QA_01-26-22.pdf

PDF 426 KB Posted

Attached to
MT PRA GLAC 10(44), Lake McDonald Utility Relocation
Solicitation number
69056721R000012
Issued by

About this file

This document contains technical questions and answers related to solicitation number 69056721R000012 from the Department of Transportation Federal Highway Administration for utility relocation work at Lake McDonald in Montana. The solicitation involves replacing lift stations and installing new utility lines at Lake McDonald and Sprague Creek. Key details include questions regarding bid due dates and times, specifications for roofing and electrical work, maintaining existing power during construction, confined space entry requirements, directional drilling allowances, and responsibility for replacing the transformer at the Lake McDonald lodge lift station. The response date for bids was extended to February 4th, 2022 with no further extensions planned.

View the file

Other files

File Type Posted
QA_02-02-22.pdf PDF
QA_01-31-22.pdf PDF
QA_01-25-22.pdf PDF
Amendment A004.pdf PDF
QA_01-21-22.pdf PDF
QA_01-20-22.pdf PDF
Amendment A003.pdf PDF
QA_01-10-22.pdf PDF
QA_01-04-22.pdf PDF
QA_12-30-21.pdf PDF
Amendment A002.pdf PDF
Amendment A001.pdf PDF
glac01044_ExistingGroundSurface.zip ZIP file
Asbestos Bldg 1359 Lake McDonald Lift Station.pdf PDF
19126788-R-Rev0-RPA GNP Lk McDonald Rpt-04172020.pdf PDF
MT_CompiledSWPPP_Final.pdf PDF
Asbestos Bldg 1305 Apgar Lift Station.pdf PDF
AsBuilts_GNP WW Fac_Lk McDonald_Sheets 11-20.pdf PDF
AsBuilts_GNP WW Fac_Lk McDonald_Sheets 31-40.pdf PDF
AsBuilts_GNP WW Fac_Lk McDonald_Sheets 41-50.pdf PDF
Bus Bay Dimension.pptx PPTX presentation
AsBuilts_GNP WW Fac_Lk McDonald_Sheets 61-70.pdf PDF
AsBuilts_GNP WW Fac_Lk McDonald_Sheets 21-30.pdf PDF
RFP_Lake McDonald.pdf PDF
glac01044_Plans_FINAL 9_27_21.pdf PDF
AsBuilts_GNP WW Fac_ Lk McDonald_Sheets 01-10.pdf PDF
glac01044_ControlSheets.pdf PDF
FLH Bridge Oversized-Overweight Permit Load Request.pdf PDF
Asbestos Bldg 1055 Sprague Crk Lift Station.pdf PDF
AsBuilts_GNP WW Fac_Lk McDonald_Sheets 71-77.pdf PDF
Show all 30

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Project No.: MT GLAC 10(44) Project: Lake McDonald Utility Relocation

# General Technical Question Answer Date

1 X SAM web page Solicitation# 69056721R000012 lists Monday January 24th, 2PM EST. Solicitation page A3 lists Monday January 24th 2PM local time for Vancouver, WA. Please clarify which time is correct.

The correct due date and time is PST. This has been updated and also shown in the description section of SAM.gov along with Amendment A001.

30-Dec-21

2 X Also the link from the emails for project updates directs to Solicitation#69056722R000001 instead of the solicitation number noted above. We have to click on the link under History to go to Solicitation #69056721R000012. Which solicitation number are we to reply to?

The solicitation number is 69056721R000012. This will be address in Amendment A001 30-Dec-21

3 X When reviewing this project I noticed that the roofing you have specified is wood sake. For past projects, we have found that EcoStar has been a great alternative that has brought some great value to property owners. I have included a copy of some information regarding the product.

Please let us know if you would like a quote for this product on this project.

Please submit bids according to the solicitation documents. 3-Jan-22

4 X Would the government please extend the bid date for the above project by two weeks to cover the difficulty of trying to reach people concerning the above project before and during the Holidays.

This will be addressed under amendment A002 4-Jan-22

5 X Is the Subcontracting Plan required to be submitted with the RFP bid proposal or only required to be submitted to the government prior to contract award?

The successful offeror will be required to submit a Subcontracting plan prior to contract award.

