Amendment A004.pdf

PDF 116 KB Posted

Attached to
CO NP MULTI PMS(1) Pavement Preservation Colorado
Solicitation number
69056723R000003
Issued by

View the file

Other files

File Type Posted
QA_12-08-2022.pdf PDF
Amendment A003.pdf PDF
QA_12-07-2022.pdf PDF
Amendment A003.pdf PDF
QA_12-05-2022.pdf PDF
Amendment A002.pdf PDF
QA_12-01-2022.pdf PDF
Amendment A001.pdf PDF
QA_11-08-2022.pdf PDF
FINAL CO NP MULTI PMS(1) Final Plans_stamped_flatten_signed_09-13-2022.pdf PDF
CURE_C6_Final_Report.pdf PDF
GRSA_C6_Final_Report.pdf PDF
RFP 69056723R000003.pdf PDF
BEOL_C6_Final_Report.pdf PDF
FLH Bridge oversized or overload vehicle permit request form April 2019.pdf PDF
MEVE_C6_Final_Report.pdf PDF
Show all 16

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT

1. CONTRACT ID CODE

N/A

PAGE

2. AMENDMENT/MODIFICATION NO. 3. EFFECTIVE DATE 4. REQUISITION/PURCHASE NO. 5. PROJECT NO. (If applicable)

A004 12/08/2022 N/A See Block 14

6. ISSUED BY CODE N/A 7. ADMINISTERED BY (If other than Item 6) CODE N/A

Department of Transportation Federal Highway Administration 610 East Fifth Street Vancouver WA 98661-3801

8. NAME AND ADDRESS OF CONTRACTOR (No., street, county, State and Zip Code) 9A. AMENDMENT OF SOLICITATION NO.

X

69056723R000003

9B. DATED (SEE ITEM 11)

Nov. 02, 2022

10A. MODIFICATION OF CONTRACT/ORDER NO.

N/A

10B. DATED (SEE ITEM 13)

CODE: N/A FACILITY CODE: N/A

N/A

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

| X | The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers

(__ ) is extended, ( x ) is not extended.

Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods:

(a) By completing Items 8 and 15, and returning 1 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted; or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

12. ACCOUNTING AND APPROPRIATION DATA (If required)

N/A

13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS,

IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.

A THIS CHANGE ORDER IS ISSUED PURSUANT TO (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT ORDER NO. IN

ITEM 10A.

N/A

B THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (Such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).

C THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D OTHER (Specify type of modification and authority)

N/A

E. IMPORTANT: Contractor n/a is not, n/a is required to sign this document and return n/a copies to the issuing office.

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

CO NP MULTI PMS (1), Pavement Preservation Colorado

SPECIAL CONTRACT REQUIREMENTS

Page E-45, Subsection 156.09, Traffic Control Supervisor. Add to the first sentence.

ENCLOSURES

Pages: E-45

Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

15a. NAME AND TITLE OF SIGNER (Type or print) 15a. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)

N/A

15B. CONTRACTOR/OFFEROR 15C. DATE SIGNED 16B. UNITED STATES OF AMERICA 16C. DATE SIGNED

BY_________________________________________ BY N/A___________________________ N/A (Signature of person authorized to sign) (Signature of Contracting Officer)

NSN 7540-01-152-8070

PREVIOUS EDITION NOT USABLE

30-105 STANDARD FORM 30 (REV. 10-83)

Prescribed by GSA

FAR (48 CFR) 53.243

E-45 DIVISION 150

Special Contract Requirements Project: CO NP MULTI PMS (1), Pavement Preservation Colorado

156.09 Traffic Control Supervisor. Amend as follows:

Add the following to the first sentence:

Provide a separate traffic control supervisor while performing work simultaneously within two separate parks.

Add the following:

(l) Transport personnel, construction signs, barricades, drums, cones, tubular markers, and other traffic control devices.

(m) Prepare a Traffic Control Plan (TCP) to ensure safe and efficient pedestrian, bicycle, and vehicular circulation (including Park operations and emergency vehicles) during construction.

Determine phasing and sequencing of signage to route visitors around construction areas and to day-use parking and other appropriate locations. Provide a description of how pedestrians and bicyclists, and safe vehicle passage is provided through the use of signs, flaggers, and pilot cars. Address access for emergency vehicles, police, school buses, rangers, fire, and disaster units. Include closures of trails to public access in the TCP. Submit plan for CO and Park review and approval 14 days prior to any construction activities impacting public traffic.

Maintain and update the TCP throughout the duration of the project and at the request of the CO. Coordinate the TCP with the written construction schedule.

(n) Keep Park visitors out of active construction areas and in designated public pathways.

(o) The traffic control supervisor will not be permitted to operate a pilot car, work as a flagger, laborer, or operator, except to relieve flaggers or pilot car drivers for short periods of time (i.e.

a lunch or rest room break), but will be onsite and available at all times to perform the duties as described in this section.