This document describes a federal highway resurfacing project in Oregon. The project involves resurfacing 19.47 miles of state highway 204 between Weston and Elgin, Oregon with hot asphalt concrete pavement, guardrail repairs, and surface treatment improvements to three snow parks. Estimated pricing for the work ranges from $7 million to $10 million. The tentative completion date is Fall 2020. Additional details include milling, asphalt tack coat, chip sealing, temporary traffic control requirements, and permanent pavement markings. The solicitation will be set aside for small businesses. Preliminary project plans and additional information are available electronically, and interested vendors should register for notification when the solicitation is formally issued. The federal Department of Transportation and Federal Highway Administration are the agencies involved.

Project Description

View the file

Other files for this federal contract opportunity

Other files attached to OR DOT 204(1), Weston-Elgin Highway Resurfacing, newest first.
File Type Posted
Prelim_Pre-Ad_Letter_Weston-Elgin_2019.pdf PDF
OR2041_pre-AD_Weston-Elgin_Plans.pdf PDF

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

OR DOT 204(1), Weston-Elgin Highway Resurfacing, Union and Umatilla, Oregon.

The work consists of Hot asphalt concrete paving, guardrail, chip seal, striping, milling and other small items of work.

Project length: 19.47 Miles

Tentative Fixed Completion Date: Summer 2020 (Once solicitation is issued, see FAR Clause 52.211-10 for exact date.)

Estimated Price Range: $7 million to $10 million

Location: 0 to 20 Miles East of Elgin, OR.

DESCRIPTION OF WORK in US CUSTOMARY UNITS

FP-14

On e S ch ed ul e

Sc h

A

Ad di tio na l S ch

Sc h B

DIVISION 150 – Project Requirements 152 Construction Survey & Staking (yes/no) Yes Yes 153 Contractor Quality Control and Assurance

(yes/no) Yes Yes 154 Contractor Sampling & Testing (yes/no) Yes Yes 155 Schedules for Construction Contracts (construction schedules) (yes/no) Yes Yes 157 Soil Erosion & Sediment Control (erosion control devices) LS LS

DIVISION 200 – Earthwork 203 Removal of Structures & Obstructions (Guardrail) 1988 LF 1988 LF 207 Earthwork Geosynthetics 2290 SY 2290 SY

On e S ch ed ul e

Sc h

A

Ad di tio na l S ch

Sc h B

DIVISION 300 – Aggregate and Base Courses 302 Minor Crushed Aggregate (Govt furnished) 750 CY 750 CY 302 Minor Crushed Aggregate shldr finishing 189900 LF 206700 LF DIVISION 400 – Asphalt Pavements & Surface Treatments 401 Asphalt Concrete Pavement By Gyratory Mix Design Method 36450 Ton 39160 Ton 406 Fog Seal 30 Ton 30 Ton 407 Chip Seal 46050 SY 46050 SY 412 Asphalt Tack Coat (asphalt surface treatment) 135 Ton 145 Ton 413 Asphalt Pavement Milling 233110 SY 233110 SY 414 Asphalt Pavement Crack Sealing & Filling 12,500 LF 12,500 LF 418 Asphalt Concrete Pavement Patching 1180 SY 1180 SY

DIVISION 600 – Incidental Construction 617 Guardrail System MGS 1988 LF 1988 LF 617 Guardrail Terminal Sections 21 EA 21 EA 617 Guardrail replacement posts 65 EA 65 EA 617 Guardrail blockouts 123 EA 123 EA 617 Raising guardrail 7475 LF 7475 LF 634 Permanent Pavement Markings (traffic pavement markings) 725,485 LF 790,318 LF 635 Temporary Traffic Control – Flagger 600 HR 660 HR 635 Temporary Traffic Control – Pilot Car 30 Day 33 Day 635 Temporary Traffic Control – Markings 190000 LF 206000 LF 635 Temporary Traffic Control – TCSupervisor 65 Day 70 Day 635 Temporary Traffic Control – Signs 766 SF 766 SF 635 Temporary Traffic Control – Tubular markers 60 60