See Page B-20 and B-21 for proposal submittal requirements.

4-Jan-22

6 X At cabin #1105 Plan sheet C.2 details new underground electrical from cabin to lift station. Would it be possible to continue to use the existing overhead feed rout from the cabin electrical panel to the existing O/H pole adjacent to the current lift station. This would eliminate removing concrete and rock walls to run underground from cabin to the existing lift station.

will be addressed under future amendment 10-Jan-22

7 X

At cabin #1106 the existing conductor appears to be direct burial UF cable. Plan sheet C.2 details this cable is to be replaced with UG conduit and new conductors. New installation may require removing some concrete, trees, and roots to trench in. The existing electrical panel is on the opposite side of the cabin than the lift station adjacent to the road. Is overhead an option from the cabin to the existing lift station? If not, is it acceptable to remove trees and roots to accommodate trench for new conduit run?

will be addressed under future amendment 10-Jan-22

8 X Utility Power at Lake McDonald. Will the power to the existing chlorination building need to be maintained until the new lift station building is completed? Chlorination building currently appears to be fed from the existing lift station building to be replaced

Power will not need to be maintained for the Chlorination building or the existing lift station.

Please bid accordingly

10-Jan-22

9 X Utility Power at Sprague Creek. Will power need to be maintained to existing building until new power lines are completed? Depending on time frame could cold weather freezing and damage existing systems remaining in place?

Power will not need to be maintained to existing building. Please bid accordingly. 10-Jan-22

10 X Are the Sprague Creek lift station building lower level and the Apgar Bio Filter Fan Replacement vault considered confined space entry locations. Yes they are both considered confined spaces. Please bid accordingly. 10-Jan-22

11 X Please refer to note #2 on page F.3 for the Sprague Creek Lift Station work.

Instructions mention to “All wiring and conduit to be removed and disposed of from basement.” Does this include lighting, switches, receptacles, conduit, gutters, conductor and such or is it just related to the equipment to be removed

Will be addressed under future amendment A004 20-Jan-22

12 X

Please refer to the “Existing Transformer Preserve and Protect” note on page D.35 of the Lake McDonald Lift Station site work.

The existing building is 240V and the new building is to be fed 480V. If the existing transformer needs to be replaced who is responsible?

Yes, a new 480v 3 phase service is required for the Lake McDonald Lift Station. This will be the responsibility of the contractor to work with Flathead Electric to upgrade the service and costs that occur with the upgrade will be the responsibility of the contractor. Government. Please bid accordingly

1/20/2022 revised 1/26/22

13 X Would the contractor be able to directional drill the entire main pipeline as means of installation? As long as the directional drilling meets the requirements of Subsection 612.04A(g). 21-Jan-22

14 X

Please send plan holders list for this project. Obtain the registered vendors list (aka plan holders list) for this project as follows. Register in sam.gov and link your entity to your registration. After doing this, log into sam.gov to find the interested vendors list under this announcement. Contact the Federal Service Help Desk if you experience further issues

24-Jan-22

15 X Is the bid date for this project expected to be extended? Originally this was bidding after the Going to the Sun Final Phase project. Amendment A002 has extended the request for proposal date for this project to February 4, 2022; and the Government does not intend to extend the request for proposal beyond this date.

25-Jan-22

16 X

Regarding item #12 transformer replacement at Lake McDonald Lodge lift station. Flathead Electric Coop has not been contacted by anyone regarding this work. They do not have a work order and will not be able to provide any costs by bid time. FEC Representative advised a work order will need to be submitted and a site visit performed before they prepare any costs. Will owner assume submitting the work order, pay the FEC costs direct to FEC, and remove this responsibility from the contractor?

Question 12 from above:

Please refer to the “Existing Transformer Preserve and Protect” note on page D.35 of the Lake McDonald Lift Station site work.

The existing building is 240V and the new building is to be fed 480V. If the existing transformer needs to be replaced who is responsible?

Yes, a new 480v 3 phase service is required for the Lake McDonald Lift Station. This will be the responsibility of the contractor to work with Flathead Electric to upgrade the service and costs that occur with the upgrade will be the responsibility of the contractor. Government. Please bid accordingly

26-Jan-22

Check General or Technical