt. Idaho Grade Road Rehabilitation

REVISIONS ARE AS FOLLOWS:

NOTICE TO BIDDERS

Page A-1, II. Pre-bid Information. Revises general and technical questions acceptance date from 09/17/2024 to 10/1/2024.

SF 1442, SOLICITATION, OFFER, AND AWARD

Page A-3, Block 13A. Revises bid opening date from 09/24/2024 to 10/08/2024

CONTRACT CLAUSES

Page C-27. Revises FAR Clauses Commencement, Prosecution, and Completion of

Work (Apr 1984) Alternate I (Apr 1984).

ENCLOSURES

Pages:

A-1

A-3

C-27

New bid opening date: 10/08/2024

A-1

Notice to Bidders

Project: ID FLAP IDAHO NF17(1), Mt. Idaho Grade Road Rehabilitation

NOTICE TO BIDDERS

07/01/24–FP14

THIS PROJECT IS BEING SOLICITED AND AWARDED UNDER FP-14.

The FP-14 is FLH’s Standard Specifications for Construction of Roads and Bridges on Federal

Highway Projects. To view the FP-14 electronically go to:

https://highways.dot.gov/federal-lands/specs.

The FP-14 is a dual unit document with U.S. Customary units being the primary unit shown.

Metric equivalents are shown in parenthesis.

When submitting bids, drawings, calculations, and other construction documents, use only U.S.

Customary units of measure, unless otherwise stated.

I. Project Location

General Location. The project work is located 6 miles southeast of Grangeville, ID in Idaho

County. Approximate Global Positioning System (GPS) coordinates for the beginning of the project are 43˚53’20.04”N, 116˚2’10.68”W.

Project Limits. Signs have not been erected to identify the project limits. No Government personnel will be available for show-me tours.

II. Pre-bid Information.

GENERAL AND TECHNICAL QUESTIONS REGARDING PROPOSED WORK FOR

THIS PROJECT WILL BE ACCEPTED UNTIL CLOSE-OF-BUSINESS ON 09/17/2024

October 1, 2024.

Refer to page A-5 for information on how to submit questions related to General Information and

Technical Information. Answers to General and Technical Questions will be posted at https://sam.gov/opp/696b60d6621d47ef92a04fa960820c06/view.

Every attempt to respond to questions will be made. However, response to questions received after the above posted date is not guaranteed.

Multiple Schedules. Bids for the construction of this project are being invited under two bid schedules, designated A and B. Schedule A and Schedule B are not alternate bids. Complete both schedules according to Subsection 102.02 of the special contract requirements. Award of the contract will be made according to Subsection 102.05A.

Electronic Plan Sheets. This solicitation includes electronic plan sheets available at https://sam.gov/opp/696b60d6621d47ef92a04fa960820c06/view.

Revised by Amendment A001 https://highways.dot.gov/federal-lands/specs https://sam.gov/opp/696b60d6621d47ef92a04fa960820c06/view https://sam.gov/opp/696b60d6621d47ef92a04fa960820c06/view

SOLICITATION, OFFER,

AND AWARD

2. TYPE OF SOLICITATION

6. PROJECT NO. 4. CONTRACT NO. 5. REQUISITION/PURCHASE REQUEST NO.

PAGE OF PAGES

7. ISSUED BY CODE

SOLICITATION

(Construction, Alteration, or Repair)

1. SOLICITATION NO. 3. DATE ISSUED

IMPORTANT -- The "offer" section on the reverse must be fully completed by offeror.

9.

INFORMATION

NOTE: In sealed bid solicitations "offer" and "offeror" mean "bid" and "bidder."

CALL:

FOR

SEALED BID (IFB)

NEGOTIATED (RFP)

Federal Highway Administration

FHWA WESTERN FED LANDS DIVISION

610 E FIFTH STREET

Vancouver WA 98661

690567 8. ADDRESS OFFER TO

Federal Highway Administration

FHWA WESTERN FED LANDS DIVISION

610 E FIFTH STREET

Vancouver WA 98661

a. NAME

ACQUISITIONS

b. TELEPHONE NO. (Include area code) (NO COLLECT CALLS)

360-619-7520

See Block 10 x69056724B000014

10. THE GOVERNMENT REQUIRES PERFORMANCE OF THE WORK DESCRIBED IN THESE DOCUMENTS (Title, identifying no., date)

This solicitation is designated ID FLAP IDAHO NF17(1), Mt. Idaho Grade Road

Rehabilitation

IN STRICT ACCORDANCE WITH:

Federal Acquisition Regulations (FAR) and Transportation Acquisition Regulations

(TAR)

General Wage Decision

Special Contract Requirements

Standard Specifications for Construction of Roads and Bridges on Federal Highway Projects, FP-14

11. The Contractor shall begin performance

12a. THE CONTRACTOR MUST FURNISH ANY REQUIRED PERFORMANCE AND PAYMENT BONDS?

award, notice to proceed. The performance period is mandatory negotiable. (See ________________________________________________.)

