Q&A_11-7-17.pdf
PDF 76 KB Posted
- Attached to
- CA NPS PP DEVA 2016(8), Pavement Preservation Death Valley Phase I Federal contract opportunity
- Solicitation number
- 69056718B000001
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| Bid_Opening_Summary_Death_Valley.pdf | ||
| A004.pdf | ||
| A003.pdf | ||
| Q&A_11-8-17.pdf | ||
| Q&A_11-1-17.pdf | ||
| A002.pdf | ||
| Q&A_10-30-17.pdf | ||
| Q&A_10-20-17.pdf | ||
| A001.pdf | ||
| IFB_Death_Valley.pdf | ||
| DEVA_C6_RipReport.pdf | ||
| CA_Death_Valley_PROJECT_DESCRIPTION.pdf |
Show all 12
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
CA NPS PP DEVA 2016(8)
Pavement Preservation Death Valley Phase 1
# General Technical Question Answer Date 1 X I am requesting the reason for requiring a
Continuous operation, rather than Truck Mounted Units which are more suitable for this project.
This will be addressed in a forthcoming amendment.
10/20/17
2 X
On the cover it has the project is a Small Business Set‐Aside but on page A‐2 it talks about a price preference applied to large businesses. Is the project a small business set‐ aside?
This project is a small business set-aqside.
The price evaluation paragraph was included on page A-2 by mistake and will be removed in a future amendment.
10/27/17
X
Please Consider the equipment specification to be ISSA A-143 deleting the requirement for the self-loading machine.
Amendment A001 changed the equipment requirements for Micro Surfacing.
10/30/17
X The given quantities for the center line striping are for yellow paint only, will FHWA require black paint in‐between the yellow center line?
No. See pavement marking details on F sheets.
11/1/17
5 X
Will hauling of aggregate be allowed on Stateline Rd.‐Bob Rund Memorial Hwy‐Bell Vista Rd.? There are signs not allowing trucks over 13 tons to haul on this Route.
Comply with legal load restrictions. Please refer to Subsection 104.05 Load Restrictions.
11/1/17
Check General or Technical
6 X
My question is: the portable changeable message signs will be removed from the project once construction is complete correct? Or are the portable changeable message signs designed to be given to the park once construction is complete?
Remove once construction is complete.