QA_02-17-2022.pdf
PDF 94 KB Posted
- Solicitation number
- 69056721R000007
View the file
Other files
| File | Type | Posted |
|---|---|---|
| A002 REVISED.pdf | ||
| Amendment A002.pdf | ||
| Amendment A001.pdf | ||
| SEQU_C6_Final_Report.pdf | ||
| KICA_C6_Final_Report.pdf | ||
| 1_nps_pp_seki_2018(3)_2020(1)_ph1_2_final_plans_sheets2-79_signed_07-08-2021.pdf | ||
| CA NPS PP RFP .pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
CA NPS PP SEKI 2018(3) & CA NPS PP SEKI 2020(1
Pavement Preservation SEKI Phase I & Pavement Preservation SEKI Phase II
# General Technical Question Answer Date
1 X
“Limit construction caused delays to public traffic to a maximum of 30 minutes per cumulative passge through the project…”
Can you please determine what the cumulative passage consists of? Are Route 0010 and 0011 considered cumulative route of travel?
All routes that have construction being performed upon are considered to be part of the cumulative route of travel.
2/17/2022