13. ADDITIONAL SOLICITATION REQUIREMENTS:

a. Sealed offers in original and is not required.is, b. An offer guarantee

c. All offers are subject to the (1) work requirements, and (2) other provisions and clauses incorporated in the solicitation in full text or by reference.

(date). If this is a sealed bid solicitation, offers will be publicly opened at that time. Sealed envelopes containing offers shall be marked to show the offeror's name and address, the solicitation number, and the date and time offers are due.

d. Offers providing less than

12b. CALENDAR DAYSYES NO

(If "YES", indicate within how many calendar days after award in Item 12b.)

10 calendar days and complete it within ________________ ________________ calendar days after receiving

* Page A-5

NSN 7540-01-155-3212

x x x x copies to perform the work required are due at the place specified in Item 8 by _____________ ___________________ (hour) local time calendar days for Government acceptance after the date offers are due will not be considered and will be rejected . _________________

STANDARD FORM 1442 (Rev. 4-85)

Prescribed by GSA

FAR(48 CFR) 53.236-1(d)

A-3

09/24/2024

08/21/2024

Revised by Amendment A001

10/08/2024 rebekah.webb Cross-Out

C-27

Contract Clauses Revised by Amendment A001

Project: ID FLAP IDAHO NF17(1), Mt. Idaho Grade Road Rehabilitation

(1) Determine if commercial products, commercial services, or, to the extent commercial products suitable to meet the agency’s needs are not available, nondevelopmental items are available that–

(i) Meet the agency’s requirements;

(ii) Could be modified to meet the agency’s requirements; or

(iii) Could meet the agency’s requirements if those requirements were modified to a reasonable extent; and

(2) Determine the extent to which commercial products, commercial services, or nondevelopmental items could be incorporated at the component level.

52.211-10 Commencement, Prosecution, and Completion of Work (Apr 1984) Alternate I

(Apr 1984)

The Contractor shall be required to (a) commence work under this contract within 10 calendar days after the date the Contractor receives the notice to proceed, (b) prosecute the work diligently, and (c) complete the entire work ready for use not later than 10/22/2025 for Schedule A and 11/14/2025 for Schedule B subject to such extensions as may be authorized. The time stated for completion shall include final cleanup of the premises.

The completion date is based on the assumption that the successful offeror will receive the notice to proceed by 11/15/2024 11/29/2024. The completion date will be extended by the number of calendar days after the above date that the contractor receives the notice to proceed, except to the extent that the delay in issuance of the notice to proceed results from the failure of the contractor to execute the contract and give the required performance and payment bonds within the time specified in the offer.

52.211-12 Liquidated Damages—Construction (Sep 2000)

(a) If the Contractor fails to complete the work within the time specified in the contract, the Contractor shall pay liquidated damages to the Government in the amount of: See Special Contract

Requirements, Subsection 108.04.

(b) If the Government terminates the Contractor’s right to proceed, liquidated damages will continue to accrue until the work is completed. These liquidated damages are in addition to excess costs of repurchase under the Termination clause.

52.211-18 Variation in Estimated Quantity (Apr 1984)

If the quantity of a unit-priced item in this contract is an estimated quantity and the actual quantity of the unit-priced item varies more than 15 percent above or below the estimated quantity, an equitable adjustment in the contract price shall be made upon demand of either party. The equitable adjustment shall be based upon any increase or decrease in costs due solely to the variation above 115 percent or below 85 percent of the estimated quantity. If the quantity variation is such as to cause an increase in the time necessary for completion, the Contractor may request, in writing, an extension of time, to be received by the Contracting Officer within 10 days from the beginning of the delay, or within such further period as may be granted by the Contracting Officer before the date of final settlement of the contract.

Upon the receipt of a written request for an extension, the Contracting Officer shall ascertain the facts and make an adjustment for extending the completion date as, in the judgment of the Contracting Officer, is justified.