QA 4.5.24.pdf
PDF 97 KB Posted
- Attached to
- MT FLAP PARK 34(2), Shields River Road Surface Improvement Federal contract opportunity
- Solicitation number
- 69056724B000004
About this file
This document contains Question and Answer responses related to the federal contract opportunity for the MT FLAP PARK 34(2), Shields River Road Surface Improvement project.
The key details are:
- The project has a current NTP of July 2024 and completion date of October 2024, which the contractor states does not provide enough time to obtain permits, open a gravel pit, crush material, and complete construction. The contractor requests an extension to allow for construction in 2025, but the government will not extend the fixed completion date.
- The contractor cannot locate the bid bond form and inquires if they should submit the AIA form instead. The government states this will be addressed in Amendment A001.
- The solicitation number is 69056724B000004 for the MT FLAP PARK 34(2), Shields River Road Surface Improvement project. It is an Invitation for Bids (IFB) for a construction project with 3 bid schedules, of which only 1 will be awarded. The opportunity is offered for full and open competition.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| Bid Tabulation_MT FLAP PARK 34(2).pdf | ||
| BidSum_MT FLAP PARK 34(2).pdf | ||
| Amendment A002.pdf | ||
| Amendment A001.pdf | ||
| QA 3.29.24.pdf | ||
| mta-park34-2_plans.pdf | ||
| mta-park34-2_Existing_Terrian_LIDAR-Feb2023.zip | ZIP file | |
| IFB_69056724B000004_MT FLAP PARK 34(2).pdf | ||
| mta-park34-2_control-points.xlsx | XLSX spreadsheet | |
| mta-park34-2_Shields River Road over Flathead MDT_Inspection_Report.pdf |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Project No. MT FLAP PARK 34(2) Project: Shields River Road Surface Improvement
# General Technical Question Answer Date
1 X
A NTP of July 2024 and completion date of October does not allow enough time to obtain the permitting needed, open a gravel pit, crush the material, and build the project. In addition, the 27 ton load limit on the bridge will contribute to slower production or if the contractor has to mitigate the bridge issue, permits with long lead times will be needed. With the current construction market and current contractor workloads, the late start time and early finish time will prevent this contractor and possibly several others from bidding the work which will eliminate much competition. Would the government please consider extending the completion date to allow for construction in 2025?
The Government will not be extending the Fixed Completion date for this project. Please bid accordingly.
3/29/24
2 X I am not finding the bid bond form to be completed for this project. Is this an oversight or should I just send our bonding company AIA form?
Please advise. Thanks, will be address under Amendment A001 4/5/24
Check General or Technical
File details come from the government source that posted it. Updated .