Q&A_10-17-19.pdf

PDF 59 KB Posted

Attached to
NV NPS PP LAKE 2019(1), Pavement Preservation Lake Mead Phase 2
Solicitation number
69056719R000019
Issued by

View the file

Other files

File Type Posted
Q&A_10-21-19.pdf PDF
Q&A_10-07-19.pdf PDF
RFP.pdf PDF
LAKE_C6_RipReport.pdf PDF
PROJECT_DESCRIPTION.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

NV NPS PP LAKE 2019(1)

Pavement Preservation Lake Mead Phase 2

# General Technical Question Answer Date

1 X RE: Subsection 152.05(m), Can a GPS be used to conduct the road width survey?

See Subsections 152.01 and 152.02(b). 10/7/19

2 X

RE: Section 108.01(f), Are the limited work hours for the entire project including parking lot areas (ie; Section 634 ‐ applying first application of Permanent Pavement Markings prior to opening the parking lot to traffic) or is the intent of this subsection for mainline operations only?

Subsection 108.01(f) is a limitation for the entire project.

10/7/19

3 X

RE: Section 108.01(g), Can the Contractor submit a blanket request to work all Saturdays and Sundays for the duration of the project at the pre‐con or will the Contractor be required to make incremental requests to work each weekend in two‐week increments?

You may submit blanket requests, but blanket requests do not relieve the contractor of the requirements to provide a 14‐day advance notice for work schedule changes that include additional shifts; as well as, the requirements of Subsection 108.01(g) and Section 155.

10/7/19

4 X Does FAR Clause 52.236‐17 apply to SCR 152.01?

FAR Clause 52.236‐17 applies to anything associated with Layout of Work.

10/15/19

5 X Is the Contractor financially responsible for shipping samples, when required, to the address shown in SCR 154.03?

Sending Vancouver Laboratory required samples is a part of the contract work required under Subsection 154.03, that would be paid for under Subsection 109.05.

10/15/19

Check General or Technical

6 X

SCR Subsection 105.04(a) states staging is available at numerous large parking areas within the park; so which large parking areas are available to the contractor for Stockpile and storage use at the following areas:

Area 1: Is the dirt parking lot located on the South West of the intersection of Colorado Street and Birch St. available for use?

Area 3: Is the mixing table located at mile 13 on the South side of Route 0116 Temple Bar Access Road available for use?

Area 4: Is the large dirt parking lot located in between/to South West of Routes 0268 and 510 Temple Bar Dry Boat Storage Road available for use?

Area 5: Is the mixing table located at mile 5.5 on the West side of Route 115 Pearce Ferry road available for use?

Area 8: Is the gravel parking lot adjacent to the West of Route 994AZ Princess Cove Parking Area A, and off of Route 300 Princess Cove Road, available for use?

Area 9: Is the NPS Maintenance area/pit located at the end of Route 209 Katherine South Campground Road available for use?

Specific stockpile and storage sites have not been identified in the contract. Note that Subsection 105.04(a) also says to use parking areas within the project limits, as approved by the CO, so follow the requirements of Subsection 105.02(c) and

105.04 as applicable for use of these sites.