QA_01-04-22.pdf

PDF 99 KB Posted

Attached to
MT PRA GLAC 10(44), Lake McDonald Utility Relocation
Solicitation number
69056721R000012
Issued by

About this file

This document contains technical questions and answers related to solicitation number 69056721R000012 from the Department of Transportation Federal Highway Administration for utility relocation services along Lake McDonald in Montana. The solicitation involves relocating utilities to accommodate a highway construction project. Key details include clarification that the bid due date is January 24th at 2PM Pacific Time, identification of the correct solicitation number as 69056721R000012, and requirements for submitting bids according to the solicitation documents and any subcontracting plans with awarded proposals. Offerors were also provided two additional weeks to submit bids due to holiday scheduling difficulties. The questions and answers help ensure offerors clearly understand the bid requirements and timeline for the utility relocation opportunity.

View the file

Other files

File Type Posted
QA_02-02-22.pdf PDF
QA_01-31-22.pdf PDF
QA_01-26-22.pdf PDF
QA_01-25-22.pdf PDF
Amendment A004.pdf PDF
QA_01-21-22.pdf PDF
QA_01-20-22.pdf PDF
Amendment A003.pdf PDF
QA_01-10-22.pdf PDF
QA_12-30-21.pdf PDF
Amendment A002.pdf PDF
Amendment A001.pdf PDF
glac01044_ExistingGroundSurface.zip ZIP file
Asbestos Bldg 1359 Lake McDonald Lift Station.pdf PDF
19126788-R-Rev0-RPA GNP Lk McDonald Rpt-04172020.pdf PDF
MT_CompiledSWPPP_Final.pdf PDF
Asbestos Bldg 1305 Apgar Lift Station.pdf PDF
AsBuilts_GNP WW Fac_Lk McDonald_Sheets 11-20.pdf PDF
AsBuilts_GNP WW Fac_Lk McDonald_Sheets 31-40.pdf PDF
AsBuilts_GNP WW Fac_Lk McDonald_Sheets 41-50.pdf PDF
Bus Bay Dimension.pptx PPTX presentation
AsBuilts_GNP WW Fac_Lk McDonald_Sheets 61-70.pdf PDF
AsBuilts_GNP WW Fac_Lk McDonald_Sheets 21-30.pdf PDF
RFP_Lake McDonald.pdf PDF
glac01044_Plans_FINAL 9_27_21.pdf PDF
AsBuilts_GNP WW Fac_ Lk McDonald_Sheets 01-10.pdf PDF
glac01044_ControlSheets.pdf PDF
FLH Bridge Oversized-Overweight Permit Load Request.pdf PDF
Asbestos Bldg 1055 Sprague Crk Lift Station.pdf PDF
AsBuilts_GNP WW Fac_Lk McDonald_Sheets 71-77.pdf PDF
Show all 30

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Project No.: MT GLAC 10(44) Project: Lake McDonald Utility Relocation

# General Technical Question Answer Date

1 X SAM web page Solicitation# 69056721R000012 lists Monday January 24th, 2PM EST.

Solicitation page A3 lists Monday January 24th 2PM local time for Vancouver, WA.

Please clarify which time is correct.

The correct due date and time is PST. This has been updated and also shown in the description section of SAM.gov along with Amendment A001.

30‐Dec‐21

2 X

Also the link from the emails for project updates directs to Solicitation#69056722R000001 instead of the solicitation number noted above. We have to click on the link under History to go to Solicitation #69056721R000012.

Which solicitation number are we to reply to?

The solicitation number is 69056721R000012. This will be address in Amendment A001 30‐Dec‐21

3 X

When reviewing this project I noticed that the roofing you have specified is wood sake. For past projects, we have found that EcoStar has been a great alternative that has brought some great value to property owners. I have included a copy of some information regarding the product. Please let us know if you would like a quote for this product on this project.

Please submit bids according to the solicitation documents. 3‐Jan‐22

4 X Would the government please extend the bid date for the above project by two weeks to cover the difficulty of trying to reach people concerning the above project before and during the Holidays.

This will be addressed under amendment A002 4‐Jan‐22

5 X Is the Subcontracting Plan required to be submitted with the RFP bid proposal or only required to be submitted to the government prior to contract award?

The successful offeror will be required to submit a Subcontracting plan prior to contract award.

See Page B‐20 and B‐21 for proposal submittal requirements.