Project Description MT FLAP DOT 236(2).pdf
PDF 152 KB Posted
- Attached to
- MT FLAP DOT 236(2), Winifred North Federal contract opportunity
- Solicitation number
- 69056724B000007
About this file
This document is a project description for a federal highway construction project in Fergus County, Montana. The MT FLAP DOT 236(2), Winifred North project involves 18.6 miles of road improvements northwest of Winifred, with an estimated budget between $5 and $10 million and a tentative completion date of Fall 2026. Project scope includes drainage work, subexcavation, roadway reconditioning, aggregate surfacing and stabilization, guardrail installation, cattle guard placement, and signage.
Specific project requirements include multiple construction divisions: Slope Reinforcement (30 cubic yards of Riprap), Aggregate and Base Courses (58,500 tons of untreated aggregate, 2,700 tons of minor crushed aggregate, 62,500 tons of stabilized aggregate surface), and Incidental Construction. The incidental construction tasks involve installing multiple pipe culverts (30-inch, 24-inch, and 54-inch sizes), cleaning and repairing existing drainage structures, installing guardrails, placing cattle guards, establishing turf, and implementing permanent and temporary traffic control measures. The project will require rental equipment and general labor, with provisions for topsoil placement and traffic control signage.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| Project Description MT FLAP DOT 236(2).pdf |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
MT FLAP DOT 236(2), Winifred North
This work consists of: Drainage, subexcavation, roadway reconditioning, aggregate surfacing, aggregate stabilization, guardrail, cattle guards, and signage.
Project Location: 4 miles NW of Winfred, Fergus County Montana
Project Length: 18.6 Miles
Estimated Price Range: Between $5 and $10 Million
Tentative Fixed Completion Date: Fall 2026
(Once solicitation is issued, see FAR Clause 52.211-10 for exact date.)
DIVISION 250 – Slope Reinforcement and Retaining Walls
251 Riprap Class 2 – 30 CUYD
DIVISION 300 – Aggregate and Base Courses
301 Untreated Aggregate Course 58500 TON
302 Minor Crushed Aggregate 2700 TON
303 Road Reconditioning 98208 LNFT
311 Stabilized Aggregate Surface Course Aggregate
62500 TON
Calcium Chloride
1115 TON
DIVISION 600 – Incidental Construction
602 Culverts & Drains (indicate one or both) 30-inch Pipe Culvert 56 LNFT 24-inch EQ DIA Arch Pipe Culvert
70 LNFT
54-inch EQ DIA Arch Pipe Culvert
70 LNFT
End Section 30-inch
2 EACH
End Section 24-inch EQ DIA Arch
Pipe
4 EACH
End Section 54-inch EQ DIA Arch Pipe
4 EACH
607 Cleaning, Relaying, & Repairing Existing Drainage Structures Cleaning 4 EACH Repairing 4 EACH
617 Guardrail Terminal Section MGS Tangent
12 EACH
Wood Post
100 EACH
Remove and Reset Guardrail
5325 LNFT
619 Fence, Gates & Cattle Guards 24-ft Cattle Guard
2 EACH
622 Rental Equipment (yes/no) Yes
623 General Labor (yes/no) Yes
624 Topsoil (landscaping & related items) 4-inch depth
700 SQYD
625 Turf Establishment (indicate seeding or mulching separately) 700 SQYD
633 Permanent Traffic Control – Sign System 496 SQFT
635 Temporary Traffic Control Barricade Type 3
6 EACH
Cone Type 36-inch
20 EACH
Drum
20 EACH
Construction Sign
267 SQFT
Flagger
1700 HOUR